| WBS | Project Categories | Labor Hrs. | Start Date | Finish Dates | Duration | : | Comments |
| | DEPARTMENT TOTAL | 26,048 | 07/19/24 | 12/13/24 | . | : | . |
| 1 | HULL/SUPERSTRUCTURE SHELL | 26,048 | 07/19/24 | 12/13/24 | 175.2w | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |
|
|
| WBS | Job Description | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 1 | HULL/SUPERSTRUCTURE SHELL | 26,048 | 07/19/24 | 12/13/24 | 175.2w | : | |
| 102 | Hull Module - Block 1 | 3,560 | 12/04/24 | 12/13/24 | 175.2w | : | |
| 102-04 | Metal Fabrication | 3,560 | 12/04/24 | 12/13/24 | 6,825.0h | : | |
| 102-04-01 | Parts Preparation | 480 | 12/09/24 | 12/13/24 | 6,825.0h | : | |
| 102-04-01-L | Labor | 480 | 12/09/24 | 12/13/24 | 120.0h | : | |
| 102-04-01-L 01 | Prepare Jig to receive frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-01-L 02 | Clean and prepare frame parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-01-L 03 | Clean and prepare shell plate parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-02 | Parts Assemble | 960 | 12/04/24 | 12/13/24 | 6,782.0h | : | |
| 102-04-02-L | Labor | 960 | 12/04/24 | 12/13/24 | 240.0h | : | |
| 102-04-02-L 01 | Assemble prepared transverse frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-02-L 02 | Assemble prepared longitudinal frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-02-L 03 | Assemble prepared parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-02-L 04 | Assemble prepared integral piping parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-03 | Frame installation | 1,200 | 12/04/24 | 12/13/24 | 6,660.0h | : | |
| 102-04-03-L | Labor | 1,200 | 12/04/24 | 12/13/24 | 300.0h | : | |
| 102-04-03-L 01 | Install prepared transverse frames to jig | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-03-L 02 | Install prepared longitudinal frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-03-L 03 | Install prepared plate stinnener frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-03-L 04 | Install remaining prepared parts onto jig as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-03-L 05 | Install integral piping if required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-04 | Shell plate installation | 800 | 12/04/24 | 12/13/24 | 6,346.0h | : | |
| 102-04-04-L | Labor | 800 | 12/04/24 | 12/13/24 | 200.0h | : | |
| 102-04-04-L 01 | Install all shell plate to module framing | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-04-L 03 | Install all topside shell plates | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 102-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 6,174.3h | : | |
| 102-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 102-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 103 | Hull Module - Block 2 | 3,560 | 12/04/24 | 12/13/24 | 171.3w | : | |
| 103-04 | Metal Fabrication | 3,560 | 12/04/24 | 12/13/24 | 6,569.0h | : | |
| 103-04-01 | Parts Preparation | 480 | 12/09/24 | 12/13/24 | 6,409.0h | : | |
| 103-04-01-L | Labor | 480 | 12/09/24 | 12/13/24 | 120.0h | : | |
| 103-04-01-L 01 | Prepare Jig to receive frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-01-L 02 | Clean and prepare frame parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-01-L 03 | Clean and prepare shell plate parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-02 | Parts Assemble | 960 | 12/04/24 | 12/13/24 | 6,548.0h | : | |
| 103-04-02-L | Labor | 960 | 12/04/24 | 12/13/24 | 240.0h | : | |
| 103-04-02-L 01 | Assemble prepared transverse frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-02-L 02 | Assemble prepared longitudinal frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-02-L 03 | Assemble prepared parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-02-L 04 | Assemble prepared integral piping parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-03 | Frame installation | 1,200 | 12/04/24 | 12/13/24 | 6,569.0h | : | |
| 103-04-03-L | Labor | 1,200 | 12/04/24 | 12/13/24 | 300.0h | : | |
| 103-04-03-L 01 | Install prepared transverse frames to jig | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-03-L 02 | Install prepared longitudinal frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-03-L 03 | Install prepared plate stinnener frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-03-L 04 | Install remaining prepared parts onto jig as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-03-L 05 | Install integral piping if required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-04 | Shell plate installation | 800 | 12/04/24 | 12/13/24 | 6,411.0h | : | |
| 103-04-04-L | Labor | 800 | 12/04/24 | 12/13/24 | 200.0h | : | |
| 103-04-04-L 01 | Install all shell plate to module framing | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-04-L 03 | Install all topside shell plates | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 103-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 6,209.0h | : | |
| 103-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 103-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 104 | Hull Module - Block 3 | 3,560 | 12/04/24 | 12/13/24 | 163.5w | : | |
| 104-04 | Metal Fabrication | 3,560 | 12/04/24 | 12/13/24 | 6,539.0h | : | |
| 104-04-01 | Parts Preparation | 480 | 12/09/24 | 12/13/24 | 6,539.0h | : | |
| 104-04-01-L | Labor | 480 | 12/09/24 | 12/13/24 | 120.0h | : | |
| 104-04-01-L 01 | Prepare Jig to receive frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-01-L 02 | Clean and prepare frame parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-01-L 03 | Clean and prepare shell plate parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-02 | Parts Assemble | 960 | 12/04/24 | 12/13/24 | 6,405.0h | : | |
| 104-04-02-L | Labor | 960 | 12/04/24 | 12/13/24 | 240.0h | : | |
| 104-04-02-L 01 | Assemble prepared transverse frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-02-L 02 | Assemble prepared longitudinal frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-02-L 03 | Assemble prepared parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-02-L 04 | Assemble prepared integral piping parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-03 | Frame installation | 1,200 | 12/04/24 | 12/13/24 | 6,244.0h | : | |
| 104-04-03-L | Labor | 1,200 | 12/04/24 | 12/13/24 | 300.0h | : | |
| 104-04-03-L 01 | Install prepared transverse frames to jig | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-03-L 02 | Install prepared longitudinal frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-03-L 03 | Install prepared plate stinnener frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-03-L 04 | Install remaining prepared parts onto jig as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-03-L 05 | Install integral piping if required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-04 | Shell plate installation | 800 | 12/04/24 | 12/13/24 | 5,969.0h | : | |
| 104-04-04-L | Labor | 800 | 12/04/24 | 12/13/24 | 200.0h | : | |
| 104-04-04-L 01 | Install all shell plate to module framing | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-04-L 03 | Install all topside shell plates | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 104-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 5,819.0h | : | |
| 104-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 104-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 105 | Hull Module - Block 4 | 3,560 | 12/04/24 | 12/13/24 | 160.6w | : | |
| 105-04 | Metal Fabrication | 3,560 | 12/04/24 | 12/13/24 | 6,422.0h | : | |
| 105-04-01 | Parts Preparation | 480 | 12/09/24 | 12/13/24 | 6,422.0h | : | |
| 105-04-01-L | Labor | 480 | 12/09/24 | 12/13/24 | 120.0h | : | |
| 105-04-01-L 01 | Prepare Jig to receive frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-01-L 02 | Clean and prepare frame parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-01-L 03 | Clean and prepare shell plate parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-02 | Parts Assemble | 960 | 12/04/24 | 12/13/24 | 6,405.0h | : | |
| 105-04-02-L | Labor | 960 | 12/04/24 | 12/13/24 | 240.0h | : | |
| 105-04-02-L 01 | Assemble prepared transverse frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-02-L 02 | Assemble prepared longitudinal frames | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-02-L 03 | Assemble prepared parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-02-L 04 | Assemble prepared integral piping parts as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-03 | Frame installation | 1,200 | 12/04/24 | 12/13/24 | 6,361.0h | : | |
| 105-04-03-L | Labor | 1,200 | 12/04/24 | 12/13/24 | 300.0h | : | |
| 105-04-03-L 01 | Install prepared transverse frames to jig | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-03-L 02 | Install prepared longitudinal frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-03-L 03 | Install prepared plate stinnener frames onto module | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-03-L 04 | Install remaining prepared parts onto jig as required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-03-L 05 | Install integral piping if required | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-04 | Shell plate installation | 800 | 12/04/24 | 12/13/24 | 6,073.0h | : | |
| 105-04-04-L | Labor | 800 | 12/04/24 | 12/13/24 | 200.0h | : | |
| 105-04-04-L 01 | Install all shell plate to module framing | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-04-L 03 | Install all topside shell plates | 240 | 12/04/24 | 12/13/24 | 60.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 105-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 5,823.3h | : | |
| 105-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 105-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 111 | Module Connection | 16 | 12/13/24 | 12/13/24 | 0.6w | : | |
| 111-04 | Metal Fabrication | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 111-04-01 | Block 101 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 111-04-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 111-04-01-L 01 | Trim and level block 201 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 111-04-01-L 02 | Final install block 201 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 111-04-02 | Block 102 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 111-04-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 111-04-02-L 01 | Trim and level block 202 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 111-04-02-L 02 | Final install block 202 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112 | Integral Tanks | 348 | 07/19/24 | 12/13/24 | 21.1w | : | |
| 112-04 | Metal fabrication | 348 | 07/19/24 | 12/13/24 | 21.1w | : | |
| 112-04-01 | Fuel Oil - Port Tank Day | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-01-L | Labor | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-01-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-01-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-01-L 03 | Fabricate tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-01-L 04 | Install tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-01-L 05 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-02 | Fuel Oil - STBD Tank Day | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-02-L | Labor | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-02-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-02-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-02-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-03 | Fuel Oil - Port Tank Mid | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-03-L | Labor | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-03-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-03-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-03-L 03 | Fabricate tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-03-L 04 | Install tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-03-L 05 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-04 | Fuel Oil - STBD Tank Mid | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-04-L | Labor | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-04-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-04-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-04-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-05 | Fuel Oil - Port Tank FWD | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-05-L | Labor | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-05-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-05-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-05-L 03 | Fabricate tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-05-L 04 | Install tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-05-L 05 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-06 | Fuel Oil - STBD Tank FWD | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-06-L | Labor | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-06-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-06-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-06-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-07 | Freshwater Tank - Port | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-07-L | Labor | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-07-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-07-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-07-L 03 | Fabricate tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-07-L 04 | Install tank vent cross-over pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-07-L 05 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-08 | Freshwater Tank - STBD | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-08-L | Labor | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-08-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-08-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-08-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-09 | Blackwater Tank | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-09-L | Labor | 20 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-09-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-09-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-09-L 03 | Fabricate intake pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-09-L 04 | Install intake pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-09-L 05 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-10 | Greywater Tank - AFT | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-10-L | Labor | 12 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-10-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-10-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-10-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11 | Greywater Tank - FWD | 44 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-11-L | Labor | 44 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-11-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-11-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 04 | Fabricate FWD intake pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 05 | Fabricate AFT intake pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 06 | Fabricate vent piping to Aft tank | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 07 | Fabricate suction piping to Aft tank | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 08 | Install FWD intake pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 09 | Install AFT intake pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 10 | Install vent piping to Aft tank | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-11-L 11 | Install suction piping to Aft tank | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12 | UREA Tank - PORT | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-12-L | Labor | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-12-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-12-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 04 | Fabricate tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 05 | Fabricate tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 06 | Fabricate tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 07 | Install tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 08 | Install tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-12-L 09 | Install tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13 | UREA Tank - STBD | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-13-L | Labor | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-13-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-13-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 04 | Fabricate tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 05 | Fabricate tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 06 | Fabricate tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 07 | Install tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 08 | Install tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-13-L 09 | Install tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14 | Lubricating Oil Tank - PORT | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-14-L | Labor | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-14-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-14-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 04 | Fabricate tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 05 | Fabricate tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 06 | Fabricate tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 07 | Install tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 08 | Install tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-14-L 09 | Install tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15 | Lubricating Oil Tank - STBD | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-15-L | Labor | 36 | 07/19/24 | 12/13/24 | 845.0h | : | |
| 112-04-15-L 01 | Fabricate tank gauge flange plate | 4 | 07/19/24 | 07/19/24 | 4.0h | : | |
| 112-04-15-L 02 | Install all tank gauge flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 03 | Install tank access hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 04 | Fabricate tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 05 | Fabricate tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 06 | Fabricate tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 07 | Install tank fill pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 08 | Install tank vent piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 112-04-15-L 09 | Install tank suction piping | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 113 | Hull Watertight Bulkheads | 24 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 113-04 | Metal Fabrication | 24 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 113-04-01 | Bulkhead 28 | 8 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 113-04-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 113-04-01-L 01 | Fit up remaining bulkhead plate to fit inside frame | 4 | 12/13/24 | 12/13/24 | 4.0h | : | Require crew interior boxes loaded before task complete |
| 113-04-01-L 02 | Final install remaining bulkhead plate insert | 4 | 12/13/24 | 12/13/24 | 4.0h | : | Require crew interior boxes loaded before task complete |
| 113-04-02 | Bulkhead 14 | 8 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 113-04-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 113-04-02-L 01 | Fit up remaining bulkhead plate to fit inside frame | 4 | 12/13/24 | 12/13/24 | 4.0h | : | Require Crew & Guest interior boxes loaded before task complete |
| 113-04-02-L 02 | Final install remaining bulkhead plate insert | 4 | 12/13/24 | 12/13/24 | 4.0h | : | Require Crew & Guest interior boxes loaded before task complete |
| 113-04-03 | Bulkhead 08 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 113-04-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 113-04-03-L 01 | Fit up remaining bulkhead plate to fit inside frame | 4 | 12/13/24 | 12/13/24 | 4.0h | : | Require Crew & Guest interior boxes loaded before task complete |
| 113-04-03-L 02 | Final install remaining bulkhead plate insert | 4 | 12/13/24 | 12/13/24 | 4.0h | : | Require Crew & Guest interior boxes loaded before task complete |
