| Code | Finishes | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| | 020. TV Audio | | . | . | . | : | . |
| | 023. Lighting/Fixtures | | . | . | . | : | . |
| | 027. Flooring | | . | . | . | : | . |
| | 061, Window Treatment | | . | . | . | : | . |
| | 085, Upholstery | | . | . | . | : | . |
| | 087. Appliances | | . | . | . | : | . |
| | | | | | | | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
| Code | Job Assignment | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 6 | INTERIOR | 1,460 | 07/21/26 | 08/18/26 | $4w | : | |
| 652 | Main Salon | 1,460 | 07/27/26 | 08/18/26 | $3w | : | |
| 652-07 | Furniture Maker | 304 | 08/06/26 | 08/18/26 | $2w | : | |
| 652-07-01 | Ship side fwd Cabinet (S) | 56 | 08/10/26 | 08/18/26 | $56h | : | |
| 652-07-02 | Ship side aft Cabinet (S) | 56 | 08/10/26 | 08/18/26 | $56h | : | |
| 652-07-05 | Walls | 68 | 08/06/26 | 08/18/26 | $68h | : | |
| 652-07-06 | Windows | 68 | 08/06/26 | 08/18/26 | $68h | : | |
| 652-07-07 | Aft Windows | 56 | 08/10/26 | 08/18/26 | $56h | : | |
| 652-08 | Interior Painting | 192 | 08/10/26 | 08/18/26 | $1w | : | |
| 652-08-01 | Ship side fwd Cabinet (S) | 44 | 08/11/26 | 08/18/26 | $44h | : | |
| 652-08-02 | Ship side aft Cabinet (S) | 44 | 08/11/26 | 08/18/26 | $44h | : | |
| 652-08-05 | Walls | 48 | 08/11/26 | 08/18/26 | $48h | : | |
| 652-08-06 | Windows | 56 | 08/10/26 | 08/18/26 | $56h | : | |
| 652-09 | Carpentry | 392 | 07/27/26 | 08/18/26 | $3w | : | |
| 652-09-01 | Room Framing | 64 | 08/07/26 | 08/18/26 | $64h | : | |
| 652-09-02 | AC Plenum | 40 | 08/12/26 | 08/18/26 | $40h | : | |
| 652-09-03 | Ship side fwd Cabinet (S) | 36 | 08/12/26 | 08/18/26 | $36h | : | |
| 652-09-04 | Ship side aft Cabinet (S) | 36 | 08/12/26 | 08/18/26 | $36h | : | |
| 652-09-07 | TV Cabinet (Ceiling) | 16 | 08/17/26 | 08/18/26 | $16h | : | |
| 652-09-08 | Wall | 72 | 08/06/26 | 08/18/26 | $72h | : | |
| 652-09-09 | Windows | 32 | 08/13/26 | 08/18/26 | $32h | : | |
| 652-09-10 | Aft Windows | 20 | 08/14/26 | 08/18/26 | $20h | : | |
| 652-09-11 | Ceiling | 72 | 07/27/26 | 08/18/26 | $130h | : | |
| 652-09-12 | Trim | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 652-10 | Plumbing | 20 | 08/14/26 | 08/18/26 | $1w | : | |
| 652-10-02 | Air Condtioning | 20 | 08/14/26 | 08/18/26 | $20h | : | |
| 652-12 | Electrical | 180 | 07/28/26 | 08/18/26 | $3w | : | |
| 652-12-01 | Rough-in Circuits | 72 | 08/06/26 | 08/18/26 | $72h | : | |
| 652-12-02 | Install/Connect | 56 | 08/10/26 | 08/18/26 | $56h | : | |
| 652-12-03 | TV/Audio | 48 | 08/13/26 | 08/18/26 | $28h | : | |
| 652-12-04 | Finish Trim | 4 | 07/28/26 | 08/18/26 | $124h | : | |
| 652-13 | Decor Carpentry | 372 | 07/29/26 | 08/18/26 | $3w | : | |
| 652-13-01 | Window treatments | 24 | 08/14/26 | 08/18/26 | $24h | : | |
| 652-13-02 | Upholstery | 80 | 08/05/26 | 08/18/26 | $80h | : | |
| 652-13-03 | Fabics | 28 | 08/13/26 | 08/18/26 | $28h | : | |
| 652-13-04 | Countertops | 120 | 07/29/26 | 08/18/26 | $120h | : | |
| 652-13-05 | Flooring | 120 | 07/29/26 | 08/18/26 | $120h | : | |
| | | | | | | | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |