| 1.4 Interior Budgets | |
| . | |
| 649. STB Main Foyer | |
| |
| Department Summary |
|
| Code | Depatment | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| | | 1,008h | . | . | . | : | . |
| | 007. Furniture Maker | 240h | . | . | . | . | . |
| | 008. Interior Painting | 272h | . | . | . | . | . |
| | 009. Fit-Out Carpentry | 208h | . | . | . | . | . |
| | 012. Electrical | 88h | . | . | . | . | . |
| | 013. Decor Carpentry | 40h | . | . | . | . | . |
| | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
| Finishes |
|
| Code | Finishes | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| | 023. Lighting/Fixtures | | . | . | . | : | . |
| | 035. Stainless Steel | 160h | . | . | . | : | . |
| | | | | | | | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
| Code | Job Assignment | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 6 | INTERIOR | 1,008 | 07/21/26 | 08/18/26 | $4w | : | |
| 648 | Port Main Foyer | 504 | 08/06/26 | 08/18/26 | $2w | : | |
| 648-07 | Furniture Maker | 120 | 08/07/26 | 08/18/26 | $2w | : | |
| 648-07-01 | Stairway/ Walls (P) | 60 | 08/07/26 | 08/18/26 | $60h | : | |
| 648-07-02 | Stairway/ Walls (S) | 60 | 08/07/26 | 08/18/26 | $60h | : | |
| 648-08 | Interior Painting | 136 | 08/06/26 | 08/18/26 | $68h | : | |
| 648-08-01 | Walls (P) | 68 | 08/06/26 | 08/18/26 | $68h | : | |
| 648-08-02 | Walls (S) | 68 | 08/06/26 | 08/18/26 | $68h | : | |
| 648-09 | Carpentry | 104 | 08/12/26 | 08/18/26 | $40h | : | |
| 648-09-01 | Wall (P) | 40 | 08/12/26 | 08/18/26 | $40h | : | |
| 648-09-02 | Wall (S) | 40 | 08/12/26 | 08/18/26 | $40h | : | |
| 648-09-03 | Flooring (P) | 12 | 08/14/26 | 08/18/26 | $18h | : | |
| 648-09-04 | Flooring (S) | 12 | 08/14/26 | 08/18/26 | $18h | : | |
| 648-12 | Electrical | 44 | 08/17/26 | 08/18/26 | $0w | : | |
| 648-12-01 | Rough in (P) | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 648-12-02 | Rough in (S) | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 648-12-03 | Intsall/ Connect (P) | 6 | 08/18/26 | 08/18/26 | $6h | : | |
| 648-12-04 | Intsall/ Connect (S) | 6 | 08/18/26 | 08/18/26 | $6h | : | |
| 648-12-05 | Finish trims (P) | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 648-12-06 | Finish trims (S) | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 648-13 | Decor Carpentry | 100 | 08/13/26 | 08/18/26 | $32h | : | |
| 648-13-01 | Fabric (P) | 10 | 08/17/26 | 08/18/26 | $10h | : | |
| 648-13-02 | Fabric (S) | 10 | 08/17/26 | 08/18/26 | $10h | : | |
| 648-13-03 | Guardrail | 40 | 08/13/26 | 08/18/26 | $32h | : | |
| 648-13-04 | Handrail | 40 | 08/13/26 | 08/18/26 | $32h | : | |
| 649 | STBD Main Foyer | 504 | 08/06/26 | 08/18/26 | $2w | : | |
| 649-07 | Furniture Maker | 120 | 08/07/26 | 08/18/26 | $2w | : | |
| 649-07-01 | Stairway/ Walls (P) | 60 | 08/07/26 | 08/18/26 | $60h | : | |
| 649-07-02 | Stairway/ Walls (S) | 60 | 08/07/26 | 08/18/26 | $60h | : | |
| 649-08 | Interior Painting | 136 | 08/06/26 | 08/18/26 | $68h | : | |
| 649-08-01 | Walls (P) | 68 | 08/06/26 | 08/18/26 | $68h | : | |
| 649-08-02 | Walls (S) | 68 | 08/06/26 | 08/18/26 | $68h | : | |
| 649-09 | Carpentry | 104 | 08/12/26 | 08/18/26 | $40h | : | |
| 649-09-01 | Wall (P) | 40 | 08/12/26 | 08/18/26 | $40h | : | |
| 649-09-02 | Wall (S) | 40 | 08/12/26 | 08/18/26 | $40h | : | |
| 649-09-03 | Flooring (P) | 12 | 08/14/26 | 08/18/26 | $18h | : | |
| 649-09-04 | Flooring (S) | 12 | 08/14/26 | 08/18/26 | $18h | : | |
| 649-12 | Electrical | 44 | 08/17/26 | 08/18/26 | $0w | : | |
| 649-12-01 | Rough in (P) | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 649-12-02 | Rough in (S) | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 649-12-03 | Intsall/ Connect (P) | 6 | 08/18/26 | 08/18/26 | $6h | : | |
| 649-12-04 | Intsall/ Connect (S) | 6 | 08/18/26 | 08/18/26 | $6h | : | |
| 649-12-05 | Finish trims (P) | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 649-12-06 | Finish trims (S) | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 649-13 | Decor Carpentry | 100 | 08/13/26 | 08/18/26 | $32h | : | |
| 649-13-01 | Fabric (P) | 10 | 08/17/26 | 08/18/26 | $10h | : | |
| 649-13-02 | Fabric (S) | 10 | 08/17/26 | 08/18/26 | $10h | : | |
| 649-13-03 | Guardrail | 40 | 08/13/26 | 08/18/26 | $32h | : | |
| 649-13-04 | Handrail | 40 | 08/13/26 | 08/18/26 | $32h | : | |
| | | | | | | | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
|
|
|