| 116 | Forepeak | 112 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 116-04 | Metal fabrication | 60 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 116-04-01 | Chain Locker | 36 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 116-04-01-P | Labor | 36 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 116-04-01-P 01 | Fabricate anchor hawse pipe | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 02 | Fabricate drain piping to hawse pipe discharge | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 03 | Install chain bin stachions | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 04 | Install chain bin foundations - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 05 | Install chain bin foundations - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 06 | Install chain bin rails - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 07 | Install chain bin rails - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 08 | Install light switch support bracket | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-01-P 09 | Install access ladder | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-02 | Access hatch | 24 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 116-04-02-P | Labor | 24 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 116-04-02-P 01 | Fabricate access hatch raised deck plate | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 116-04-02-P 02 | Fabricate access hatch coaming plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-02-P 03 | Fabricate access hatch attachment flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-04-02-P 04 | Install access hatch raised deck plate | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 116-04-02-P 05 | Install access hatch coaming plate | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 116-04-02-P 06 | Install access hatch attachment flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05 | Metal Welding | 52 | 12/12/24 | 12/13/24 | 1.5d | : | |
| 116-05-01 | Chain Locker | 36 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 116-05-01-P | Labor | 36 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 116-05-01-P 01 | Weld anchor hawse pipe | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 116-05-01-P 02 | Weld drain piping to hawse pipe discharge | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 03 | Weld chain bin stachions | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 04 | Weld chain bin foundations - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 05 | Weld chain bin foundations - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 06 | Weld chain bin rails - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 07 | Weld chain bin rails - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 08 | Weld light switch support bracket | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-01-P 09 | Weld access ladder | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-02 | Access hatch | 16 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 116-05-02-P | Labor | 16 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 116-05-02-P 01 | Weld access hatch deck raised plate | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 116-05-02-P 02 | Weld access hatch coaming plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-02-P 03 | Weld access hatch attachment flange plate | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 116-05-02-P 04 | Weld light switch support bracket | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117 | Machinery Room - FWD | 264 | 12/06/24 | 12/13/24 | 1.1w | : | |
| 117-04 | Metal Fabrication | 264 | 12/06/24 | 12/13/24 | 44.0h | : | |
| 117-04-01 | Foundations | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L | Labor | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 01 | Fabricate DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 02 | Fabricate overhead light foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 03 | Fabricate access hatch coaming | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 04 | Fabricate access steps foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 05 | Install DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 06 | Install overhead light foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 07 | Install access hatch coaming | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-01-L 08 | Install access steps foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-02 | Intake/Discharge Standpipes | 20 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-02-L | Labor | 20 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 117-04-02-L 01 | Fabricate aux overboard thru hull - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-02-L 02 | Fabricate aux overboard thru hull - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-02-L 03 | Install aux overboard thru hull - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-02-L 04 | Install aux overboard thru hull - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-02-L 05 | Lloyds Inspection | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-03 | Transducers | 20 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-03-L | Labor | 20 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 117-04-03-L 01 | Fabricate speed log transducer housing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-03-L 02 | Fabricate sonar transducer housing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-03-L 03 | Install speed log transducer housing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-03-L 04 | Install sonar transducer housing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-03-L 05 | Lloyds Inspection | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04 | Freshwater Pumps | 64 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 117-04-04-L | Labor | 64 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 117-04-04-L 01 | Fabricate pump foundations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 117-04-04-L 02 | Fabricate high pressur filter foundations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 117-04-04-L 03 | Fabricate distribution manifold foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 04 | Fabricate waterheater foundations Port Aft | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 05 | Fabricate waterheater foundations Port FWD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 06 | Fabricate waterheater foundations STBD Aft | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 07 | Fabricate waterheater foundations STBD FWD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 08 | Fabricate control panel mounts | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 09 | Install pump foundations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 117-04-04-L 10 | Install high pressur filter foundations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 117-04-04-L 11 | Install distribution manifold foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 12 | Install waterheater foundations Port Aft | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 13 | Install waterheater foundations Port FWD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 14 | Install waterheater foundations STBD Aft | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 15 | Install waterheater foundations STBD FWD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-04-L 16 | Install control panel mounts | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-05 | Watermaker System | 112 | 12/06/24 | 12/13/24 | 44.0h | : | |
| 117-04-05-L | Labor | 112 | 12/06/24 | 12/13/24 | 1.1w | : | |
| 117-04-05-L 01 | Fabricate L.P pump foundations | 16 | 12/06/24 | 12/10/24 | 16.0h | : | |
| 117-04-05-L 02 | Fabricate H.P pump foundations | 16 | 12/10/24 | 12/12/24 | 16.0h | : | |
| 117-04-05-L 03 | Fabricate membrane foundations | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 117-04-05-L 04 | Fabricate all filter foundations | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 117-04-05-L 05 | Install L.P pump foundations | 16 | 12/06/24 | 12/10/24 | 16.0h | : | |
| 117-04-05-L 06 | Install H.P pump foundations | 16 | 12/10/24 | 12/12/24 | 16.0h | : | |
| 117-04-05-L 07 | Install membrane foundations | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 117-04-05-L 08 | Install all filter foundations | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 117-04-06 | Floor Framing | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 117-04-06-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 117-04-06-L 01 | Fabricate all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-06-L 02 | Fabricate floor mount clips | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-06-L 03 | Install floor mount clips | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 117-04-06-L 04 | Install all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118 | Engine room | 64 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 118-04 | Metal fabrication | 64 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 118-04-01 | Foundations | 24 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 118-04-01-L | Labor | 24 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 118-04-01-L 01 | Fabricate lower stanchion foundations FR10 | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-01-L 02 | Fabricate upper stanchion foundations FR10 | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-01-L 03 | Fabricate DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-01-L 04 | Install lower stanchion foundations FR10 | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-01-L 05 | Install upper stanchion foundations FR10 | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-01-L 06 | Install DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-02 | Ceiling Framing | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 118-04-02-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 118-04-02-L 01 | Fabricate all overhead frame panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 118-04-02-L 02 | Fabricate overhead mount clips | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 118-04-02-L 03 | Install outer and aft overhead frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-02-L 04 | Dry-fit center overhead panels, remove for engine installation | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-03 | Floor Framing | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 118-04-03-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 118-04-03-L 01 | Fabricate all floor frame panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 118-04-03-L 02 | Fabricate floor mount clips | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 118-04-03-L 03 | Install under-floor cable trays | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-03-L 04 | Install all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-04 | MISC - Updated Items | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 