1.2 Department Schedules
004. Metal Fabrication
.
Department Catagory Schedules
WBSProject CategoriesLabor Hrs.Start DateFinish DatesDuration:Comments
DEPARTMENT TOTAL26,04807/19/2412/13/24.:.
1HULL/SUPERSTRUCTURE SHELL26,04807/19/2412/13/24175.2w:
******** *********************************************************************************
.
Department Job Schedules
WBSJob DescriptionLabor Hrs.Start DateFinish DateDuration:Comments
1HULL/SUPERSTRUCTURE SHELL26,04807/19/2412/13/24175.2w:
102  Hull Module - Block 13,56012/04/2412/13/24175.2w:
102-04    Metal Fabrication3,56012/04/2412/13/246,825.0h:
102-04-01      Parts Preparation48012/09/2412/13/246,825.0h:
102-04-01-L        Labor48012/09/2412/13/24120.0h:
102-04-01-L 01          Prepare Jig to receive frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
102-04-01-L 02          Clean and prepare frame parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
102-04-01-L 03          Clean and prepare shell plate parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
102-04-02      Parts Assemble96012/04/2412/13/246,782.0h:
102-04-02-L        Labor96012/04/2412/13/24240.0h:
102-04-02-L 01          Assemble prepared transverse frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-02-L 02          Assemble prepared longitudinal frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-02-L 03          Assemble prepared parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-02-L 04          Assemble prepared integral piping parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-03      Frame installation 1,20012/04/2412/13/246,660.0h:
102-04-03-L        Labor1,20012/04/2412/13/24300.0h:
102-04-03-L 01          Install prepared transverse frames to jig24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-03-L 02          Install prepared longitudinal frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-03-L 03          Install prepared plate stinnener frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-03-L 04          Install remaining prepared parts onto jig as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-03-L 05          Install integral piping if required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-04      Shell plate installation 80012/04/2412/13/246,346.0h:
102-04-04-L        Labor80012/04/2412/13/24200.0h:
102-04-04-L 01          Install all shell plate to module framing24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
102-04-04-L 03          Install all topside shell plates24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
102-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
102-04-05      Prepartions for connection12012/09/2412/13/246,174.3h:
102-04-05-L        Labor12012/09/2412/13/2440.0h:
102-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
103  Hull Module - Block 23,56012/04/2412/13/24171.3w:
103-04    Metal Fabrication3,56012/04/2412/13/246,569.0h:
103-04-01      Parts Preparation48012/09/2412/13/246,409.0h:
103-04-01-L        Labor48012/09/2412/13/24120.0h:
103-04-01-L 01          Prepare Jig to receive frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
103-04-01-L 02          Clean and prepare frame parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
103-04-01-L 03          Clean and prepare shell plate parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
103-04-02      Parts Assemble96012/04/2412/13/246,548.0h:
103-04-02-L        Labor96012/04/2412/13/24240.0h:
103-04-02-L 01          Assemble prepared transverse frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-02-L 02          Assemble prepared longitudinal frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-02-L 03          Assemble prepared parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-02-L 04          Assemble prepared integral piping parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-03      Frame installation 1,20012/04/2412/13/246,569.0h:
103-04-03-L        Labor1,20012/04/2412/13/24300.0h:
103-04-03-L 01          Install prepared transverse frames to jig24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-03-L 02          Install prepared longitudinal frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-03-L 03          Install prepared plate stinnener frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-03-L 04          Install remaining prepared parts onto jig as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-03-L 05          Install integral piping if required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-04      Shell plate installation 80012/04/2412/13/246,411.0h:
103-04-04-L        Labor80012/04/2412/13/24200.0h:
103-04-04-L 01          Install all shell plate to module framing24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
103-04-04-L 03          Install all topside shell plates24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
103-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
103-04-05      Prepartions for connection12012/09/2412/13/246,209.0h:
103-04-05-L        Labor12012/09/2412/13/2440.0h:
103-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
104  Hull Module - Block 33,56012/04/2412/13/24163.5w:
104-04    Metal Fabrication3,56012/04/2412/13/246,539.0h:
104-04-01      Parts Preparation48012/09/2412/13/246,539.0h:
104-04-01-L        Labor48012/09/2412/13/24120.0h:
104-04-01-L 01          Prepare Jig to receive frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
104-04-01-L 02          Clean and prepare frame parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
104-04-01-L 03          Clean and prepare shell plate parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
104-04-02      Parts Assemble96012/04/2412/13/246,405.0h:
104-04-02-L        Labor96012/04/2412/13/24240.0h:
104-04-02-L 01          Assemble prepared transverse frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-02-L 02          Assemble prepared longitudinal frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-02-L 03          Assemble prepared parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-02-L 04          Assemble prepared integral piping parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-03      Frame installation 1,20012/04/2412/13/246,244.0h:
104-04-03-L        Labor1,20012/04/2412/13/24300.0h:
104-04-03-L 01          Install prepared transverse frames to jig24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-03-L 02          Install prepared longitudinal frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-03-L 03          Install prepared plate stinnener frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-03-L 04          Install remaining prepared parts onto jig as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-03-L 05          Install integral piping if required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-04      Shell plate installation 80012/04/2412/13/245,969.0h:
104-04-04-L        Labor80012/04/2412/13/24200.0h:
104-04-04-L 01          Install all shell plate to module framing24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
104-04-04-L 03          Install all topside shell plates24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
104-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
104-04-05      Prepartions for connection12012/09/2412/13/245,819.0h:
104-04-05-L        Labor12012/09/2412/13/2440.0h:
104-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
105  Hull Module - Block 43,56012/04/2412/13/24160.6w:
105-04    Metal Fabrication3,56012/04/2412/13/246,422.0h:
105-04-01      Parts Preparation48012/09/2412/13/246,422.0h:
105-04-01-L        Labor48012/09/2412/13/24120.0h:
105-04-01-L 01          Prepare Jig to receive frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
105-04-01-L 02          Clean and prepare frame parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
105-04-01-L 03          Clean and prepare shell plate parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
105-04-02      Parts Assemble96012/04/2412/13/246,405.0h:
105-04-02-L        Labor96012/04/2412/13/24240.0h:
105-04-02-L 01          Assemble prepared transverse frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-02-L 02          Assemble prepared longitudinal frames24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-02-L 03          Assemble prepared parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-02-L 04          Assemble prepared integral piping parts as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-03      Frame installation 1,20012/04/2412/13/246,361.0h:
105-04-03-L        Labor1,20012/04/2412/13/24300.0h:
105-04-03-L 01          Install prepared transverse frames to jig24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-03-L 02          Install prepared longitudinal frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-03-L 03          Install prepared plate stinnener frames onto module24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-03-L 04          Install remaining prepared parts onto jig as required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-03-L 05          Install integral piping if required24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-04      Shell plate installation 80012/04/2412/13/246,073.0h:
105-04-04-L        Labor80012/04/2412/13/24200.0h:
105-04-04-L 01          Install all shell plate to module framing24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
105-04-04-L 03          Install all topside shell plates24012/04/2412/13/2460.0h:Require crew interior boxes loaded before task complete
105-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
105-04-05      Prepartions for connection12012/09/2412/13/245,823.3h:
105-04-05-L        Labor12012/09/2412/13/2440.0h:
105-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
111  Module Connection1612/13/2412/13/240.6w:
111-04    Metal Fabrication1612/13/2412/13/240.2w:
111-04-01      Block 101812/13/2412/13/248.0h:
111-04-01-L        Labor812/13/2412/13/240.2w:
111-04-01-L 01          Trim and level block 201 to main deck 412/13/2412/13/244.0h:
111-04-01-L 02          Final install block 201 to main deck412/13/2412/13/244.0h:
111-04-02      Block 102812/13/2412/13/248.0h:
111-04-02-L        Labor812/13/2412/13/240.2w:
111-04-02-L 01          Trim and level block 202 to main deck 412/13/2412/13/244.0h:
111-04-02-L 02          Final install block 202 to main deck412/13/2412/13/244.0h:
112  Integral Tanks34807/19/2412/13/2421.1w:
112-04    Metal fabrication34807/19/2412/13/2421.1w:
112-04-01      Fuel Oil - Port Tank Day2007/19/2412/13/24845.0h:
112-04-01-L        Labor2007/19/2412/13/24845.0h:
112-04-01-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-01-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-01-L 03          Fabricate tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-01-L 04          Install tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-01-L 05          Install tank access hatch412/13/2412/13/244.0h:
112-04-02      Fuel Oil - STBD Tank Day1207/19/2412/13/24845.0h:
112-04-02-L        Labor1207/19/2412/13/24845.0h:
112-04-02-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-02-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-02-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-03      Fuel Oil - Port Tank Mid2007/19/2412/13/24845.0h:
112-04-03-L        Labor2007/19/2412/13/24845.0h:
112-04-03-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-03-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-03-L 03          Fabricate tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-03-L 04          Install tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-03-L 05          Install tank access hatch412/13/2412/13/244.0h:
112-04-04      Fuel Oil - STBD Tank Mid1207/19/2412/13/24845.0h:
112-04-04-L        Labor1207/19/2412/13/24845.0h:
112-04-04-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-04-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-04-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-05      Fuel Oil - Port Tank FWD2007/19/2412/13/24845.0h:
112-04-05-L        Labor2007/19/2412/13/24845.0h:
112-04-05-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-05-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-05-L 03          Fabricate tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-05-L 04          Install tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-05-L 05          Install tank access hatch412/13/2412/13/244.0h:
112-04-06      Fuel Oil - STBD Tank FWD1207/19/2412/13/24845.0h:
112-04-06-L        Labor1207/19/2412/13/24845.0h:
112-04-06-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-06-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-06-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-07      Freshwater Tank - Port2007/19/2412/13/24845.0h:
112-04-07-L        Labor2007/19/2412/13/24845.0h:
112-04-07-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-07-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-07-L 03          Fabricate tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-07-L 04          Install tank vent cross-over pipe412/13/2412/13/244.0h:
112-04-07-L 05          Install tank access hatch412/13/2412/13/244.0h:
112-04-08      Freshwater Tank - STBD1207/19/2412/13/24845.0h:
112-04-08-L        Labor1207/19/2412/13/24845.0h:
112-04-08-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-08-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-08-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-09      Blackwater Tank2007/19/2412/13/24845.0h:
112-04-09-L        Labor2007/19/2412/13/24845.0h:
112-04-09-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-09-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-09-L 03          Fabricate intake pipe412/13/2412/13/244.0h:
112-04-09-L 04          Install intake pipe412/13/2412/13/244.0h:
112-04-09-L 05          Install tank access hatch412/13/2412/13/244.0h:
112-04-10      Greywater Tank - AFT1207/19/2412/13/24845.0h:
112-04-10-L        Labor1207/19/2412/13/24845.0h:
112-04-10-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-10-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-10-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-11      Greywater Tank - FWD4407/19/2412/13/24845.0h:
112-04-11-L        Labor4407/19/2412/13/24845.0h:
112-04-11-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-11-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-11-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-11-L 04          Fabricate FWD intake pipe412/13/2412/13/244.0h:
112-04-11-L 05          Fabricate AFT intake pipe412/13/2412/13/244.0h:
112-04-11-L 06          Fabricate vent piping to Aft tank412/13/2412/13/244.0h:
112-04-11-L 07          Fabricate suction piping to Aft tank412/13/2412/13/244.0h:
112-04-11-L 08          Install FWD intake pipe412/13/2412/13/244.0h:
112-04-11-L 09          Install AFT intake pipe412/13/2412/13/244.0h:
112-04-11-L 10          Install vent piping to Aft tank412/13/2412/13/244.0h:
112-04-11-L 11          Install suction piping to Aft tank412/13/2412/13/244.0h:
112-04-12      UREA Tank - PORT3607/19/2412/13/24845.0h:
112-04-12-L        Labor3607/19/2412/13/24845.0h:
112-04-12-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-12-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-12-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-12-L 04          Fabricate tank fill pipe412/13/2412/13/244.0h:
112-04-12-L 05          Fabricate tank vent piping412/13/2412/13/244.0h:
112-04-12-L 06          Fabricate tank suction piping412/13/2412/13/244.0h:
112-04-12-L 07          Install tank fill pipe412/13/2412/13/244.0h:
112-04-12-L 08          Install tank vent piping412/13/2412/13/244.0h:
112-04-12-L 09          Install tank suction piping412/13/2412/13/244.0h:
112-04-13      UREA Tank - STBD3607/19/2412/13/24845.0h:
112-04-13-L        Labor3607/19/2412/13/24845.0h:
112-04-13-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-13-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-13-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-13-L 04          Fabricate tank fill pipe412/13/2412/13/244.0h:
112-04-13-L 05          Fabricate tank vent piping412/13/2412/13/244.0h:
112-04-13-L 06          Fabricate tank suction piping412/13/2412/13/244.0h:
112-04-13-L 07          Install tank fill pipe412/13/2412/13/244.0h:
112-04-13-L 08          Install tank vent piping412/13/2412/13/244.0h:
112-04-13-L 09          Install tank suction piping412/13/2412/13/244.0h:
112-04-14      Lubricating Oil Tank - PORT3607/19/2412/13/24845.0h:
112-04-14-L        Labor3607/19/2412/13/24845.0h:
112-04-14-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-14-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-14-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-14-L 04          Fabricate tank fill pipe412/13/2412/13/244.0h:
112-04-14-L 05          Fabricate tank vent piping412/13/2412/13/244.0h:
112-04-14-L 06          Fabricate tank suction piping412/13/2412/13/244.0h:
112-04-14-L 07          Install tank fill pipe412/13/2412/13/244.0h:
112-04-14-L 08          Install tank vent piping412/13/2412/13/244.0h:
112-04-14-L 09          Install tank suction piping412/13/2412/13/244.0h:
112-04-15      Lubricating Oil Tank - STBD3607/19/2412/13/24845.0h:
112-04-15-L        Labor3607/19/2412/13/24845.0h:
112-04-15-L 01          Fabricate tank gauge flange plate407/19/2407/19/244.0h:
112-04-15-L 02          Install all tank gauge flange plate412/13/2412/13/244.0h:
112-04-15-L 03          Install tank access hatch412/13/2412/13/244.0h:
112-04-15-L 04          Fabricate tank fill pipe412/13/2412/13/244.0h:
112-04-15-L 05          Fabricate tank vent piping412/13/2412/13/244.0h:
112-04-15-L 06          Fabricate tank suction piping412/13/2412/13/244.0h:
112-04-15-L 07          Install tank fill pipe412/13/2412/13/244.0h:
112-04-15-L 08          Install tank vent piping412/13/2412/13/244.0h:
