DESTINATION ONE
A- Project Data
B- Drawings
C- Photographs
D- Documentation
E- Worksheets
1.4 Interior Budgets
.
607. Guest Bathroom 3
Department Summary
CodeDepatmentLabor Hrs.Start DateFinish DateDuration:Comments
543h...:.
006. Marine Painting16h.....
007. Furniture Maker75h.....
008. Interior Painting48h.....
009. Fit-Out Carpentry186h.....
010. Plumbing28h.....
011. Mechanical12h.....
012. Electrical40h.....
013. Decor Carpentry42h.....
************ ****************************************************************************************************************************************************
Finishes
CodeFinishesLabor Hrs.Start DateFinish DateDuration:Comments
023. Lighting/Fixtures...:.
029. Mirror/Glass...:.
030. Wall Covering...:.
081. Plumbing Hardware...:.
083. Stone/Marble96h...:.
************ ****************************************************************************************************************************************************
.
Job Assignments
CodeJob AssignmentLabor Hrs.Start DateFinish DateDuration:Comments
6INTERIOR54307/21/2608/18/26$4w:
607  Guest Bathroom 354308/03/2608/18/26$2w:
607-06    Marine Painting1608/17/2608/18/26$16h:
607-06-01      Ceiling1608/17/2608/18/26$16h:
607-07    Furniture Maker7508/11/2608/18/26$1w:
607-07-01      Sink vanity4708/11/2608/18/26$47h:
607-07-02      Medicine Cabinet2808/13/2608/18/26$28h:
607-08    Interior Painting4808/12/2608/18/26$1w:
607-08-01      Sink Cabinet3608/12/2608/18/26$36h:
607-08-02      Medicine Cabinet1208/17/2608/18/26$12h:
607-09    Carpentry18608/05/2608/18/26$2w:
607-09-01      Room Framing7608/05/2608/18/26$76h:
607-09-02      Sink Vanity Cabinet1808/14/2608/18/26$18h:
607-09-03      Medicine Cabinet1208/17/2608/18/26$12h:
607-09-04      Walls2408/14/2608/18/26$24h:
607-09-05      Ceiling2808/13/2608/18/26$28h:
607-09-06      Flooring1208/17/2608/18/26$12h:
607-09-07      Finish Trims1608/17/2608/18/26$16h:
607-10    Plumbing2808/18/2608/18/26$0w:
607-10-01      Sink808/18/2608/18/26$8h:
607-10-02      Shower808/18/2608/18/26$8h:
607-10-03      Toilet808/18/2608/18/26$8h:
607-10-04      Finish trims408/18/2608/18/26$4h:
607-11    Mechanical1208/17/2608/18/26$0w:
607-11-01      Extraction fan1208/17/2608/18/26$12h:
607-12    Electrical4008/14/2608/18/26$1w:
607-12-01      Rough in circuits2408/14/2608/18/26$24h:
607-12-02      Install/Connect1208/17/2608/18/26$12h:
607-12-03      Finish trims408/18/2608/18/26$4h:
607-14    Decor Carpentry13808/03/2608/18/26$2w:
607-14-01      Stone/Marble9608/03/2608/18/26$96h:
607-14-02      Walls1608/17/2608/18/26$16h:
607-14-03      Finishes2608/13/2608/18/26$26h:
************ ****************************************************************************************************************************************************