118-04-04-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 118-04-04-L 01 | Rework fuel fill pipes in FWD overhead - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 118-04-04-L 02 | Rework fuel fill pipes in FWD overhead - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120 | Garage | 172 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 120-04 | Metal Fabrication | 172 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 120-04-01 | Garage door Foundations | 28 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 120-04-01-L | Labor | 28 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 120-04-01-L 01 | Fabricate garage door foundation frame | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-01-L 02 | Fabricate garage door hinges | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 120-04-01-L 03 | Fabricate garage door hinge fouldations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-01-L 04 | Fabricate garage door dog fouldations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 120-04-01-L 05 | Install garage door foundations to structure | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-01-L 06 | Install garage door hinges | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-01-L 07 | Install garage door hinge fouldations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02 | Garage Door | 72 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 120-04-02-L | Labor | 72 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 01 | Fabricate door transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 02 | Fabricate door longtitudinal frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 03 | Fabricate door plate stiffener frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 04 | Fabricate door shell plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 05 | Fabricate door hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 06 | Fabricate door accuator foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 07 | Fabricate sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 08 | Fabricate dog foundations to door structure | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 09 | Fabricate inner plate for door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 10 | Install door transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 11 | Install door longtitudinal frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 12 | Install door plate stiffener frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 13 | Install door shell plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 14 | Install door hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 15 | Install door accuator foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 16 | Install sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 17 | Install dog foundations to door structure | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-02-L 18 | Install inner plate for door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-03 | Foundations | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 120-04-03-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 120-04-03-L 01 | Fabricate tender mount foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-03-L 02 | Fabricate DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-03-L 03 | Install tender mount foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-03-L 04 | Install DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-04 | Ceiling Framing | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 120-04-04-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 120-04-04-L 01 | Fabricate all overhead frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-04-L 02 | Fabricate overhead mount support brackets | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-05 | Floor Framing | 12 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 120-04-05-L | Labor | 12 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 120-04-05-L 01 | Fabricate all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-05-L 02 | Fabricate floor mount clips | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-05-L 03 | Install all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-06 | Work Bench Framing | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 120-04-06-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 120-04-06-L 01 | Fabricate work bench framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-06-L 02 | Install work bench framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-07 | Passerelle Ladder | 16 | 12/13/24 | 12/13/24 | 5.0h | : | |
| 120-04-07-L | Labor | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-07-L 01 | Fabricate passerelle foundation plates | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-07-L 02 | Fabricate passerelle opening in transom step - Stbd | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-07-L 03 | Install passerelle foundation plates | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-07-L 04 | Install passerelle box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-08 | Overhead Crane | 12 | 12/13/24 | 12/13/24 | 5.0h | : | |
| 120-04-08-L | Labor | 12 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-08-L 01 | Fabricate overhead crane foundation plates | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-08-L 02 | Install overhead crane foundation plates | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 120-04-08-L 03 | Install overhead crane | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121 | Rudder Room | 140 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 121-04 | Metal fabrication | 140 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 121-04-01 | Foundations | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-01-L | Labor | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-01-L 01 | Fabricate DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-01-L 02 | Fabricate overhead light foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-01-L 03 | Install DC bilge pump foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-01-L 04 | Install overhead light foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-02 | Steering System | 24 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 121-04-02-L | Labor | 24 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 121-04-02-L 01 | Fabricate steering power pack foundations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 121-04-02-L 02 | Fabricate steering electrical panel foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-02-L 03 | Fabricate steering cylinder foundations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 121-04-02-L 04 | Install steering power pack foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-02-L 05 | Install steering electrical panel foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-02-L 06 | Install steering cylinder foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-03 | Compressed Air System | 56 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 121-04-03-L | Labor | 56 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 121-04-03-L 01 | Fabricate air compressor foundations | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 121-04-03-L 02 | Fabricate air reciever foundations | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 121-04-03-L 03 | Fabricate air filter foundations | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 121-04-03-L 04 | Install air compressor foundations | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 121-04-03-L 05 | Install air reciever foundations | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 121-04-03-L 06 | Install air filter foundations | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 121-04-04 | Shorepower System | 32 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 121-04-04-L | Labor | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 121-04-04-L 01 | Fabricate shorepower cable container - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 02 | Fabricate shorepower cable container - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 03 | Fabricate shorepower electical panel - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 04 | Fabricate shorepower electical panel - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 05 | Install shorepower cable container - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 06 | Install shorepower cable container - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 07 | Install shorepower electical panel - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-04-L 08 | Install shorepower electical panel - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-05 | Floor Framing | 12 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 121-04-05-L | Labor | 12 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 121-04-05-L 01 | Fabricate all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-05-L 02 | Fabricate floor mount clips | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 121-04-05-L 03 | Install all floor frame panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122 | Transom | 164 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 122-04 | Metal fabrication | 164 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 122-04-01 | Beach Club Door | 72 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 122-04-01-L | Labor | 72 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 01 | Fabricate door transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 02 | Fabricate door longtitudinal frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 03 | Fabricate door plate stiffener frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 04 | Fabricate door shell plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 05 | Fabricate door hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 06 | Fabricate door accuator foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 07 | Fabricate sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 08 | Fabricate dog foundations to door structure | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 09 | Fabricate inner plate for door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 10 | Install door transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 11 | Install door longtitudinal frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 12 | Install door plate