112-04-15-L 09          Install tank suction piping412/13/2412/13/244.0h:
113  Hull Watertight Bulkheads2412/13/2412/13/240.2w:
113-04    Metal Fabrication2412/13/2412/13/248.0h:
113-04-01      Bulkhead 28812/13/2412/13/246.0h:
113-04-01-L        Labor812/13/2412/13/244.0h:
113-04-01-L 01          Fit up remaining bulkhead plate to fit inside frame412/13/2412/13/244.0h:Require crew interior boxes loaded before task complete
113-04-01-L 02          Final install remaining bulkhead plate insert 412/13/2412/13/244.0h:Require crew interior boxes loaded before task complete
113-04-02      Bulkhead 14812/13/2412/13/246.0h:
113-04-02-L        Labor812/13/2412/13/244.0h:
113-04-02-L 01          Fit up remaining bulkhead plate to fit inside frame412/13/2412/13/244.0h:Require Crew & Guest interior boxes loaded before task complete
113-04-02-L 02          Final install remaining bulkhead plate insert 412/13/2412/13/244.0h:Require Crew & Guest interior boxes loaded before task complete
113-04-03      Bulkhead 08812/13/2412/13/248.0h:
113-04-03-L        Labor812/13/2412/13/244.0h:
113-04-03-L 01          Fit up remaining bulkhead plate to fit inside frame412/13/2412/13/244.0h:Require Crew & Guest interior boxes loaded before task complete
113-04-03-L 02          Final install remaining bulkhead plate insert 412/13/2412/13/244.0h:Require Crew & Guest interior boxes loaded before task complete
116  Forepeak11212/12/2412/13/240.4w:
116-04    Metal fabrication6012/12/2412/13/2416.0h:
116-04-01      Chain Locker3612/13/2412/13/248.0h:
116-04-01-P        Labor3612/13/2412/13/240.2w:
116-04-01-P 01          Fabricate anchor hawse pipe412/13/2412/13/244.0h:
116-04-01-P 02          Fabricate drain piping to hawse pipe discharge412/13/2412/13/244.0h:
116-04-01-P 03          Install chain bin stachions412/13/2412/13/244.0h:
116-04-01-P 04          Install chain bin foundations - Port412/13/2412/13/244.0h:
116-04-01-P 05          Install chain bin foundations - STBD412/13/2412/13/244.0h:
116-04-01-P 06          Install chain bin rails - Port412/13/2412/13/244.0h:
116-04-01-P 07          Install chain bin rails - STBD412/13/2412/13/244.0h:
116-04-01-P 08          Install light switch support bracket412/13/2412/13/244.0h:
116-04-01-P 09          Install access ladder412/13/2412/13/244.0h:
116-04-02      Access hatch2412/12/2412/13/2416.0h:
116-04-02-P        Labor2412/12/2412/13/240.4w:
116-04-02-P 01          Fabricate access hatch raised deck plate412/12/2412/12/244.0h:
116-04-02-P 02          Fabricate access hatch coaming plate412/13/2412/13/244.0h:
116-04-02-P 03          Fabricate access hatch attachment flange plate412/13/2412/13/244.0h:
116-04-02-P 04          Install access hatch raised deck plate412/12/2412/12/244.0h:
116-04-02-P 05          Install access hatch coaming plate412/12/2412/12/244.0h:
116-04-02-P 06          Install access hatch attachment flange plate412/13/2412/13/244.0h:
116-05    Metal Welding5212/12/2412/13/241.5d:
116-05-01      Chain Locker3612/12/2412/13/2412.0h:
116-05-01-P        Labor3612/12/2412/13/240.3w:
116-05-01-P 01          Weld anchor hawse pipe412/12/2412/12/244.0h:
116-05-01-P 02          Weld drain piping to hawse pipe discharge412/13/2412/13/244.0h:
116-05-01-P 03          Weld chain bin stachions412/13/2412/13/244.0h:
116-05-01-P 04          Weld chain bin foundations - Port412/13/2412/13/244.0h:
116-05-01-P 05          Weld chain bin foundations - STBD412/13/2412/13/244.0h:
116-05-01-P 06          Weld chain bin rails - Port412/13/2412/13/244.0h:
116-05-01-P 07          Weld chain bin rails - STBD412/13/2412/13/244.0h:
116-05-01-P 08          Weld light switch support bracket412/13/2412/13/244.0h:
116-05-01-P 09          Weld access ladder412/13/2412/13/244.0h:
116-05-02      Access hatch1612/12/2412/13/2412.0h:
116-05-02-P        Labor1612/12/2412/13/240.3w:
116-05-02-P 01          Weld access hatch deck raised plate412/12/2412/12/244.0h:
116-05-02-P 02          Weld access hatch coaming plate412/13/2412/13/244.0h:
116-05-02-P 03          Weld access hatch attachment flange plate412/13/2412/13/244.0h:
116-05-02-P 04          Weld light switch support bracket412/13/2412/13/244.0h:
117  Machinery Room - FWD 26412/06/2412/13/241.1w:
117-04    Metal Fabrication26412/06/2412/13/2444.0h:
117-04-01      Foundations3212/13/2412/13/244.0h:
117-04-01-L        Labor3212/13/2412/13/244.0h:
117-04-01-L 01          Fabricate DC bilge pump foundations412/13/2412/13/244.0h:
117-04-01-L 02          Fabricate overhead light foundations412/13/2412/13/244.0h:
117-04-01-L 03          Fabricate access hatch coaming412/13/2412/13/244.0h:
117-04-01-L 04          Fabricate access steps foundations412/13/2412/13/244.0h:
117-04-01-L 05          Install DC bilge pump foundations412/13/2412/13/244.0h:
117-04-01-L 06          Install overhead light foundations412/13/2412/13/244.0h:
117-04-01-L 07          Install access hatch coaming412/13/2412/13/244.0h:
117-04-01-L 08          Install access steps foundations412/13/2412/13/244.0h:
117-04-02      Intake/Discharge Standpipes2012/13/2412/13/244.0h:
117-04-02-L        Labor2012/13/2412/13/240.1w:
117-04-02-L 01          Fabricate aux overboard thru hull - Port412/13/2412/13/244.0h:
117-04-02-L 02          Fabricate aux overboard thru hull - STBD412/13/2412/13/244.0h:
117-04-02-L 03          Install aux overboard thru hull - Port412/13/2412/13/244.0h:
117-04-02-L 04          Install aux overboard thru hull - STBD412/13/2412/13/244.0h:
117-04-02-L 05          Lloyds Inspection412/13/2412/13/244.0h:
117-04-03      Transducers2012/13/2412/13/244.0h:
117-04-03-L        Labor2012/13/2412/13/240.1w:
117-04-03-L 01          Fabricate speed log transducer housing412/13/2412/13/244.0h:
117-04-03-L 02          Fabricate sonar transducer housing412/13/2412/13/244.0h:
117-04-03-L 03          Install speed log transducer housing412/13/2412/13/244.0h:
117-04-03-L 04          Install sonar transducer housing412/13/2412/13/244.0h:
117-04-03-L 05          Lloyds Inspection412/13/2412/13/244.0h:
117-04-04      Freshwater Pumps6412/12/2412/13/2416.0h:
117-04-04-L        Labor6412/12/2412/13/240.4w:
117-04-04-L 01          Fabricate pump foundations412/12/2412/12/244.0h:
117-04-04-L 02          Fabricate high pressur filter foundations412/12/2412/12/244.0h:
117-04-04-L 03          Fabricate distribution manifold foundations412/13/2412/13/244.0h:
117-04-04-L 04          Fabricate waterheater foundations Port Aft412/13/2412/13/244.0h:
117-04-04-L 05          Fabricate waterheater foundations Port FWD412/13/2412/13/244.0h:
117-04-04-L 06          Fabricate waterheater foundations STBD Aft412/13/2412/13/244.0h:
117-04-04-L 07          Fabricate waterheater foundations STBD FWD412/13/2412/13/244.0h:
117-04-04-L 08          Fabricate control panel mounts412/13/2412/13/244.0h:
117-04-04-L 09          Install pump foundations412/12/2412/12/244.0h:
117-04-04-L 10          Install high pressur filter foundations412/12/2412/12/244.0h:
117-04-04-L 11          Install distribution manifold foundations412/13/2412/13/244.0h:
117-04-04-L 12          Install waterheater foundations Port Aft412/13/2412/13/244.0h:
117-04-04-L 13          Install waterheater foundations Port FWD412/13/2412/13/244.0h:
117-04-04-L 14          Install waterheater foundations STBD Aft412/13/2412/13/244.0h:
117-04-04-L 15          Install waterheater foundations STBD FWD412/13/2412/13/244.0h:
117-04-04-L 16          Install control panel mounts412/13/2412/13/244.0h:
117-04-05      Watermaker System11212/06/2412/13/2444.0h:
117-04-05-L        Labor11212/06/2412/13/241.1w:
117-04-05-L 01          Fabricate L.P pump foundations1612/06/2412/10/2416.0h:
117-04-05-L 02          Fabricate H.P pump foundations1612/10/2412/12/2416.0h:
117-04-05-L 03          Fabricate membrane foundations1212/12/2412/13/2412.0h:
117-04-05-L 04          Fabricate all filter foundations1212/12/2412/13/2412.0h:
117-04-05-L 05          Install L.P pump foundations1612/06/2412/10/2416.0h:
117-04-05-L 06          Install H.P pump foundations1612/10/2412/12/2416.0h:
117-04-05-L 07          Install membrane foundations1212/12/2412/13/2412.0h:
117-04-05-L 08          Install all filter foundations1212/12/2412/13/2412.0h:
117-04-06      Floor Framing1612/13/2412/13/248.0h:
117-04-06-L        Labor1612/13/2412/13/240.2w:
117-04-06-L 01          Fabricate all floor frame panels412/13/2412/13/244.0h:
117-04-06-L 02          Fabricate floor mount clips412/13/2412/13/244.0h:
117-04-06-L 03          Install floor mount clips412/13/2412/13/244.0h:
117-04-06-L 04          Install all floor frame panels412/13/2412/13/244.0h:
118  Engine room6412/12/2412/13/240.4w:
118-04    Metal fabrication6412/12/2412/13/2416.0h:
118-04-01      Foundations2412/13/2412/13/246.0h:
118-04-01-L        Labor2412/13/2412/13/240.1w:
118-04-01-L 01          Fabricate lower stanchion foundations FR10412/13/2412/13/244.0h:
118-04-01-L 02          Fabricate upper stanchion foundations FR10412/13/2412/13/244.0h:
