| 1.4 Interior Budgets | |
| . | |
| 635. Crew Laundry | |
| |
| Department Summary |
|
| Code | Depatment | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| | | 352h | . | . | . | : | . |
| | 007. Furniture Maker | 72h | . | . | . | . | . |
| | 008. Interior Painting | 28h | . | . | . | . | . |
| | 009. Fit-Out Carpentry | 148h | . | . | . | . | . |
| | 010. Plumbing | 12h | . | . | . | . | . |
| | 011. Mechanical | 12h | . | . | . | . | . |
| | 012. Electrical | 48h | . | . | . | . | . |
| | 013. Decor Carpentry | 32h | . | . | . | . | . |
| | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
| Finishes |
|
| Code | Finishes | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| | 023. Lighting/Fixtures | | . | . | . | : | . |
| | 027. Flooring | | . | . | . | : | . |
| | 030. Wall Covering | | . | . | . | : | . |
| | 085, Upholstery | | . | . | . | : | . |
| | 087. Appliances | | . | . | . | : | . |
| | | | | | | | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
| Code | Job Assignment | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 6 | INTERIOR | 352 | 07/21/26 | 08/18/26 | $4w | : | |
| 635 | Laundry | 352 | 08/10/26 | 08/18/26 | $1w | : | |
| 635-07 | Furniture Maker | 72 | 08/12/26 | 08/18/26 | $1w | : | |
| 635-07-01 | STBD side Cabinet | 40 | 08/12/26 | 08/18/26 | $40h | : | |
| 635-07-02 | Stairway/ Walls | 32 | 08/13/26 | 08/18/26 | $32h | : | |
| 635-08 | Interior Painting | 28 | 08/13/26 | 08/18/26 | $28h | : | |
| 635-08-01 | Stairway/ Walls | 28 | 08/13/26 | 08/18/26 | $28h | : | |
| 635-09 | Carpentry | 148 | 08/10/26 | 08/18/26 | $52h | : | |
| 635-09-01 | Room Framing | 52 | 08/10/26 | 08/18/26 | $52h | : | |
| 635-09-02 | Ship side Cabinet (S) | 24 | 08/14/26 | 08/18/26 | $24h | : | |
| 635-09-03 | Wall | 44 | 08/11/26 | 08/18/26 | $44h | : | |
| 635-09-04 | Ceiling | 24 | 08/14/26 | 08/18/26 | $24h | : | |
| 635-09-05 | Finish Trims | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 635-10 | Plumbing | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 635-10-01 | Appliances | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 635-11 | Mechanical | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 635-11-01 | Appliances | 12 | 08/17/26 | 08/18/26 | $12h | : | |
| 635-12 | Electrical | 48 | 08/13/26 | 08/18/26 | $1w | : | |
| 635-12-01 | Rough in | 28 | 08/13/26 | 08/18/26 | $28h | : | |
| 635-12-02 | Intsall/ Connect | 16 | 08/17/26 | 08/18/26 | $16h | : | |
| 635-12-03 | Finish trims | 4 | 08/18/26 | 08/18/26 | $4h | : | |
| 635-13 | Decor Carpentry | 32 | 08/17/26 | 08/18/26 | $16h | : | |
| 635-13-02 | Overhead | 8 | 08/18/26 | 08/18/26 | $8h | : | |
| 635-13-03 | Walls | 16 | 08/17/26 | 08/18/26 | $16h | : | |
| 635-13-04 | Floor | 8 | 08/18/26 | 08/18/26 | $8h | : | |
| | | | | | | | |
| ************ | *********************************************** | *********** | *************** | *************** | *************** | | ********************************************* |
|
|
|
|
|