stiffener frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 13 | Install door shell plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 14 | Install door hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 15 | Install door accuator foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 16 | Install sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 17 | Install dog foundations to door structure | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-01-L 18 | Install inner plate for door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-02 | Guardrail Foundations | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 122-04-02-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 122-04-02-L 01 | Fabricate removable hoop rail foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-02-L 02 | Fabricate stairway handrail supports | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-02-L 03 | Install removable guard rail foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-02-L 04 | Install stairway handrail supports | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-03 | ShorePower reccesses | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 122-04-03-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 122-04-03-L 01 | Fabricate shorepower reccess box - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-03-L 02 | Fabricate shorepower reccess box - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-03-L 03 | Install shorepower reccess box - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-03-L 04 | Install shorepower reccess box - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-04 | Beach Club Door Foundations | 20 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 122-04-04-L | Labor | 20 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 122-04-04-L 01 | Fabricate Beach Club door hinges | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 122-04-04-L 02 | Fabricate Beach Club door hinge fouldations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-04-L 03 | Fabricate Beach Club door dog fouldations | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 122-04-04-L 04 | Install Beach Club door hinges | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-04-L 05 | Install Beach Club door hinge fouldations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-05 | Ceiling Framing | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 122-04-05-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 122-04-05-L 01 | Fabricate ceiling framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-05-L 02 | Install ceiling framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06 | Beach Club Walls/Floor | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 122-04-06-L | Labor | 32 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 122-04-06-L 01 | Fabricate beach club Fwd bulkhead framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 02 | Fabricate beach club side wall framing - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 03 | Fabricate beach club side wall framing - Stbd | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 04 | Fabricate beach club step to garage | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 05 | Install beach club Fwd bulkhead framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 06 | Install beach club side wall framing - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 07 | Install beach club side wall framing - Stbd | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 122-04-06-L 08 | Install beach club step to garage | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124 | Driveline | 52 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 124-04 | Metal fabrication | 36 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 124-04-01 | Main Engine Driveline | 36 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 124-04-01-L | Labor | 36 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 124-04-01-L 01 | Fabricate top outer driveline tube - Port | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 124-04-01-L 02 | Fabricate top outer driveline tube - STBD | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 124-04-01-L 03 | Fabricate lower outer driveline tube - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-04-01-L 04 | Fabricate lower outer driveline tube - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-04-01-L 05 | Install top outer driveline tube - Port | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 124-04-01-L 06 | Install top outer driveline tube - STBD | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 124-04-01-L 07 | Install lower outer driveline tube - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-04-01-L 08 | Install lower outer driveline tube - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-04-01-L 09 | Lloyds inspection | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-05 | Metal Welding | 16 | 12/12/24 | 12/13/24 | 1.5d | : | |
| 124-05-01 | Main Engine Driveline | 16 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 124-05-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 124-05-01-L 01 | Weld top outer driveline tube - Port | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 124-05-01-L 02 | Weld top outer driveline tube - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-05-01-L 03 | Weld lower outer driveline tube - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 124-05-01-L 04 | Weld lower outer driveline tube - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125 | Hull Appendages | 48 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 125-04 | Metal fabrication | 48 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 125-04-01 | Bowthruster Tunnel | 32 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 125-04-01-L | Labor | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 01 | Prepare tunnel for installation | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 02 | Drill motor holes as needed | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 03 | Install tunnel to hull | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 04 | Install doubler plates as needed | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 05 | Fabricate port & Stbd tunnel grill foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 06 | Fabricate port & Stbd removable tunnel grills | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 07 | Lloyds structure inspection | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-01-L 08 | Install port & Stbd tunnel grills | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-02 | Transducter Penetrations | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-02-L | Labor | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-02-L 01 | Fabricate speed log penetration | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-02-L 02 | Fabricate sonar penetration | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-02-L 03 | Install speed log penetration | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 125-04-02-L 04 | Install sonar penetration | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130 | Main Decking Construction | 140 | 12/13/24 | 12/13/24 | 0.3w | : | |
| 130-04 | Metal Fabrication | 124 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 130-04-01 | Caprail | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-01-L 01 | Install bow section caprail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-01-L 02 | Install bow section handrail sockets | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02 | Bulkwark Patio Door - Port | 100 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L | Labor | 100 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 01 | Cut hull sheel, caprail and structure at patio door for reuse | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 02 | Cut deck plate in way of the hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 03 | Cut transverse frames in way of the hinge box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 04 | Fabricate new transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 05 | Fabricate new longtitudinal deck girder | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 06 | Fabricate door hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 07 | Fabricate door accuator foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 08 | Fabricate bulkwark frame w/ recess box for door dogs - FWD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 09 | Modify structure in part removed from hull to create patio door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 10 | Fabricate bulkwark frame w/ recess box for door dogs - AFT | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 11 | Fabricate sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 12 | Fabricate dog foundations to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 13 | Fabricate inner plate for new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 14 | Fabricate deck sewer drains | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 15 | Install new transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 16 | Install new longtitudinal deck girder | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 17 | Install door hinge foundation box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 18 | Install door accuator foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 19 | Install bulkwark frame w/ recess box for door dogs - FWD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 20 | Install bulkwark frame w/ recess box for door dogs - AFT | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 21 | Install bulkwark frame w/ recess box for door dogs - AFT | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 22 | Install sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 23 | Install dog foundations to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 24 | Install inner plate for new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-02-L 25 | Install deck sewer drains | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-03 | Foundations | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-03-L 01 | Fabricate Niclad Bi-metal strip for house connection | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-03-L 02 | Install Niclad Bi-metal strip for house connection | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-04 | Main decking Penetrations | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 130-04-04-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-04-L 01 | Install engine room fan plate - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-04-04-L 02 | Install engine room fan plate - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-05 | Metal Welding | 16 | 12/13/24 | 12/13/24 | 1.3d | : | |