118-04-01-L 03          Fabricate DC bilge pump foundations412/13/2412/13/244.0h:
118-04-01-L 04          Install lower stanchion foundations FR10412/13/2412/13/244.0h:
118-04-01-L 05          Install upper stanchion foundations FR10412/13/2412/13/244.0h:
118-04-01-L 06          Install DC bilge pump foundations412/13/2412/13/244.0h:
118-04-02      Ceiling Framing1612/12/2412/13/2416.0h:
118-04-02-L        Labor1612/12/2412/13/240.4w:
118-04-02-L 01          Fabricate all overhead frame panels412/12/2412/12/244.0h:
118-04-02-L 02          Fabricate overhead mount clips412/12/2412/12/244.0h:
118-04-02-L 03          Install outer and aft overhead frame panels412/13/2412/13/244.0h:
118-04-02-L 04          Dry-fit center overhead panels, remove for engine installation412/13/2412/13/244.0h:
118-04-03      Floor Framing1612/12/2412/13/2416.0h:
118-04-03-L        Labor1612/12/2412/13/240.4w:
118-04-03-L 01          Fabricate all floor frame panels412/12/2412/12/244.0h:
118-04-03-L 02          Fabricate floor mount clips412/12/2412/12/244.0h:
118-04-03-L 03          Install under-floor cable trays412/13/2412/13/244.0h:
118-04-03-L 04          Install all floor frame panels412/13/2412/13/244.0h:
118-04-04      MISC - Updated Items812/13/2412/13/248.0h:
118-04-04-L        Labor812/13/2412/13/240.2w:
118-04-04-L 01          Rework fuel fill pipes in FWD overhead - Port412/13/2412/13/244.0h:
118-04-04-L 02          Rework fuel fill pipes in FWD overhead - STBD412/13/2412/13/244.0h:
120  Garage17212/11/2412/13/240.5w:
120-04    Metal Fabrication17212/11/2412/13/2420.0h:
120-04-01      Garage door Foundations2812/12/2412/13/2416.0h:
120-04-01-L        Labor2812/12/2412/13/240.4w:
120-04-01-L 01          Fabricate garage door foundation frame412/13/2412/13/244.0h:
120-04-01-L 02          Fabricate garage door hinges412/12/2412/12/244.0h:
120-04-01-L 03          Fabricate garage door hinge fouldations412/13/2412/13/244.0h:
120-04-01-L 04          Fabricate garage door dog fouldations412/12/2412/12/244.0h:
120-04-01-L 05          Install garage door foundations to structure412/13/2412/13/244.0h:
120-04-01-L 06          Install garage door hinges412/13/2412/13/244.0h:
120-04-01-L 07          Install garage door hinge fouldations412/13/2412/13/244.0h:
120-04-02      Garage Door7212/11/2412/13/2420.0h:
120-04-02-L        Labor7212/13/2412/13/244.0h:
120-04-02-L 01          Fabricate door transverse frames412/13/2412/13/244.0h:
120-04-02-L 02          Fabricate door longtitudinal frames412/13/2412/13/244.0h:
120-04-02-L 03          Fabricate door plate stiffener frames412/13/2412/13/244.0h:
120-04-02-L 04          Fabricate door shell plating412/13/2412/13/244.0h:
120-04-02-L 05          Fabricate door hinge foundation box412/13/2412/13/244.0h:
120-04-02-L 06          Fabricate door accuator foundations412/13/2412/13/244.0h:
120-04-02-L 07          Fabricate sides to new door412/13/2412/13/244.0h:
120-04-02-L 08          Fabricate dog foundations to door structure412/13/2412/13/244.0h:
120-04-02-L 09          Fabricate inner plate for door412/13/2412/13/244.0h:
120-04-02-L 10          Install door transverse frames412/13/2412/13/244.0h:
120-04-02-L 11          Install door longtitudinal frames412/13/2412/13/244.0h:
120-04-02-L 12          Install door plate stiffener frames412/13/2412/13/244.0h:
120-04-02-L 13          Install door shell plating412/13/2412/13/244.0h:
120-04-02-L 14          Install door hinge foundation box412/13/2412/13/244.0h:
120-04-02-L 15          Install door accuator foundations412/13/2412/13/244.0h:
120-04-02-L 16          Install sides to new door412/13/2412/13/244.0h:
120-04-02-L 17          Install dog foundations to door structure412/13/2412/13/244.0h:
120-04-02-L 18          Install inner plate for door412/13/2412/13/244.0h:
120-04-03      Foundations1612/13/2412/13/248.0h:
120-04-03-L        Labor1612/13/2412/13/240.2w:
120-04-03-L 01          Fabricate tender mount foundations412/13/2412/13/244.0h:
120-04-03-L 02          Fabricate DC bilge pump foundations412/13/2412/13/244.0h:
120-04-03-L 03          Install tender mount foundations412/13/2412/13/244.0h:
120-04-03-L 04          Install DC bilge pump foundations412/13/2412/13/244.0h:
120-04-04      Ceiling Framing812/13/2412/13/248.0h:
120-04-04-L        Labor812/13/2412/13/240.2w:
120-04-04-L 01          Fabricate all overhead frame panels412/13/2412/13/244.0h:
120-04-04-L 02          Fabricate overhead mount support brackets412/13/2412/13/244.0h:
120-04-05      Floor Framing1212/13/2412/13/248.0h:
120-04-05-L        Labor1212/13/2412/13/240.2w:
120-04-05-L 01          Fabricate all floor frame panels412/13/2412/13/244.0h:
120-04-05-L 02          Fabricate floor mount clips412/13/2412/13/244.0h:
120-04-05-L 03          Install all floor frame panels412/13/2412/13/244.0h:
120-04-06      Work Bench Framing812/13/2412/13/248.0h:
120-04-06-L        Labor812/13/2412/13/240.2w:
120-04-06-L 01          Fabricate work bench framing412/13/2412/13/244.0h:
120-04-06-L 02          Install work bench framing412/13/2412/13/244.0h:
120-04-07      Passerelle Ladder1612/13/2412/13/245.0h:
120-04-07-L        Labor1612/13/2412/13/244.0h:
120-04-07-L 01          Fabricate passerelle foundation plates412/13/2412/13/244.0h:
120-04-07-L 02          Fabricate passerelle opening in transom step - Stbd412/13/2412/13/244.0h:
120-04-07-L 03          Install passerelle foundation plates412/13/2412/13/244.0h:
120-04-07-L 04          Install passerelle box412/13/2412/13/244.0h:
120-04-08      Overhead Crane1212/13/2412/13/245.0h:
120-04-08-L        Labor1212/13/2412/13/244.0h:
120-04-08-L 01          Fabricate overhead crane foundation plates412/13/2412/13/244.0h:
120-04-08-L 02          Install overhead crane foundation plates412/13/2412/13/244.0h:
120-04-08-L 03          Install overhead crane 412/13/2412/13/244.0h:
121  Rudder Room14012/10/2412/13/240.7w:
121-04    Metal fabrication14012/10/2412/13/2428.0h:
121-04-01      Foundations1612/13/2412/13/244.0h:
121-04-01-L        Labor1612/13/2412/13/244.0h:
121-04-01-L 01          Fabricate DC bilge pump foundations412/13/2412/13/244.0h:
121-04-01-L 02          Fabricate overhead light foundations412/13/2412/13/244.0h:
121-04-01-L 03          Install DC bilge pump foundations412/13/2412/13/244.0h:
121-04-01-L 04          Install overhead light foundations412/13/2412/13/244.0h:
121-04-02      Steering System2412/12/2412/13/2416.0h:
121-04-02-L        Labor2412/12/2412/13/240.4w:
121-04-02-L 01          Fabricate steering power pack foundations412/12/2412/12/244.0h:
121-04-02-L 02          Fabricate steering electrical panel foundations412/13/2412/13/244.0h:
121-04-02-L 03          Fabricate steering cylinder foundations412/12/2412/12/244.0h:
121-04-02-L 04          Install steering power pack foundations412/13/2412/13/244.0h:
121-04-02-L 05          Install steering electrical panel foundations412/13/2412/13/244.0h:
121-04-02-L 06          Install steering cylinder foundations412/13/2412/13/244.0h:
121-04-03      Compressed Air System5612/10/2412/13/2428.0h:
121-04-03-L        Labor5612/10/2412/13/240.7w:
121-04-03-L 01          Fabricate air compressor foundations1212/10/2412/11/2412.0h:
121-04-03-L 02          Fabricate air reciever foundations812/12/2412/12/248.0h:
121-04-03-L 03          Fabricate air filter foundations812/13/2412/13/248.0h:
121-04-03-L 04          Install air compressor foundations1212/10/2412/11/2412.0h:
121-04-03-L 05          Install air reciever foundations812/12/2412/12/248.0h:
121-04-03-L 06          Install air filter foundations812/13/2412/13/248.0h:
121-04-04      Shorepower System3212/11/2412/13/2420.0h:
121-04-04-L        Labor3212/13/2412/13/248.0h:
121-04-04-L 01          Fabricate shorepower cable container - Port412/13/2412/13/244.0h:
121-04-04-L 02          Fabricate shorepower cable container - STBD412/13/2412/13/244.0h:
121-04-04-L 03          Fabricate shorepower electical panel - Port412/13/2412/13/244.0h:
121-04-04-L 04          Fabricate shorepower electical panel - STBD412/13/2412/13/244.0h:
121-04-04-L 05          Install shorepower cable container - Port412/13/2412/13/244.0h:
121-04-04-L 06          Install shorepower cable container - STBD412/13/2412/13/244.0h:
121-04-04-L 07          Install shorepower electical panel - Port412/13/2412/13/244.0h:
121-04-04-L 08          Install shorepower electical panel - STBD412/13/2412/13/244.0h:
121-04-05      Floor Framing1212/13/2412/13/248.0h:
121-04-05-L        Labor1212/13/2412/13/240.2w:
121-04-05-L 01          Fabricate all floor frame panels412/13/2412/13/244.0h:
121-04-05-L 02          Fabricate floor mount clips412/13/2412/13/244.0h:
121-04-05-L 03          Install all floor frame panels412/13/2412/13/244.0h:
122  Transom16412/11/2412/13/240.5w:
122-04    Metal fabrication16412/11/2412/13/2420.0h:
122-04-01      Beach Club Door7212/11/2412/13/2420.0h:
122-04-01-L        Labor7212/13/2412/13/244.0h:
122-04-01-L 01          Fabricate door transverse frames412/13/2412/13/244.0h:
122-04-01-L 02          Fabricate door longtitudinal frames412/13/2412/13/244.0h:
122-04-01-L 03          Fabricate door plate stiffener frames412/13/2412/13/244.0h:
122-04-01-L 04          Fabricate door shell plating412/13/2412/13/244.0h:
122-04-01-L 05          Fabricate door hinge foundation box412/13/2412/13/244.0h:
122-04-01-L 06          Fabricate door accuator foundations412/13/2412/13/244.0h:
122-04-01-L 07          Fabricate sides to new door412/13/2412/13/244.0h:
122-04-01-L 08          Fabricate dog foundations to door structure412/13/2412/13/244.0h:
122-04-01-L 09          Fabricate inner plate for door412/13/2412/13/244.0h:
122-04-01-L 10          Install door transverse frames412/13/2412/13/244.0h:
122-04-01-L 11          Install door longtitudinal frames412/13/2412/13/244.0h:
122-04-01-L 12          Install door plate stiffener frames412/13/2412/13/244.0h:
122-04-01-L 13          Install door shell plating412/13/2412/13/244.0h:
122-04-01-L 14          Install door hinge foundation box412/13/2412/13/244.0h:
122-04-01-L 15          Install door accuator foundations412/13/2412/13/244.0h:
122-04-01-L 16          Install sides to new door412/13/2412/13/244.0h:
122-04-01-L 17          Install dog foundations to door structure412/13/2412/13/244.0h:
122-04-01-L 18          Install inner plate for door412/13/2412/13/244.0h:
122-04-02      Guardrail Foundations1612/13/2412/13/248.0h:
122-04-02-L        Labor1612/13/2412/13/240.2w:
122-04-02-L 01          Fabricate removable hoop rail foundations412/13/2412/13/244.0h:
122-04-02-L 02          Fabricate stairway handrail supports412/13/2412/13/244.0h:
122-04-02-L 03          Install removable guard rail foundations412/13/2412/13/244.0h:
122-04-02-L 04          Install stairway handrail supports412/13/2412/13/244.0h:
122-04-03      ShorePower reccesses1612/13/2412/13/248.0h:
122-04-03-L        Labor1612/13/2412/13/240.2w:
122-04-03-L 01          Fabricate shorepower reccess box - Port412/13/2412/13/244.0h:
122-04-03-L 02          Fabricate shorepower reccess box - STBD412/13/2412/13/244.0h:
122-04-03-L 03          Install shorepower reccess box - Port412/13/2412/13/244.0h:
122-04-03-L 04          Install shorepower reccess box - STBD412/13/2412/13/244.0h:
122-04-04      Beach Club Door Foundations2012/12/2412/13/2416.0h:
122-04-04-L        Labor2012/12/2412/13/240.4w:
122-04-04-L 01          Fabricate Beach Club door hinges412/12/2412/12/244.0h:
122-04-04-L 02          Fabricate Beach Club door hinge fouldations412/13/2412/13/244.0h:
122-04-04-L 03          Fabricate Beach Club door dog fouldations412/12/2412/12/244.0h:
122-04-04-L 04          Install Beach Club door hinges412/13/2412/13/244.0h:
122-04-04-L 05          Install Beach Club door hinge fouldations412/13/2412/13/244.0h:
122-04-05      Ceiling Framing812/13/2412/13/248.0h:
122-04-05-L        Labor812/13/2412/13/240.2w:
122-04-05-L 01          Fabricate ceiling framing412/13/2412/13/244.0h:
122-04-05-L 02          Install ceiling framing412/13/2412/13/244.0h:
122-04-06      Beach Club Walls/Floor3212/13/2412/13/248.0h:
122-04-06-L        Labor3212/13/2412/13/240.2w:
122-04-06-L 01          Fabricate beach club Fwd bulkhead framing412/13/2412/13/244.0h:
122-04-06-L 02          Fabricate beach club side wall framing - Port412/13/2412/13/244.0h:
122-04-06-L 03          Fabricate beach club side wall framing - Stbd412/13/2412/13/244.0h:
122-04-06-L 04          Fabricate beach club step to garage412/13/2412/13/244.0h:
122-04-06-L 05          Install beach club Fwd bulkhead framing412/13/2412/13/244.0h:
122-04-06-L 06          Install beach club side wall framing - Port412/13/2412/13/244.0h:
122-04-06-L 07          Install beach club side wall framing - Stbd412/13/2412/13/244.0h:
122-04-06-L 08          Install beach club step to garage412/13/2412/13/244.0h:
124  Driveline5212/12/2412/13/240.4w:
124-04    Metal fabrication3612/12/2412/13/240.4w:
124-04-01      Main Engine Driveline3612/12/2412/13/240.4w:
124-04-01-L        Labor3612/12/2412/13/240.4w:
124-04-01-L 01          Fabricate top outer driveline tube - Port412/12/2412/12/244.0h:
124-04-01-L 02          Fabricate top outer driveline tube - STBD412/12/2412/12/244.0h:
124-04-01-L 03          Fabricate lower outer driveline tube - Port412/13/2412/13/244.0h:
124-04-01-L 04          Fabricate lower outer driveline tube - STBD412/13/2412/13/244.0h:
124-04-01-L 05          Install top outer driveline tube - Port412/12/2412/12/244.0h:
124-04-01-L 06          Install top outer driveline tube - STBD412/12/2412/12/244.0h:
124-04-01-L 07          Install lower outer driveline tube - Port412/13/2412/13/244.0h:
124-04-01-L 08          Install lower outer driveline tube - STBD412/13/2412/13/244.0h:
124-04-01-L 09          Lloyds inspection412/13/2412/13/244.0h:
124-05    Metal Welding1612/12/2412/13/241.5d:
124-05-01      Main Engine Driveline1612/12/2412/13/2412.0h:
124-05-01-L        Labor1612/12/2412/13/240.3w:
124-05-01-L 01          Weld top outer driveline tube - Port412/12/2412/12/244.0h:
124-05-01-L 02          Weld top outer driveline tube - STBD412/13/2412/13/244.0h:
124-05-01-L 03          Weld lower outer driveline tube - Port412/13/2412/13/244.0h:
124-05-01-L 04          Weld lower outer driveline tube - STBD412/13/2412/13/244.0h:
125  Hull Appendages4812/12/2412/13/240.3w:
125-04    Metal fabrication4812/12/2412/13/2410.0h:
125-04-01      Bowthruster Tunnel3212/12/2412/13/2410.0h:
125-04-01-L        Labor3212/13/2412/13/244.0h:
125-04-01-L 01          Prepare tunnel for installation412/13/2412/13/244.0h:
125-04-01-L 02          Drill motor holes as needed412/13/2412/13/244.0h:
125-04-01-L 03          Install tunnel to hull412/13/2412/13/244.0h:
125-04-01-L 04          Install doubler plates as needed412/13/2412/13/244.0h:
125-04-01-L 05          Fabricate port & Stbd tunnel grill foundations412/13/2412/13/244.0h:
125-04-01-L 06          Fabricate port & Stbd removable tunnel grills412/13/2412/13/244.0h:
125-04-01-L 07          Lloyds structure inspection412/13/2412/13/244.0h:
125-04-01-L 08          Install port & Stbd tunnel grills412/13/2412/13/244.0h:
125-04-02      Transducter Penetrations1612/13/2412/13/244.0h:
125-04-02-L        Labor1612/13/2412/13/244.0h:
125-04-02-L 01          Fabricate speed log penetration412/13/2412/13/244.0h:
125-04-02-L 02          Fabricate sonar penetration412/13/2412/13/244.0h:
125-04-02-L 03          Install speed log penetration412/13/2412/13/244.0h:
125-04-02-L 04          Install sonar penetration412/13/2412/13/244.0h:
130  Main Decking Construction14012/13/2412/13/240.3w:
130-04    Metal Fabrication12412/13/2412/13/240.2w:
130-04-01      Caprail812/13/2412/13/244.0h:
130-04-01-L        Labor812/13/2412/13/244.0h:
130-04-01-L 01          Install bow section caprail412/13/2412/13/244.0h:
130-04-01-L 02          Install bow section handrail sockets412/13/2412/13/244.0h:
130-04-02      Bulkwark Patio Door - Port10012/13/2412/13/244.0h:
130-04-02-L        Labor10012/13/2412/13/244.0h:
130-04-02-L 01          Cut hull sheel, caprail and structure at patio door for reuse412/13/2412/13/244.0h:
130-04-02-L 02          Cut deck plate in way of the hinge foundation box412/13/2412/13/244.0h:
130-04-02-L 03          Cut transverse frames in way of the hinge box412/13/2412/13/244.0h:
130-04-02-L 04          Fabricate new transverse frames412/13/2412/13/244.0h:
130-04-02-L 05          Fabricate new longtitudinal deck girder412/13/2412/13/244.0h:
130-04-02-L 06          Fabricate door hinge foundation box412/13/2412/13/244.0h:
130-04-02-L 07          Fabricate door accuator foundations412/13/2412/13/244.0h:
130-04-02-L 08          Fabricate bulkwark frame w/ recess box for door dogs - FWD412/13/2412/13/244.0h:
130-04-02-L 09          Modify structure in part removed from hull to create patio door412/13/2412/13/244.0h:
130-04-02-L 10          Fabricate bulkwark frame w/ recess box for door dogs - AFT412/13/2412/13/244.0h:
130-04-02-L 11          Fabricate sides to new door412/13/2412/13/244.0h:
130-04-02-L 12          Fabricate dog foundations to new door 412/13/2412/13/244.0h:
130-04-02-L 13          Fabricate inner plate for new door412/13/2412/13/244.0h:
130-04-02-L 14          Fabricate deck sewer drains412/13/2412/13/244.0h:
130-04-02-L 15          Install new transverse frames412/13/2412/13/244.0h:
130-04-02-L 16          Install new longtitudinal deck girder412/13/2412/13/244.0h:
130-04-02-L 17          Install door hinge foundation box412/13/2412/13/244.0h:
130-04-02-L 18          Install door accuator foundations412/13/2412/13/244.0h:
130-04-02-L 19          Install bulkwark frame w/ recess box for door dogs - FWD412/13/2412/13/244.0h:
130-04-02-L 20          Install bulkwark frame w/ recess box for door dogs - AFT412/13/2412/13/244.0h:
130-04-02-L 21          Install bulkwark frame w/ recess box for door dogs - AFT412/13/2412/13/244.0h:
130-04-02-L 22          Install sides to new door412/13/2412/13/244.0h:
130-04-02-L 23          Install dog foundations to new door 412/13/2412/13/244.0h:
130-04-02-L 24          Install inner plate for new door412/13/2412/13/244.0h:
130-04-02-L 25          Install deck sewer drains412/13/2412/13/244.0h:
130-04-03      Foundations812/13/2412/13/244.0h:
130-04-03-L        Labor812/13/2412/13/244.0h:
130-04-03-L 01          Fabricate Niclad Bi-metal strip for house connection412/13/2412/13/244.0h:
130-04-03-L 02          Install Niclad Bi-metal strip for house connection412/13/2412/13/244.0h:
130-04-04      Main decking Penetrations812/13/2412/13/248.0h:
130-04-04-L        Labor812/13/2412/13/244.0h:
130-04-04-L 01          Install engine room fan plate - Port412/13/2412/13/244.0h:
130-04-04-L 02          Install engine room fan plate - STBD412/13/2412/13/244.0h:
130-05    Metal Welding1612/13/2412/13/241.3d:
130-05-02      Bulkwark Patio Door - Port1612/13/2412/13/244.0h:
130-05-02-L        Labor1612/13/2412/13/244.0h:
130-05-02-L 07          Weld structure in part removed from hull to create patio door412/13/2412/13/244.0h:
130-05-02-L 08          Weld sides to new door412/13/2412/13/244.0h:
130-05-02-L 09          Weld dog foundations to new door 412/13/2412/13/244.0h:
130-05-02-L 10          Weld inner plate for new door412/13/2412/13/244.0h:
131  Main Cabin Module - Block 12,68012/09/2412/13/241.0w:
131-04    Metal Fabrication2,68012/09/2412/13/241.0w:
131-04-01      Parts Preparation48012/09/2412/13/2440.0h:
131-04-01-L        Labor48012/09/2412/13/2440.0h:
131-04-01-L 01          Prepare Jig to receive frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-01-L 02          Clean and prepare frame parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-01-L 03          Clean and prepare shell plate parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-02      Parts Assemble64012/09/2412/13/2440.0h:
131-04-02-L        Labor64012/09/2412/13/2440.0h:
131-04-02-L 01          Assemble prepared transverse frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-02-L 02          Assemble prepared longitudinal frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-02-L 03          Assemble prepared parts as required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-02-L 04          Assemble prepared integral piping parts as required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-03      Frame installation 80012/09/2412/13/2440.0h:
131-04-03-L        Labor80012/09/2412/13/2440.0h:
131-04-03-L 01          Install prepared transverse frames to jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-03-L 02          Install prepared longitudinal frames onto module16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-03-L 03          Install prepared plate stinnener frames onto module16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-03-L 04          Install remaining prepared parts onto jig as required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-03-L 05          Install integral piping if required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-04      Shell plate installation 64012/09/2412/13/2440.0h:
131-04-04-L        Labor64012/09/2412/13/2440.0h:
131-04-04-L 01          Install all shell plate to module framing16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-04-L 03          Install all topside shell plates16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
131-04-05      Prepartions for connection12012/09/2412/13/2440.0h:
131-04-05-L        Labor12012/09/2412/13/2440.0h:
131-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132  Main Cabin Module - Block 22,68012/09/2412/13/241.0w:
132-04    Metal Fabrication2,68012/09/2412/13/241.0w:
132-04-01      Parts Preparation48012/09/2412/13/2440.0h:
132-04-01-L        Labor48012/09/2412/13/2440.0h:
132-04-01-L 01          Prepare Jig to receive frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-01-L 02          Clean and prepare frame parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-01-L 03          Clean and prepare shell plate parts from CNC16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-02      Parts Assemble64012/09/2412/13/2440.0h:
132-04-02-L        Labor64012/09/2412/13/2440.0h:
132-04-02-L 01          Assemble prepared transverse frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-02-L 02          Assemble prepared longitudinal frames16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-02-L 03          Assemble prepared parts as required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-02-L 04          Assemble prepared integral piping parts as required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-03      Frame installation 80012/09/2412/13/2440.0h:
132-04-03-L        Labor80012/09/2412/13/2440.0h:
132-04-03-L 01          Install prepared transverse frames to jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-03-L 02          Install prepared longitudinal frames onto module16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-03-L 03          Install prepared plate stinnener frames onto module16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-03-L 04          Install remaining prepared parts onto jig as required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-03-L 05          Install integral piping if required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-04      Shell plate installation 64012/09/2412/13/2440.0h:
132-04-04-L        Labor64012/09/2412/13/2440.0h:
132-04-04-L 01          Install all shell plate to module framing16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-04-L 03          Install all topside shell plates16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
132-04-05      Prepartions for connection12012/09/2412/13/2440.0h:
132-04-05-L        Labor12012/09/2412/13/2440.0h:
132-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
137  Module Connection1612/13/2412/13/240.6w:
137-04    Metal Fabrication1612/13/2412/13/240.2w:
137-04-01      Block 201812/13/2412/13/248.0h:
137-04-01-L        Labor812/13/2412/13/240.2w:
137-04-01-L 01          Trim and level block 201 to main deck 412/13/2412/13/244.0h:
137-04-01-L 02          Final install block 201 to main deck412/13/2412/13/244.0h:
137-04-02      Block 202812/13/2412/13/248.0h:
137-04-02-L        Labor812/13/2412/13/240.2w:
137-04-02-L 01          Trim and level block 202 to main deck 412/13/2412/13/244.0h:
137-04-02-L 02          Final install block 202 to main deck412/13/2412/13/244.0h:
139  Main deck - Fwd 6812/12/2412/13/2416.0h:
139-04    Metal Fabrication6812/12/2412/13/240.4w:
139-04-01      Foundations3212/13/2412/13/248.0h:
139-04-01-L        Labor3212/13/2412/13/240.2w:
139-04-01-L 01          Fabricate deck doubler plates for ladder attachment - Port412/13/2412/13/244.0h:
139-04-01-L 02          Fabricate cabin doubler plates for ladder attachment - Port412/13/2412/13/244.0h:
139-04-01-L 03          Fabricate deck doubler plates for ladder attachment - STBD412/13/2412/13/244.0h:
139-04-01-L 04          Fabricate cabin doubler plates for ladder attachment - STBD412/13/2412/13/244.0h:
139-04-01-L 05          Install deck doubler plates for ladder attachment - Port412/13/2412/13/244.0h:
139-04-01-L 06          Install cabin doubler plates for ladder attachment - Port412/13/2412/13/244.0h:
139-04-01-L 07          Install deck doubler plates for ladder attachment - STBD412/13/2412/13/244.0h:
139-04-01-L 08          Install cabin doubler plates for ladder attachment - STBD412/13/2412/13/244.0h:
139-04-02      Bench seat3612/12/2412/13/2416.0h:
139-04-02-L        Labor3612/12/2412/13/240.4w:
139-04-02-L 01          Fabricate bench seat framing412/12/2412/12/244.0h:
139-04-02-L 02          Fabricate bench seat plating412/13/2412/13/244.0h:
139-04-02-L 03          Fabricate bench seat storage hatches412/13/2412/13/244.0h:
139-04-02-L 04          Fabricate bench seat crew escape hatch412/13/2412/13/244.0h:
139-04-02-L 05          Assemble bench seat412/13/2412/13/244.0h:
139-04-02-L 06          Install bench seat hatch drains412/13/2412/13/244.0h:
139-04-02-L 07          Install bench seat storage hatches412/12/2412/12/244.0h:
139-04-02-L 08          Install bench seat crew escape hatch412/13/2412/13/244.0h:
139-04-02-L 09          Install bench seat412/13/2412/13/244.0h:
142  Main deck - Aft812/13/2412/13/241.0w:
142-04    Metal fabrication812/13/2412/13/240.1w:
142-04-01      Decking812/13/2412/13/245.0h:
142-04-01-L        Labor812/13/2412/13/244.0h:
142-04-01-L 01          Fabricate deck doubler plates for table412/13/2412/13/244.0h:
142-04-01-L 02          Install deck doubler plates for table412/13/2412/13/244.0h:
160  Flybridge Module - Block 13,84012/02/2412/13/242.0w:
160-04    Metal Fabrication3,84012/02/2412/13/242.0w:
160-04-01      Parts Preparation36012/09/2412/13/2440.0h:
160-04-01-L        Labor36012/09/2412/13/2440.0h:
160-04-01-L 01          Prepare Jig to receive frames12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
160-04-01-L 02          Clean and prepare frame parts from CNC12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
160-04-01-L 03          Clean and prepare shell plate parts from CNC12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
160-04-02      Parts Assemble96012/02/2412/13/2480.0h:
160-04-02-L        Labor96012/02/2412/13/2480.0h:
160-04-02-L 01          Assemble prepared transverse frames24012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-02-L 02          Assemble prepared longitudinal frames24012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-02-L 03          Assemble prepared parts as required24012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-02-L 04          Assemble prepared integral piping parts as required24012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-03      Frame installation 1,44012/02/2412/13/2480.0h:
160-04-03-L        Labor1,44012/02/2412/13/2480.0h:
160-04-03-L 01          Install prepared transverse frames to jig32012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-03-L 02          Install prepared longitudinal frames onto module32012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-03-L 03          Install prepared plate stinnener frames onto module32012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-03-L 04          Install remaining prepared parts onto jig as required32012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-03-L 05          Install integral piping if required16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
160-04-04      Shell plate installation 96012/02/2412/13/2480.0h:
160-04-04-L        Labor96012/02/2412/13/2480.0h:
160-04-04-L 01          Install all shell plate to module framing32012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-04-L 02          Remove from jig16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
160-04-04-L 03          Install all topside shell plates32012/02/2412/13/2480.0h:Require crew interior boxes loaded before task complete
160-04-04-L 04          Install topside plate openings16012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
160-04-05      Prepartions for connection12012/09/2412/13/2440.0h:
160-04-05-L        Labor12012/09/2412/13/2440.0h:
160-04-05-L 01          Prepare module for sandblasting12012/09/2412/13/2440.0h:Require crew interior boxes loaded before task complete
163  Hardtop 14412/12/2412/13/240.4w:
163-04    Metal Fabrication14412/12/2412/13/240.3w:
163-04-01      Hardtop enclosure4412/12/2412/13/2412.0h:
163-04-01-L        Labor4412/12/2412/13/2412.0h:
163-04-01-L 01          Fabricate transverse frames412/12/2412/12/244.0h:
163-04-01-L 02          Fabricate longitudinal girders412/13/2412/13/244.0h:
163-04-01-L 03          Fabricate longitidinal plate stiffeners412/13/2412/13/244.0h:
163-04-01-L 04          Fabriace coaming plates412/12/2412/12/244.0h:
163-04-01-L 05          Fabricate shell plating412/13/2412/13/244.0h:
163-04-01-L 06          Prepare jig412/13/2412/13/244.0h:
163-04-01-L 07          Install shell plating412/13/2412/13/244.0h:
163-04-01-L 08          Install transverse frames412/13/2412/13/244.0h:
163-04-01-L 09          Install longitudinal girders412/13/2412/13/244.0h:
163-04-01-L 10          Install longitidinal plate stiffeners412/13/2412/13/244.0h:
163-04-01-L 11          Install coaming plates412/13/2412/13/244.0h:
163-04-02      Foundations5612/12/2412/13/2412.0h:
163-04-02-L        Labor5612/12/2412/13/2412.0h:
163-04-02-L 01          Fabricate hardtop stanchion AFT foundation - Port412/12/2412/12/244.0h:
163-04-02-L 02          Fabricate hardtop stanchion AFT foundation - STBD412/13/2412/13/244.0h:
163-04-02-L 03          Fabricate hardtop stanchion FWD foundation - Port412/13/2412/13/244.0h:
163-04-02-L 04          Fabricate hardtop stanchion FWD foundation - STBD412/12/2412/12/244.0h:
163-04-02-L 05          Fabricate radar arch foundation - Port412/13/2412/13/244.0h:
163-04-02-L 06          Fabricate radar arch foundation - STBD412/13/2412/13/244.0h:
163-04-02-L 07          Fabricate solar panel foundations412/13/2412/13/244.0h:
163-04-02-L 08          Install hardtop stanchion AFT foundation - Port412/12/2412/12/244.0h:
163-04-02-L 09          Install hardtop stanchion AFT foundation - STBD412/13/2412/13/244.0h:
163-04-02-L 10          Install hardtop stanchion FWD foundation - Port412/13/2412/13/244.0h:
163-04-02-L 11          Install hardtop stanchion FWD foundation - STBD412/12/2412/12/244.0h:
163-04-02-L 12          Install radar arch foundation - Port412/13/2412/13/244.0h:
163-04-02-L 13          Install radar arch foundation - STBD412/13/2412/13/244.0h:
163-04-02-L 14          Install solar panel foundations412/13/2412/13/244.0h:
163-04-03      Wire Trays1212/13/2412/13/240.1w:
163-04-03-L        Labor1212/13/2412/13/240.1w:
163-04-03-L 01          Fabricate access panels to cable tray412/13/2412/13/244.0h:
163-04-03-L 02          Install access panels to cable tray412/13/2412/13/244.0h:
163-04-03-L 03          Install cable trays412/13/2412/13/244.0h:
163-04-04      Mast Piping3212/13/2412/13/248.0h:
163-04-04-L        Labor3212/13/2412/13/244.0h:
163-04-04-L 01          Fabricate fuel tank vent piping - Port412/13/2412/13/244.0h:
163-04-04-L 02          Fabricate fuel tank vent piping - STBD412/13/2412/13/244.0h:
163-04-04-L 03          Fabricate black/Grey tank vent piping - Port412/13/2412/13/244.0h:
163-04-04-L 04          Fabricate black/Grey tank vent piping - STBD412/13/2412/13/244.0h:
163-04-04-L 05          Install fuel tank vent piping - Port412/13/2412/13/244.0h:
163-04-04-L 06          Install fuel tank vent piping - STBD412/13/2412/13/244.0h:
163-04-04-L 07          Install black/Grey tank vent piping - Port412/13/2412/13/244.0h:
163-04-04-L 08          Install black/Grey tank vent piping - STBD412/13/2412/13/244.0h:
164  Mast Arch 20812/11/2412/13/240.6w:
164-04    Metal Fabrication20812/11/2412/13/240.6w:
164-04-01      Mast Arch Framing10412/11/2412/13/2424.0h:
164-04-01-L        Labor10412/11/2412/13/2424.0h:
164-04-01-L 01          Fabricate transverse frames812/11/2412/11/248.0h:
164-04-01-L 02          Fabricate longitudinal girders812/12/2412/12/248.0h:
164-04-01-L 03          Fabricate longitidinal plate stiffeners812/13/2412/13/248.0h:
164-04-01-L 04          Fabricate shell plating812/12/2412/12/248.0h:
164-04-01-L 05          Prepare jig812/13/2412/13/248.0h:
164-04-01-L 06          Install transverse frames1612/12/2412/13/2416.0h:
164-04-01-L 07          Install longitudinal girders1612/12/2412/13/2416.0h:
164-04-01-L 08          Install longitidinal plate stiffeners1612/12/2412/13/2416.0h:
164-04-01-L 09          Install shell plating1612/12/2412/13/2416.0h:
164-04-02      Foundations4812/11/2412/13/2424.0h:
164-04-02-L        Labor4812/11/2412/13/2424.0h:
164-04-02-L 01          Fabricate lower foundation to hardtop - Port812/12/2412/12/248.0h:
164-04-02-L 02          Fabricate lower foundation to hardtop - STBD812/13/2412/13/248.0h:
164-04-02-L 03          Fabricate mast foundation812/13/2412/13/248.0h:
164-04-02-L 04          Install lower foundation to hardtop - Port812/11/2412/11/248.0h:
164-04-02-L 05          Install lower foundation to hardtop - STBD812/12/2412/12/248.0h:
164-04-02-L 06          Install mast foundation812/13/2412/13/248.0h:
164-04-03      Internal Wire Trays2412/13/2412/13/240.2w:
164-04-03-L        Labor2412/13/2412/13/240.2w:
164-04-03-L 01          Fabricate access panels to cable tray812/13/2412/13/248.0h:
164-04-03-L 02          Install access panels to cable tray812/13/2412/13/248.0h:
164-04-03-L 03          Install cable trays812/13/2412/13/248.0h:
164-04-04      Mast Arch Pipe Terminations3212/13/2412/13/248.0h:
164-04-04-L        Labor3212/13/2412/13/248.0h:
164-04-04-L 01          Install fuel tank vent piping - Port812/13/2412/13/248.0h:
164-04-04-L 02          Install fuel tank vent piping - STBD812/13/2412/13/248.0h:
164-04-04-L 03          Install black/Grey tank vent piping - Port812/13/2412/13/248.0h:
164-04-04-L 04          Install black/Grey tank vent piping - STBD812/13/2412/13/248.0h:
165  Electronic Mast29612/03/2412/13/241.8w:
165-04    Metal Fabrication29612/03/2412/13/241.8w:
165-04-01      Mast Arch Framing21612/03/2412/13/2472.0h:
165-04-01-L        Labor21612/03/2412/13/2472.0h:
165-04-01-L 01          Fabricate transverse frames2412/03/2412/05/2424.0h:
165-04-01-L 02          Fabricate longitudinal girders2412/06/2412/10/2424.0h:
165-04-01-L 03          Fabricate longitidinal plate stiffeners2412/11/2412/13/2424.0h:
165-04-01-L 04          Fabricate shell plating2412/06/2412/10/2424.0h:
165-04-01-L 05          Prepare jig2412/11/2412/13/2424.0h:
165-04-01-L 06          Install shell plating2412/11/2412/13/2424.0h:
165-04-01-L 07          Install transverse frames2412/11/2412/13/2424.0h:
165-04-01-L 08          Install longitudinal girders2412/11/2412/13/2424.0h:
165-04-01-L 09          Install longitidinal plate stiffeners2412/11/2412/13/2424.0h:
165-04-02      Foundations3212/12/2412/13/2416.0h:
165-04-02-L        Labor3212/12/2412/13/2416.0h:
165-04-02-L 01          Fabricate foundation to radar arch1612/12/2412/13/2416.0h:
165-04-02-L 02          Install foundation to radar arch1612/12/2412/13/2416.0h:
165-04-03      Internal Wire Trays4812/12/2412/13/240.4w:
165-04-03-J        Labor4812/12/2412/13/240.4w:
165-04-03-J 01          Fabricate access panels to cable tray1612/12/2412/13/2416.0h:
165-04-03-J 02          Install access panels to cable tray1612/12/2412/13/2416.0h:
165-04-03-J 03          Install cable trays1612/12/2412/13/2416.0h:
166  Module Connection1612/13/2412/13/240.6w:
166-04    Metal Fabrication1612/13/2412/13/240.2w:
166-04-01      Block 201812/13/2412/13/248.0h:
166-04-01-L        Labor812/13/2412/13/240.2w:
166-04-01-L 01          Trim and level block 201 to main deck 412/13/2412/13/244.0h:
166-04-01-L 02          Final install block 201 to main deck412/13/2412/13/244.0h:
166-04-02      Block 202812/13/2412/13/248.0h:
166-04-02-L        Labor812/13/2412/13/240.2w:
166-04-02-L 01          Trim and level block 202 to main deck 412/13/2412/13/244.0h:
166-04-02-L 02          Final install block 202 to main deck412/13/2412/13/244.0h:
168  Flybridge - Furniture30812/13/2412/13/240.2w:
168-04    Metal Fabrication30812/13/2412/13/240.2w:
168-04-01      Control Console1612/13/2412/13/248.0h:
168-04-01-L        Labor1612/13/2412/13/244.0h:
168-04-01-L 01          Fabricate control console framing412/13/2412/13/244.0h:
168-04-01-L 02          Fabricate control console plating412/13/2412/13/244.0h:
168-04-01-L 03          Assemble control console 412/13/2412/13/244.0h:
168-04-01-L 04          Install control console to bulkhead412/13/2412/13/244.0h:
168-04-02      Wing Station Reccess - STBD812/13/2412/13/248.0h:
168-04-02-L        Labor812/13/2412/13/244.0h:
168-04-02-L 01          Fabricate wing station reccess box412/13/2412/13/244.0h:
168-04-02-L 02          Install wing station box into bulwark412/13/2412/13/244.0h:
168-04-03      Console Bench Seat - Port2812/13/2412/13/248.0h:
168-04-03-L        Labor2812/13/2412/13/248.0h:
168-04-03-L 01          Fabricate console bench seat framing - Port412/13/2412/13/244.0h:
168-04-03-L 02          Fabricate console bench seat plating - Port412/13/2412/13/244.0h:
168-04-03-L 03          Fabricate console bench seat storage hatches - Port412/13/2412/13/244.0h:
168-04-03-L 04          Assemble console bench seat - Port412/13/2412/13/244.0h:
168-04-03-L 05          Install console bench seat hatch drains - Port412/13/2412/13/244.0h:
168-04-03-L 06          Install console bench seat storage hatches - Port412/13/2412/13/244.0h:
168-04-03-L 07          Install console bench seat to deck - Port412/13/2412/13/244.0h:
168-04-04      Console Bench Seat - STBD2812/13/2412/13/248.0h:
168-04-04-L        Labor2812/13/2412/13/248.0h:
168-04-04-L 01          Fabricate console bench seat framing - STBD412/13/2412/13/244.0h:
168-04-04-L 02          Fabricate console bench seat plating - STBD412/13/2412/13/244.0h:
168-04-04-L 03          Fabricate console bench seat storage hatches - STBD412/13/2412/13/244.0h:
168-04-04-L 04          Assemble console bench seat - STBD412/13/2412/13/244.0h:
168-04-04-L 05          Install console bench seat hatch drains - STBD412/13/2412/13/244.0h:
168-04-04-L 06          Install console bench seat storage hatches - STBD412/13/2412/13/244.0h:
168-04-04-L 07          Install console bench seat to deck - STBD412/13/2412/13/244.0h:
168-04-05      Dining Table Bench Seat - Port2812/13/2412/13/248.0h:
168-04-05-L        Labor2812/13/2412/13/248.0h:
168-04-05-L 01          Fabricate dining table bench seat framing412/13/2412/13/244.0h:
168-04-05-L 02          Fabricate dining table bench seat plating412/13/2412/13/244.0h:
168-04-05-L 03          Fabricate dining table bench seat storage hatches412/13/2412/13/244.0h:
168-04-05-L 04          Assemble dining table bench seat412/13/2412/13/244.0h:
168-04-05-L 05          Install dining table bench seat hatch drains412/13/2412/13/244.0h:
168-04-05-L 06          Install dining table bench seat storage hatches412/13/2412/13/244.0h:
168-04-05-L 07          Install dining table bench seat to deck412/13/2412/13/244.0h:
168-04-06      AFT Settee - Port2812/13/2412/13/248.0h:
168-04-06-L        Labor2812/13/2412/13/248.0h:
168-04-06-L 01          Fabricate AFT settee framing - Port412/13/2412/13/244.0h:
168-04-06-L 02          Fabricate AFT settee plating - Port412/13/2412/13/244.0h:
168-04-06-L 03          Fabricate AFT settee storage hatches - Port412/13/2412/13/244.0h:
168-04-06-L 04          Assemble AFT settee - Port412/13/2412/13/244.0h:
168-04-06-L 05          Install AFT settee hatch drains - Port412/13/2412/13/244.0h:
168-04-06-L 06          Install AFT settee storage hatches - Port412/13/2412/13/244.0h:
168-04-06-L 07          Install AFT settee deck - Port412/13/2412/13/244.0h:
168-04-07      AFT Settee - STBD2812/13/2412/13/248.0h:
168-04-07-L        Labor2812/13/2412/13/248.0h:
168-04-07-L 01          Fabricate AFT settee framing - STBD412/13/2412/13/244.0h:
168-04-07-L 02          Fabricate AFT settee plating - STBD412/13/2412/13/244.0h:
168-04-07-L 03          Fabricate AFT settee storage hatches - STBD412/13/2412/13/244.0h:
168-04-07-L 04          Assemble AFT settee - STBD412/13/2412/13/244.0h:
168-04-07-L 05          Install AFT settee hatch drains - STBD412/13/2412/13/244.0h:
168-04-07-L 06          Install AFT settee storage hatches - STBD412/13/2412/13/244.0h:
168-04-07-L 07          Install AFT settee to deck - STBD412/13/2412/13/244.0h:
168-04-08      Wet Bar3212/13/2412/13/248.0h:
168-04-08-L        Labor3212/13/2412/13/244.0h:
168-04-08-L 01          Fabricate wet bar framing412/13/2412/13/244.0h:
168-04-08-L 02          Fabricate wet bar plating412/13/2412/13/244.0h:
168-04-08-L 03          Fabricate wet bar upper platform412/13/2412/13/244.0h:
168-04-08-L 04          Fabricate wet bar door framing412/13/2412/13/244.0h:
168-04-08-L 05          Assemble wet bar 412/13/2412/13/244.0h:
168-04-08-L 06          Install wet bar upper platform412/13/2412/13/244.0h:
168-04-08-L 07          Install wet bar door framing412/13/2412/13/244.0h:
168-04-08-L 08          Install wet bar to deck412/13/2412/13/244.0h:
168-04-09      Jacuzzi Enclosure4812/13/2412/13/248.0h:
168-04-09-L        Labor4812/13/2412/13/244.0h:
168-04-09-L 01          Fabricate jacuzzi enclosure framing412/13/2412/13/244.0h:
168-04-09-L 02          Fabricate jacuzzi enclosure plating412/13/2412/13/244.0h:
168-04-09-L 03          Fabricate jacuzzi drain channels412/13/2412/13/244.0h:
168-04-09-L 04          Fabricate jacuzzi steps412/13/2412/13/244.0h:
168-04-09-L 05          Fabricate jacuzzi door framing412/13/2412/13/244.0h:
168-04-09-L 06          Fabricate jacuzzi equipment foundations412/13/2412/13/244.0h:
168-04-09-L 07          Assemble jacuzzi412/13/2412/13/244.0h:
168-04-09-L 08          Install jacuzzi drain channels412/13/2412/13/244.0h:
168-04-09-L 09          Install jacuzzi steps412/13/2412/13/244.0h:
168-04-09-L 10          Install jacuzzi door framing412/13/2412/13/244.0h:
168-04-09-L 11          Install jacuzzi equipment foundations412/13/2412/13/244.0h:
168-04-09-L 12          Install jacuzzi to deck412/13/2412/13/244.0h:
168-04-10      BBQ Cabinet3212/13/2412/13/248.0h:
168-04-10-L        Labor3212/13/2412/13/244.0h:
168-04-10-L 01          Fabricate BBQ cabinet framing412/13/2412/13/244.0h:
168-04-10-L 02          Fabricate BBQ cabinet plating412/13/2412/13/244.0h:
168-04-10-L 03          Fabricate BBQ cabinet door framing412/13/2412/13/244.0h:
168-04-10-L 04          Fabricate BBQ cabinet equipment foundations412/13/2412/13/244.0h:
168-04-10-L 05          Assemble BBQ cabinet412/13/2412/13/244.0h:
168-04-10-L 06          Install BBQ cabinet door framing412/13/2412/13/244.0h:
168-04-10-L 07          Install BBQ cabinet equipment foundations412/13/2412/13/244.0h:
168-04-10-L 08          Install BBQ cabinet to deck412/13/2412/13/244.0h:
168-04-11      Stairway Cabinet3212/13/2412/13/248.0h:
168-04-11-L        Labor3212/13/2412/13/244.0h:
168-04-11-L 01          Fabricate stairway cabinet framing412/13/2412/13/244.0h:
168-04-11-L 02          Fabricate stairway cabinet plating412/13/2412/13/244.0h:
168-04-11-L 03          Fabricate stairway cabinet door framing412/13/2412/13/244.0h:
168-04-11-L 04          Fabricate stairway cabinet equipment foundations412/13/2412/13/244.0h:
168-04-11-L 05          Assemble stairway cabinet412/13/2412/13/244.0h:
168-04-11-L 06          Install stairway cabinet door framing412/13/2412/13/244.0h:
168-04-11-L 07          Install stairway cabinet equipment foundations412/13/2412/13/244.0h:
168-04-11-L 08          Install stairway cabinet to deck412/13/2412/13/244.0h:
******** *********************************************************************************