| 130-05-02 | Bulkwark Patio Door - Port | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-05-02-L | Labor | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-05-02-L 07 | Weld structure in part removed from hull to create patio door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-05-02-L 08 | Weld sides to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-05-02-L 09 | Weld dog foundations to new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 130-05-02-L 10 | Weld inner plate for new door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 131 | Main Cabin Module - Block 1 | 2,680 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 131-04 | Metal Fabrication | 2,680 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 131-04-01 | Parts Preparation | 480 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-01-L | Labor | 480 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-01-L 01 | Prepare Jig to receive frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-01-L 02 | Clean and prepare frame parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-01-L 03 | Clean and prepare shell plate parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-02 | Parts Assemble | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-02-L | Labor | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-02-L 01 | Assemble prepared transverse frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-02-L 02 | Assemble prepared longitudinal frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-02-L 03 | Assemble prepared parts as required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-02-L 04 | Assemble prepared integral piping parts as required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-03 | Frame installation | 800 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-03-L | Labor | 800 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-03-L 01 | Install prepared transverse frames to jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-03-L 02 | Install prepared longitudinal frames onto module | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-03-L 03 | Install prepared plate stinnener frames onto module | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-03-L 04 | Install remaining prepared parts onto jig as required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-03-L 05 | Install integral piping if required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-04 | Shell plate installation | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-04-L | Labor | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-04-L 01 | Install all shell plate to module framing | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-04-L 03 | Install all topside shell plates | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 131-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 131-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132 | Main Cabin Module - Block 2 | 2,680 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 132-04 | Metal Fabrication | 2,680 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 132-04-01 | Parts Preparation | 480 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-01-L | Labor | 480 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-01-L 01 | Prepare Jig to receive frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-01-L 02 | Clean and prepare frame parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-01-L 03 | Clean and prepare shell plate parts from CNC | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-02 | Parts Assemble | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-02-L | Labor | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-02-L 01 | Assemble prepared transverse frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-02-L 02 | Assemble prepared longitudinal frames | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-02-L 03 | Assemble prepared parts as required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-02-L 04 | Assemble prepared integral piping parts as required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-03 | Frame installation | 800 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-03-L | Labor | 800 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-03-L 01 | Install prepared transverse frames to jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-03-L 02 | Install prepared longitudinal frames onto module | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-03-L 03 | Install prepared plate stinnener frames onto module | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-03-L 04 | Install remaining prepared parts onto jig as required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-03-L 05 | Install integral piping if required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-04 | Shell plate installation | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-04-L | Labor | 640 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-04-L 01 | Install all shell plate to module framing | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-04-L 03 | Install all topside shell plates | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 132-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 132-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 137 | Module Connection | 16 | 12/13/24 | 12/13/24 | 0.6w | : | |
| 137-04 | Metal Fabrication | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 137-04-01 | Block 201 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 137-04-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 137-04-01-L 01 | Trim and level block 201 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 137-04-01-L 02 | Final install block 201 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 137-04-02 | Block 202 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 137-04-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 137-04-02-L 01 | Trim and level block 202 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 137-04-02-L 02 | Final install block 202 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139 | Main deck - Fwd | 68 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 139-04 | Metal Fabrication | 68 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 139-04-01 | Foundations | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 139-04-01-L | Labor | 32 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 139-04-01-L 01 | Fabricate deck doubler plates for ladder attachment - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 02 | Fabricate cabin doubler plates for ladder attachment - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 03 | Fabricate deck doubler plates for ladder attachment - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 04 | Fabricate cabin doubler plates for ladder attachment - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 05 | Install deck doubler plates for ladder attachment - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 06 | Install cabin doubler plates for ladder attachment - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 07 | Install deck doubler plates for ladder attachment - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-01-L 08 | Install cabin doubler plates for ladder attachment - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02 | Bench seat | 36 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 139-04-02-L | Labor | 36 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 139-04-02-L 01 | Fabricate bench seat framing | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 139-04-02-L 02 | Fabricate bench seat plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02-L 03 | Fabricate bench seat storage hatches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02-L 04 | Fabricate bench seat crew escape hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02-L 05 | Assemble bench seat | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02-L 06 | Install bench seat hatch drains | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02-L 07 | Install bench seat storage hatches | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 139-04-02-L 08 | Install bench seat crew escape hatch | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 139-04-02-L 09 | Install bench seat | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 142 | Main deck - Aft | 8 | 12/13/24 | 12/13/24 | 1.0w | : | |
| 142-04 | Metal fabrication | 8 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 142-04-01 | Decking | 8 | 12/13/24 | 12/13/24 | 5.0h | : | |
| 142-04-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 142-04-01-L 01 | Fabricate deck doubler plates for table | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 142-04-01-L 02 | Install deck doubler plates for table | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 160 | Flybridge Module - Block 1 | 3,840 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 160-04 | Metal Fabrication | 3,840 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 160-04-01 | Parts Preparation | 360 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 160-04-01-L | Labor | 360 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 160-04-01-L 01 | Prepare Jig to receive frames | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-01-L 02 | Clean and prepare frame parts from CNC | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-01-L 03 | Clean and prepare shell plate parts from CNC | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-02 | Parts Assemble | 960 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 160-04-02-L | Labor | 960 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 160-04-02-L 01 | Assemble prepared transverse frames | 240 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-02-L 02 | Assemble prepared longitudinal frames | 240 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-02-L 03 | Assemble prepared parts as required | 240 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-02-L 04 | Assemble prepared integral piping parts as required | 240 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-03 | Frame installation | 1,440 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 160-04-03-L | Labor | 1,440 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 160-04-03-L 01 | Install prepared transverse frames to jig | 320 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-03-L 02 | Install prepared longitudinal frames onto module | 320 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-03-L 03 | Install prepared plate stinnener frames onto module | 320 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-03-L 04 | Install remaining prepared parts onto jig as required | 320 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-03-L 05 | Install integral piping if required | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-04 | Shell plate installation | 960 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 160-04-04-L | Labor | 960 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 160-04-04-L 01 | Install all shell plate to module framing | 320 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-04-L 02 | Remove from jig | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-04-L 03 | Install all topside shell plates | 320 | 12/02/24 | 12/13/24 | 80.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-04-L 04 | Install topside plate openings | 160 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 160-04-05 | Prepartions for connection | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 160-04-05-L | Labor | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 160-04-05-L 01 | Prepare module for sandblasting | 120 | 12/09/24 | 12/13/24 | 40.0h | : | Require crew interior boxes loaded before task complete |
| 163 | Hardtop | 144 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 163-04 | Metal Fabrication | 144 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 163-04-01 | Hardtop enclosure | 44 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 163-04-01-L | Labor | 44 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 163-04-01-L 01 | Fabricate transverse frames | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 163-04-01-L 02 | Fabricate longitudinal girders | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 03 | Fabricate longitidinal plate stiffeners | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 04 | Fabriace coaming plates | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 163-04-01-L 05 | Fabricate shell plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 06 | Prepare jig | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 07 | Install shell plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 08 | Install transverse frames | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 09 | Install longitudinal girders | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 10 | Install longitidinal plate stiffeners | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-01-L 11 | Install coaming plates | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02 | Foundations | 56 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 163-04-02-L | Labor | 56 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 163-04-02-L 01 | Fabricate hardtop stanchion AFT foundation - Port | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 163-04-02-L 02 | Fabricate hardtop stanchion AFT foundation - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 03 | Fabricate hardtop stanchion FWD foundation - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 04 | Fabricate hardtop stanchion FWD foundation - STBD | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 163-04-02-L 05 | Fabricate radar arch foundation - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 06 | Fabricate radar arch foundation - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 07 | Fabricate solar panel foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 08 | Install hardtop stanchion AFT foundation - Port | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 163-04-02-L 09 | Install hardtop stanchion AFT foundation - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 10 | Install hardtop stanchion FWD foundation - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 11 | Install hardtop stanchion FWD foundation - STBD | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 163-04-02-L 12 | Install radar arch foundation - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 13 | Install radar arch foundation - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-02-L 14 | Install solar panel foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-03 | Wire Trays | 12 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 163-04-03-L | Labor | 12 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 163-04-03-L 01 | Fabricate access panels to cable tray | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-03-L 02 | Install access panels to cable tray | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-03-L 03 | Install cable trays | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04 | Mast Piping | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 163-04-04-L | Labor | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 01 | Fabricate fuel tank vent piping - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 02 | Fabricate fuel tank vent piping - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 03 | Fabricate black/Grey tank vent piping - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 04 | Fabricate black/Grey tank vent piping - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 05 | Install fuel tank vent piping - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 06 | Install fuel tank vent piping - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 07 | Install black/Grey tank vent piping - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 163-04-04-L 08 | Install black/Grey tank vent piping - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 164 | Mast Arch | 208 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 164-04 | Metal Fabrication | 208 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 164-04-01 | Mast Arch Framing | 104 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 164-04-01-L | Labor | 104 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 164-04-01-L 01 | Fabricate transverse frames | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 164-04-01-L 02 | Fabricate longitudinal girders | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 164-04-01-L 03 | Fabricate longitidinal plate stiffeners | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-01-L 04 | Fabricate shell plating | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 164-04-01-L 05 | Prepare jig | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-01-L 06 | Install transverse frames | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 164-04-01-L 07 | Install longitudinal girders | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 164-04-01-L 08 | Install longitidinal plate stiffeners | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 164-04-01-L 09 | Install shell plating | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 164-04-02 | Foundations | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 164-04-02-L | Labor | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 164-04-02-L 01 | Fabricate lower foundation to hardtop - Port | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 164-04-02-L 02 | Fabricate lower foundation to hardtop - STBD | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-02-L 03 | Fabricate mast foundation | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-02-L 04 | Install lower foundation to hardtop - Port | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 164-04-02-L 05 | Install lower foundation to hardtop - STBD | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 164-04-02-L 06 | Install mast foundation | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-03 | Internal Wire Trays | 24 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 164-04-03-L | Labor | 24 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 164-04-03-L 01 | Fabricate access panels to cable tray | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-03-L 02 | Install access panels to cable tray | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-03-L 03 | Install cable trays | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-04 | Mast Arch Pipe Terminations | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-04-L | Labor | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-04-L 01 | Install fuel tank vent piping - Port | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-04-L 02 | Install fuel tank vent piping - STBD | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-04-L 03 | Install black/Grey tank vent piping - Port | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 164-04-04-L 04 | Install black/Grey tank vent piping - STBD | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 165 | Electronic Mast | 296 | 12/03/24 | 12/13/24 | 1.8w | : | |
| 165-04 | Metal Fabrication | 296 | 12/03/24 | 12/13/24 | 1.8w | : | |
| 165-04-01 | Mast Arch Framing | 216 | 12/03/24 | 12/13/24 | 72.0h | : | |
| 165-04-01-L | Labor | 216 | 12/03/24 | 12/13/24 | 72.0h | : | |
| 165-04-01-L 01 | Fabricate transverse frames | 24 | 12/03/24 | 12/05/24 | 24.0h | : | |
| 165-04-01-L 02 | Fabricate longitudinal girders | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 165-04-01-L 03 | Fabricate longitidinal plate stiffeners | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 165-04-01-L 04 | Fabricate shell plating | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 165-04-01-L 05 | Prepare jig | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 165-04-01-L 06 | Install shell plating | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 165-04-01-L 07 | Install transverse frames | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 165-04-01-L 08 | Install longitudinal girders | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 165-04-01-L 09 | Install longitidinal plate stiffeners | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 165-04-02 | Foundations | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 165-04-02-L | Labor | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 165-04-02-L 01 | Fabricate foundation to radar arch | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 165-04-02-L 02 | Install foundation to radar arch | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 165-04-03 | Internal Wire Trays | 48 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 165-04-03-J | Labor | 48 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 165-04-03-J 01 | Fabricate access panels to cable tray | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 165-04-03-J 02 | Install access panels to cable tray | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 165-04-03-J 03 | Install cable trays | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 166 | Module Connection | 16 | 12/13/24 | 12/13/24 | 0.6w | : | |
| 166-04 | Metal Fabrication | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 166-04-01 | Block 201 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 166-04-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 166-04-01-L 01 | Trim and level block 201 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 166-04-01-L 02 | Final install block 201 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 166-04-02 | Block 202 | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 166-04-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 166-04-02-L 01 | Trim and level block 202 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 166-04-02-L 02 | Final install block 202 to main deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168 | Flybridge - Furniture | 308 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 168-04 | Metal Fabrication | 308 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 168-04-01 | Control Console | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-01-L | Labor | 16 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-01-L 01 | Fabricate control console framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-01-L 02 | Fabricate control console plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-01-L 03 | Assemble control console | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-01-L 04 | Install control console to bulkhead | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-02 | Wing Station Reccess - STBD | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-02-L 01 | Fabricate wing station reccess box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-02-L 02 | Install wing station box into bulwark | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03 | Console Bench Seat - Port | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-03-L | Labor | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-03-L 01 | Fabricate console bench seat framing - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03-L 02 | Fabricate console bench seat plating - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03-L 03 | Fabricate console bench seat storage hatches - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03-L 04 | Assemble console bench seat - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03-L 05 | Install console bench seat hatch drains - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03-L 06 | Install console bench seat storage hatches - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-03-L 07 | Install console bench seat to deck - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04 | Console Bench Seat - STBD | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-04-L | Labor | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-04-L 01 | Fabricate console bench seat framing - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04-L 02 | Fabricate console bench seat plating - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04-L 03 | Fabricate console bench seat storage hatches - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04-L 04 | Assemble console bench seat - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04-L 05 | Install console bench seat hatch drains - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04-L 06 | Install console bench seat storage hatches - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-04-L 07 | Install console bench seat to deck - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05 | Dining Table Bench Seat - Port | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-05-L | Labor | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-05-L 01 | Fabricate dining table bench seat framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05-L 02 | Fabricate dining table bench seat plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05-L 03 | Fabricate dining table bench seat storage hatches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05-L 04 | Assemble dining table bench seat | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05-L 05 | Install dining table bench seat hatch drains | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05-L 06 | Install dining table bench seat storage hatches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-05-L 07 | Install dining table bench seat to deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06 | AFT Settee - Port | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-06-L | Labor | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-06-L 01 | Fabricate AFT settee framing - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06-L 02 | Fabricate AFT settee plating - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06-L 03 | Fabricate AFT settee storage hatches - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06-L 04 | Assemble AFT settee - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06-L 05 | Install AFT settee hatch drains - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06-L 06 | Install AFT settee storage hatches - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-06-L 07 | Install AFT settee deck - Port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07 | AFT Settee - STBD | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-07-L | Labor | 28 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-07-L 01 | Fabricate AFT settee framing - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07-L 02 | Fabricate AFT settee plating - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07-L 03 | Fabricate AFT settee storage hatches - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07-L 04 | Assemble AFT settee - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07-L 05 | Install AFT settee hatch drains - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07-L 06 | Install AFT settee storage hatches - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-07-L 07 | Install AFT settee to deck - STBD | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08 | Wet Bar | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-08-L | Labor | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 01 | Fabricate wet bar framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 02 | Fabricate wet bar plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 03 | Fabricate wet bar upper platform | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 04 | Fabricate wet bar door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 05 | Assemble wet bar | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 06 | Install wet bar upper platform | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 07 | Install wet bar door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-08-L 08 | Install wet bar to deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09 | Jacuzzi Enclosure | 48 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-09-L | Labor | 48 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 01 | Fabricate jacuzzi enclosure framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 02 | Fabricate jacuzzi enclosure plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 03 | Fabricate jacuzzi drain channels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 04 | Fabricate jacuzzi steps | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 05 | Fabricate jacuzzi door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 06 | Fabricate jacuzzi equipment foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 07 | Assemble jacuzzi | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 08 | Install jacuzzi drain channels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 09 | Install jacuzzi steps | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 10 | Install jacuzzi door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 11 | Install jacuzzi equipment foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-09-L 12 | Install jacuzzi to deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10 | BBQ Cabinet | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-10-L | Labor | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 01 | Fabricate BBQ cabinet framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 02 | Fabricate BBQ cabinet plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 03 | Fabricate BBQ cabinet door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 04 | Fabricate BBQ cabinet equipment foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 05 | Assemble BBQ cabinet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 06 | Install BBQ cabinet door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 07 | Install BBQ cabinet equipment foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-10-L 08 | Install BBQ cabinet to deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11 | Stairway Cabinet | 32 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 168-04-11-L | Labor | 32 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 01 | Fabricate stairway cabinet framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 02 | Fabricate stairway cabinet plating | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 03 | Fabricate stairway cabinet door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 04 | Fabricate stairway cabinet equipment foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 05 | Assemble stairway cabinet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 06 | Install stairway cabinet door framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 07 | Install stairway cabinet equipment foundations | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 168-04-11-L 08 | Install stairway cabinet to deck | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |