| WBS | Project Categories | Labor Hrs. | Start Date | Finish Dates | Duration | : | Comments |
| | DEPARTMENT TOTAL | 10,109 | 11/15/24 | 12/13/24 | . | : | . |
| 6 | INTERIOR | 9,497 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 8 | EXTERIOR | 612 | 12/02/24 | 12/13/24 | 33.2w | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |
|
|
| WBS | Job Description | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 6 | INTERIOR | 9,497 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 601 | LOWER GUEST FRAMING | 680 | 11/18/24 | 12/13/24 | 4.2w | : | |
| 601-09 | Carpentry | 680 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 601-09-01 | Joiner Floor | 400 | 11/18/24 | 12/13/24 | 160.0h | : | |
| 601-09-01-L | Labor | 400 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 601-09-01-L 01 | Cut floor panels | 40 | 11/25/24 | 11/29/24 | 40.0h | : | |
| 601-09-01-L 02 | Fabricate sound damping foundation strips | 120 | 11/18/24 | 11/22/24 | 40.0h | : | |
| 601-09-01-L 03 | Install floor panels foundation strips | 120 | 12/02/24 | 12/06/24 | 40.0h | : | |
| 601-09-01-L 04 | Install sub-floor panels | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 601-09-02 | Bulkheads/Cabins | 280 | 11/26/24 | 12/13/24 | 108.0h | : | |
| 601-09-02-L | Labor | 280 | 11/26/24 | 12/13/24 | 2.7w | : | |
| 601-09-02-L 01 | Cut all shipside and inner wall panels | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 601-09-02-L 02 | Cut all AC and window boxes | 40 | 11/26/24 | 12/03/24 | 40.0h | : | |
| 601-09-02-L 03 | Assemble all shipside and inner wall panels | 48 | 12/03/24 | 12/06/24 | 24.0h | : | |
| 601-09-02-L 04 | Assemble all AC and window boxes | 24 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 601-09-02-L 05 | Dry-fit all shipside and inner wall panels onboard | 32 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 601-09-02-L 06 | Dry-fit all AC and window boxes onboard | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 601-09-02-L 07 | Install all shipside and inner wall panels onboard | 32 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 601-09-02-L 08 | Install all AC and window boxes onboard | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 602 | Guest Stateroom 1 | 323 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 602-09 | Carpentry | 323 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 602-09-01 | Room Framing | 48 | 12/04/24 | 12/13/24 | 58.0h | : | |
| 602-09-01-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 602-09-01-L 01 | Install shipside framing | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 602-09-01-L 02 | Install portlight framing | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 602-09-01-L 03 | Frame closet sides | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 602-09-01-L 04 | Install overhead framing | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 602-09-01-L 05 | Rough in window box | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 602-09-01-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 602-09-02 | AC Plenum | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 602-09-02-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 602-09-02-L 01 | Fabricate AC plenum | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 602-09-02-L 02 | Install AC plenum | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 602-09-02-L 03 | Rough in AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-02-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-03 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 602-09-03-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 602-09-03-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 602-09-03-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 602-09-03-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-03-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-04 | Nightstand | 13 | 12/12/24 | 12/13/24 | 13.0h | : | |
| 602-09-04-L | Labor | 13 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 602-09-04-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 602-09-04-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 602-09-04-L 03 | Fabricate upper rail/Countertop | 2 | 12/12/24 | 12/13/24 | 2.0h | : | |
| 602-09-04-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 602-09-04-L 05 | Install panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-04-L 06 | Install shelf | 1 | 12/13/24 | 12/13/24 | 1.0h | : | |
| 602-09-05 | Wall | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 602-09-05-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 602-09-05-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 602-09-05-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 602-09-05-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 602-09-05-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 602-09-05-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 602-09-05-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 602-09-05-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 602-09-05-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 602-09-05-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 602-09-05-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 602-09-06 | Ceiling | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 602-09-06-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 602-09-06-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 602-09-06-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 602-09-06-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 602-09-06-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-07 | Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 602-09-07-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 602-09-07-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 602-09-07-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 602-09-07-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 602-09-08 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 602-09-08-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 602-09-08-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 602-09-08-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 602-09-08-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-08-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-09-09 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 602-09-09-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 602-09-09-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 602-09-09-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 603 | Guest Bathroom 1 | 142 | 12/06/24 | 12/13/24 | 2.4w | : | |
| 603-09 | Carpentry | 142 | 12/06/24 | 12/13/24 | 1.0w | : | |
| 603-09-01 | Room Framing | 32 | 12/06/24 | 12/13/24 | 41.0h | : | |
| 603-09-01-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 603-09-01-L 01 | Install cabin side paneling | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 603-09-01-L 02 | Frame shower enclousre | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 603-09-01-L 03 | Install shower sub-floor | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 603-09-01-L 04 | Fabricate shower overhead panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 603-09-01-L 05 | West system shower enclosure | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 603-09-01-L 06 | Install overhead framing | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 603-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 603-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 603-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 603-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 603-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 603-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 603-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 603-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 603-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 603-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 603-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 603-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 603-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 603-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 603-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 603-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 603-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 603-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 603-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 603-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 603-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 603-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 603-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 603-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 603-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 603-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 603-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 603-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 604 | Guest Stateroom 2 | 407 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 604-09 | Carpentry | 407 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 604-09-01 | Room Framing | 88 | 11/29/24 | 12/13/24 | 88.0h | : | |
| 604-09-01-L | Labor | 88 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 604-09-01-L 01 | Install shipside framing | 16 | 11/29/24 | 12/02/24 | 16.0h | : | |
| 604-09-01-L 02 | Install portlight framing | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 604-09-01-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 604-09-01-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 604-09-01-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 604-09-01-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 604-09-02 | AC Plenum | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 604-09-02-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 604-09-02-L 01 | Fabricate AC plenum | 32 | 12/04/24 | 12/10/24 | 32.0h | : | |
| 604-09-02-L 02 | Install AC plenum | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 604-09-02-L 03 | Rough in AC ducting | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 604-09-02-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-03 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 604-09-03-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 604-09-03-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 604-09-03-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 604-09-03-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-03-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-04 | Nightstand | 13 | 12/12/24 | 12/13/24 | 13.0h | : | |
| 604-09-04-L | Labor | 13 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 604-09-04-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 604-09-04-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 604-09-04-L 03 | Fabricate upper rail/Countertop | 2 | 12/12/24 | 12/13/24 | 2.0h | : | |
| 604-09-04-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 604-09-04-L 05 | Install panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-04-L 06 | Install shelf | 1 | 12/13/24 | 12/13/24 | 1.0h | : | |
| 604-09-05 | Wall | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 604-09-05-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 604-09-05-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 604-09-05-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 604-09-05-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 604-09-05-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 604-09-05-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 604-09-05-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 604-09-05-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 604-09-05-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 604-09-05-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 604-09-05-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 604-09-06 | Ceiling | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 604-09-06-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 604-09-06-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 604-09-06-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 604-09-06-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 604-09-06-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-07 | Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 604-09-07-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 604-09-07-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 604-09-07-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 604-09-07-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 604-09-08 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 604-09-08-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 604-09-08-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 604-09-08-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 604-09-08-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-08-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-09-09 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 604-09-09-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 604-09-09-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 604-09-09-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 605 | Guest Bathroom 2 | 172 | 12/04/24 | 12/13/24 | 2.4w | : | |
| 605-09 | Carpentry | 172 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 605-09-01 | Room Framing | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 605-09-01-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 605-09-01-L 01 | Install cabin side paneling | 8 | 12/04/24 | 12/05/24 | 8.0h | : | |
| 605-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 605-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 605-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 605-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 605-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 605-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-09-02 | Sink Vanity Cabinet | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 605-09-02-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 605-09-02-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 605-09-02-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 605-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 605-09-02-L 04 | Install finish panels/door | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 605-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-02-L 06 | Install pipe box around plumbing | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-02-L 07 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-03 | Medicine Cabinet | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 605-09-03-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 605-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 605-09-03-L 02 | Install verical light recesses | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-03-L 04 | Install doors | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-09-04 | Walls | 30 | 12/10/24 | 12/13/24 | 30.0h | : | |
| 605-09-04-M | Labor | 30 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 605-09-04-M 01 | Install Ship side finish wood panel | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 605-09-04-M 02 | Install fwd finish wood panel | 4 | 12/10/24 | 12/11/24 | 4.0h | : | |
| 605-09-04-M 03 | Install fwd finish wood panel molding | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 605-09-04-M 04 | Install base board | 6 | 12/11/24 | 12/12/24 | 6.0h | : | |
| 605-09-04-M 05 | Prep walls for wall coverings | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 605-09-04-M 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 605-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 605-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 605-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 605-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 605-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 605-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 605-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 605-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 605-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 605-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 605-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 605-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606 | Guest Stateroom 3 | 592 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 606-09 | Carpentry | 592 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 606-09-02 | Room Assembly | 116 | 11/25/24 | 12/13/24 | 116.0h | : | |
| 606-09-02-L | Labor | 116 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 606-09-02-L 01 | Install shipside framing | 32 | 11/25/24 | 11/29/24 | 32.0h | : | |
| 606-09-02-L 02 | Install portlight framing | 24 | 11/29/24 | 12/04/24 | 24.0h | : | |
| 606-09-02-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 606-09-02-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 606-09-02-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 606-09-02-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-05 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 606-09-05-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 606-09-05-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 606-09-05-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 606-09-05-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-05-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-06 | Nightstands | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-06-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-06-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-06-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-06-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-06-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-06-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-06-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-07 | Dresser Cabinet | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-07-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-07-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-07-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-07-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-07-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-07-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-07-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-08 | Vanity | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-08-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-08-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-08-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-08-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-08-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-08-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-08-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-09 | TV Cabinet | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-09-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-09-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-09-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-09-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-09-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-09-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-09-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-10 | AC Plenum | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-10-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-10-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-10-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-10-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-10-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-10-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-10-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-11 | Closet | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-11-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-11-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-11-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-11-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-11-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-11-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-11-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-12 | Window Box | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-12-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 606-09-12-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-12-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-12-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-12-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-12-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-12-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 606-09-13 | Panels - Ceiling | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 606-09-13-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 606-09-13-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 606-09-13-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 606-09-13-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 606-09-13-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 606-09-13-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 606-09-13-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 606-09-13-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 606-09-13-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 606-09-13-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 606-09-13-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 606-09-14 | Panels - Wall | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 606-09-14-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 606-09-14-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 606-09-14-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 606-09-14-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 606-09-14-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-15 | Panels - Headboard | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 606-09-15-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 606-09-15-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 606-09-15-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 606-09-15-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 606-09-15-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-16 | Moulding - Ceiling | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 606-09-16-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 606-09-16-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 606-09-16-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 606-09-16-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-16-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-17 | Moulding - Crown | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 606-09-17-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 606-09-17-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 606-09-17-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 606-09-17-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-17-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-18 | Moulding - Baseboard | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 606-09-18-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 606-09-18-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 606-09-18-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 606-09-18-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-18-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-09-19 | Entry Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 606-09-19-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 606-09-19-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 606-09-19-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 606-09-19-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 606-09-20 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 606-09-20-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 606-09-20-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 606-09-20-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 607 | Guest Bathroom 3 | 186 | 12/02/24 | 12/13/24 | 2.4w | : | |
| 607-09 | Carpentry | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 607-09-01 | Room Framing | 76 | 12/02/24 | 12/13/24 | 76.0h | : | |
| 607-09-01-L | Labor | 76 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 607-09-01-L 01 | Install cabin side paneling | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 607-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 607-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 607-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 607-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 607-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 607-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 607-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 607-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 607-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 607-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 607-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 607-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 607-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 607-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 607-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 607-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 607-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 607-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 607-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 607-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 607-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 607-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 607-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 607-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 607-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 607-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 607-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 607-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 607-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 607-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 607-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 607-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 607-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608 | Guest Stateroom 4 | 592 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 608-09 | Carpentry | 592 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 608-09-02 | Room Assembly | 116 | 11/25/24 | 12/13/24 | 116.0h | : | |
| 608-09-02-L | Labor | 116 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 608-09-02-L 01 | Install shipside framing | 32 | 11/25/24 | 11/29/24 | 32.0h | : | |
| 608-09-02-L 02 | Install portlight framing | 24 | 11/29/24 | 12/04/24 | 24.0h | : | |
| 608-09-02-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 608-09-02-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 608-09-02-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 608-09-02-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-05 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 608-09-05-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 608-09-05-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 608-09-05-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 608-09-05-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-05-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-06 | Nightstands | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-06-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-06-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-06-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-06-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-06-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-06-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-06-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-07 | Dresser Cabinet | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-07-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-07-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-07-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-07-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-07-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-07-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-07-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-08 | Vanity | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-08-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-08-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-08-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-08-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-08-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-08-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-08-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-09 | TV Cabinet | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-09-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-09-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-09-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-09-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-09-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-09-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-09-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-10 | AC Plenum | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-10-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-10-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-10-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-10-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-10-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-10-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-10-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-11 | Closet | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-11-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-11-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-11-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-11-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-11-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-11-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-11-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-12 | Window Box | 14 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-12-L | Labor | 14 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 608-09-12-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-12-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-12-L 03 | Install side panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-12-L 04 | Install drawers | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-12-L 05 | Install toe kick finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-12-L 06 | Install countertop finish panels | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 608-09-13 | Panels - Ceiling | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 608-09-13-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 608-09-13-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 608-09-13-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 608-09-13-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 608-09-13-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 608-09-13-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 608-09-13-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 608-09-13-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 608-09-13-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 608-09-13-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 608-09-13-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 608-09-14 | Panels - Wall | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 608-09-14-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 608-09-14-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 608-09-14-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 608-09-14-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 608-09-14-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-15 | Panels - Headboard | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 608-09-15-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 608-09-15-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 608-09-15-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 608-09-15-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 608-09-15-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-16 | Moulding - Ceiling | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 608-09-16-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 608-09-16-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 608-09-16-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 608-09-16-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-16-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-17 | Moulding - Crown | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 608-09-17-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 608-09-17-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 608-09-17-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 608-09-17-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-17-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-18 | Moulding - Baseboard | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 608-09-18-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 608-09-18-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 608-09-18-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 608-09-18-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-18-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-09-19 | Entry Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 608-09-19-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 608-09-19-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 608-09-19-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 608-09-19-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 608-09-20 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 608-09-20-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 608-09-20-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 608-09-20-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 609 | Guest Bathroom 4 | 186 | 12/02/24 | 12/13/24 | 2.4w | : | |
| 609-09 | Carpentry | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 609-09-01 | Room Framing | 76 | 12/02/24 | 12/13/24 | 76.0h | : | |
| 609-09-01-L | Labor | 76 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 609-09-01-L 01 | Install cabin side paneling | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 609-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 609-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 609-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 609-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 609-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 609-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 609-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 609-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 609-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 609-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 609-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 609-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 609-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 609-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 609-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 609-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 609-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 609-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 609-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 609-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 609-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 609-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 609-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 609-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 609-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 609-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 609-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 609-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 609-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 609-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 609-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 609-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 609-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 615 | Lower Guest Foyer - STBD | 148 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 615-09 | Carpentry | 148 | 12/05/24 | 12/13/24 | 52.0h | : | |
| 615-09-01 | Room Framing | 52 | 12/05/24 | 12/13/24 | 52.0h | : | |
| 615-09-01-L | Labor | 52 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 615-09-01-L 01 | Install shipside framing | 8 | 12/05/24 | 12/06/24 | 8.0h | : | |
| 615-09-01-L 02 | Install portlight framing | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 615-09-01-L 03 | Frame closet sides | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 615-09-01-L 04 | Frame stairway walls | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 615-09-01-L 05 | Install stariway steps | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 615-09-01-L 06 | Install ceiling head box | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 615-09-01-L 07 | Install ceiling box framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 615-09-01-L 08 | Rough in window box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 615-09-02 | Ship side Cabinet (S) | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 615-09-02-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 615-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 615-09-02-L 02 | Install toe kick molding | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 615-09-02-L 03 | Install base frame cabinets | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 615-09-02-L 04 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 615-09-02-L 05 | Install cabinet doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 615-09-02-L 06 | Install countertop | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 615-09-02-L 07 | Install countertop edge molding | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 615-09-03 | Wall | 44 | 12/06/24 | 12/13/24 | 44.0h | : | |
| 615-09-03-L | Labor | 44 | 12/06/24 | 12/13/24 | 1.1w | : | |
| 615-09-03-L 01 | Install wood panels | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 615-09-03-L 02 | Install column at stairway | 8 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 615-09-03-L 03 | Install simple base board molding | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 615-09-03-L 04 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 615-09-04 | Ceiling | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 615-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 615-09-04-L 01 | Install simple perimeter crown molding | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 615-09-04-L 02 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 615-09-05 | Finish Trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 615-09-05-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 615-09-05-L 01 | Install overhead panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 619 | LOWER CREW FRAMING | 520 | 11/26/24 | 12/13/24 | 4.2w | : | |
| 619-09 | Carpentry | 520 | 11/26/24 | 12/13/24 | 2.7w | : | |
| 619-09-01 | Joiner Floor | 240 | 11/27/24 | 12/13/24 | 100.0h | : | |
| 619-09-01-L | Labor | 240 | 11/28/24 | 12/13/24 | 2.4w | : | |
| 619-09-01-L 01 | Cut floor panels | 24 | 12/03/24 | 12/05/24 | 24.0h | : | |
| 619-09-01-L 02 | Fabricate sound damping foundation strips | 72 | 11/28/24 | 12/02/24 | 24.0h | : | |
| 619-09-01-L 03 | Install floor panels foundation strips | 72 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 619-09-01-L 04 | Install sub-floor panels | 72 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 619-09-02 | Bulkheads/Cabins | 280 | 11/26/24 | 12/13/24 | 108.0h | : | |
| 619-09-02-L | Labor | 280 | 11/26/24 | 12/13/24 | 2.7w | : | |
| 619-09-02-L 01 | Cut all shipside and inner wall panels | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 619-09-02-L 02 | Cut all AC and window boxes | 40 | 11/26/24 | 12/03/24 | 40.0h | : | |
| 619-09-02-L 03 | Assemble all shipside and inner wall panels | 48 | 12/03/24 | 12/06/24 | 24.0h | : | |
| 619-09-02-L 04 | Assemble all AC and window boxes | 24 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 619-09-02-L 05 | Dry-fit all shipside and inner wall panels onboard | 32 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 619-09-02-L 06 | Dry-fit all AC and window boxes onboard | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 619-09-02-L 07 | Install all shipside and inner wall panels onboard | 32 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 619-09-02-L 08 | Install all AC and window boxes onboard | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 620 | Captain's cabin 1 | 435 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 620-09 | Carpentry | 435 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 620-09-01 | Room Framing | 116 | 11/25/24 | 12/13/24 | 116.0h | : | |
| 620-09-01-L | Labor | 116 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 620-09-01-L 01 | Install shipside framing | 32 | 11/25/24 | 11/29/24 | 32.0h | : | |
| 620-09-01-L 02 | Install portlight framing | 24 | 11/29/24 | 12/04/24 | 24.0h | : | |
| 620-09-01-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 620-09-01-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 620-09-01-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 620-09-01-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 620-09-02 | AC Plenum | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 620-09-02-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 620-09-02-L 01 | Fabricate AC plenum | 32 | 12/04/24 | 12/10/24 | 32.0h | : | |
| 620-09-02-L 02 | Install AC plenum | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 620-09-02-L 03 | Rough in AC ducting | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 620-09-02-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-03 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 620-09-03-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 620-09-03-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 620-09-03-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 620-09-03-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-03-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-04 | Nightstand | 13 | 12/12/24 | 12/13/24 | 13.0h | : | |
| 620-09-04-L | Labor | 13 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 620-09-04-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 620-09-04-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 620-09-04-L 03 | Fabricate upper rail/Countertop | 2 | 12/12/24 | 12/13/24 | 2.0h | : | |
| 620-09-04-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 620-09-04-L 05 | Install panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-04-L 06 | Install shelf | 1 | 12/13/24 | 12/13/24 | 1.0h | : | |
| 620-09-05 | Wall | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 620-09-05-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 620-09-05-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 620-09-05-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 620-09-05-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 620-09-05-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 620-09-05-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 620-09-05-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 620-09-05-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 620-09-05-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 620-09-05-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 620-09-05-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 620-09-06 | Ceiling | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 620-09-06-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 620-09-06-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 620-09-06-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 620-09-06-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 620-09-06-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-07 | Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 620-09-07-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 620-09-07-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 620-09-07-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 620-09-07-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 620-09-08 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 620-09-08-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 620-09-08-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 620-09-08-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 620-09-08-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-08-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-09-09 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 620-09-09-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 620-09-09-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 620-09-09-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 621 | Captain's Bathroom | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 621-09 | Carpentry | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 621-09-01 | Room Framing | 76 | 12/02/24 | 12/13/24 | 76.0h | : | |
| 621-09-01-L | Labor | 76 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 621-09-01-L 01 | Install cabin side paneling | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 621-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 621-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 621-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 621-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 621-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 621-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 621-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 621-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 621-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 621-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 621-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 621-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 621-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 621-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 621-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 621-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 621-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 621-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 621-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 621-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 621-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 621-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 621-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 621-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 621-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 621-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 621-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 621-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 621-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 621-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 621-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 621-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 621-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 622 | Crew cabin 1 | 435 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 622-09 | Carpentry | 435 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 622-09-01 | Room Framing | 116 | 11/25/24 | 12/13/24 | 116.0h | : | |
| 622-09-01-L | Labor | 116 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 622-09-01-L 01 | Install shipside framing | 32 | 11/25/24 | 11/29/24 | 32.0h | : | |
| 622-09-01-L 02 | Install portlight framing | 24 | 11/29/24 | 12/04/24 | 24.0h | : | |
| 622-09-01-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 622-09-01-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 622-09-01-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 622-09-01-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 622-09-02 | AC Plenum | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 622-09-02-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 622-09-02-L 01 | Fabricate AC plenum | 32 | 12/04/24 | 12/10/24 | 32.0h | : | |
| 622-09-02-L 02 | Install AC plenum | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 622-09-02-L 03 | Rough in AC ducting | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 622-09-02-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-03 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 622-09-03-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 622-09-03-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 622-09-03-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 622-09-03-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-03-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-04 | Nightstand | 13 | 12/12/24 | 12/13/24 | 13.0h | : | |
| 622-09-04-L | Labor | 13 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 622-09-04-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 622-09-04-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 622-09-04-L 03 | Fabricate upper rail/Countertop | 2 | 12/12/24 | 12/13/24 | 2.0h | : | |
| 622-09-04-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 622-09-04-L 05 | Install panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-04-L 06 | Install shelf | 1 | 12/13/24 | 12/13/24 | 1.0h | : | |
| 622-09-05 | Wall | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 622-09-05-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 622-09-05-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 622-09-05-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 622-09-05-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 622-09-05-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 622-09-05-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 622-09-05-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 622-09-05-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 622-09-05-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 622-09-05-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 622-09-05-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 622-09-06 | Ceiling | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 622-09-06-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 622-09-06-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 622-09-06-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 622-09-06-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 622-09-06-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-07 | Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 622-09-07-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 622-09-07-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 622-09-07-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 622-09-07-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 622-09-08 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 622-09-08-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 622-09-08-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 622-09-08-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 622-09-08-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-08-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-09-09 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 622-09-09-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 622-09-09-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 622-09-09-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 623 | Crew Bathroom | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 623-09 | Carpentry | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 623-09-01 | Room Framing | 76 | 12/02/24 | 12/13/24 | 76.0h | : | |
| 623-09-01-L | Labor | 76 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 623-09-01-L 01 | Install cabin side paneling | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 623-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 623-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 623-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 623-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 623-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 623-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 623-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 623-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 623-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 623-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 623-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 623-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 623-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 623-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 623-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 623-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 623-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 623-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 623-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 623-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 623-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 623-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 623-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 623-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 623-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 623-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 623-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 623-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 623-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 623-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 623-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 623-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 623-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 624 | Crew cabin 2 | 435 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 624-09 | Carpentry | 435 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 624-09-01 | Room Framing | 116 | 11/25/24 | 12/13/24 | 116.0h | : | |
| 624-09-01-L | Labor | 116 | 11/25/24 | 12/13/24 | 2.9w | : | |
| 624-09-01-L 01 | Install shipside framing | 32 | 11/25/24 | 11/29/24 | 32.0h | : | |
| 624-09-01-L 02 | Install portlight framing | 24 | 11/29/24 | 12/04/24 | 24.0h | : | |
| 624-09-01-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 624-09-01-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 624-09-01-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 624-09-01-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 624-09-02 | AC Plenum | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 624-09-02-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 624-09-02-L 01 | Fabricate AC plenum | 32 | 12/04/24 | 12/10/24 | 32.0h | : | |
| 624-09-02-L 02 | Install AC plenum | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 624-09-02-L 03 | Rough in AC ducting | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 624-09-02-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-03 | Bed | 14 | 12/12/24 | 12/13/24 | 14.0h | : | |
| 624-09-03-L | Labor | 14 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 624-09-03-L 01 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 624-09-03-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 624-09-03-L 03 | Install side/foot rails | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-03-L 04 | Install upper rail | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-04 | Nightstand | 13 | 12/12/24 | 12/13/24 | 13.0h | : | |
| 624-09-04-L | Labor | 13 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 624-09-04-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 624-09-04-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 624-09-04-L 03 | Fabricate upper rail/Countertop | 2 | 12/12/24 | 12/13/24 | 2.0h | : | |
| 624-09-04-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 624-09-04-L 05 | Install panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-04-L 06 | Install shelf | 1 | 12/13/24 | 12/13/24 | 1.0h | : | |
| 624-09-05 | Wall | 78 | 12/02/24 | 12/13/24 | 78.0h | : | |
| 624-09-05-L | Labor | 78 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 624-09-05-L 01 | Install finish walls boxes at FWD nightstand | 4 | 12/02/24 | 12/02/24 | 4.0h | : | |
| 624-09-05-L 02 | Install finish walls boxes at AFT nightstand | 4 | 12/02/24 | 12/03/24 | 4.0h | : | |
| 624-09-05-L 03 | Clean and prep walls for wall covering | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 624-09-05-L 04 | Install finish window box panels (sides/top/bottom) | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 624-09-05-L 05 | Install finish window box pilasters | 6 | 12/06/24 | 12/06/24 | 6.0h | : | |
| 624-09-05-L 06 | Install finish window box picture framing | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 624-09-05-L 07 | Install simple Base board molding | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 624-09-05-L 08 | Install portlight panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 624-09-05-L 09 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 624-09-05-L 10 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 624-09-06 | Ceiling | 60 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 624-09-06-L | Labor | 60 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 624-09-06-L 01 | Install simple perimeter crown molding | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 624-09-06-L 02 | Install AC grill finish panel | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 624-09-06-L 03 | Fabricate ceiling panels | 40 | 12/06/24 | 12/13/24 | 40.0h | : | |
| 624-09-06-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-07 | Doors | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 624-09-07-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 624-09-07-L 01 | Prep door opening to receive door jabs | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 624-09-07-L 02 | Install entry door casing and Jabs (3) | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 624-09-07-L 03 | Install entry doors (3) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 624-09-08 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 624-09-08-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 624-09-08-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 624-09-08-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 624-09-08-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-08-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-09-09 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 624-09-09-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 624-09-09-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 624-09-09-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 625 | Crew Bathroom 2 | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 625-09 | Carpentry | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 625-09-01 | Room Framing | 76 | 12/02/24 | 12/13/24 | 76.0h | : | |
| 625-09-01-L | Labor | 76 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 625-09-01-L 01 | Install cabin side paneling | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 625-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 625-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 625-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 625-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 625-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 625-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 625-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 625-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 625-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 625-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 625-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 625-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 625-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 625-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 625-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 625-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 625-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 625-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 625-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 625-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 625-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 625-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 625-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 625-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 625-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 625-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 625-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 625-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 625-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 625-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 625-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 625-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 625-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 635 | Laundry | 148 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 635-09 | Carpentry | 148 | 12/05/24 | 12/13/24 | 52.0h | : | |
| 635-09-01 | Room Framing | 52 | 12/05/24 | 12/13/24 | 52.0h | : | |
| 635-09-01-L | Labor | 52 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 635-09-01-L 01 | Install shipside framing | 8 | 12/05/24 | 12/06/24 | 8.0h | : | |
| 635-09-01-L 02 | Install portlight framing | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 635-09-01-L 03 | Frame closet sides | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 635-09-01-L 04 | Frame stairway walls | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 635-09-01-L 05 | Install stariway steps | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 635-09-01-L 06 | Install ceiling head box | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 635-09-01-L 07 | Install ceiling box framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 635-09-01-L 08 | Rough in window box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 635-09-02 | Ship side Cabinet (S) | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 635-09-02-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 635-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 635-09-02-L 02 | Install toe kick molding | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 635-09-02-L 03 | Install base frame cabinets | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 635-09-02-L 04 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 635-09-02-L 05 | Install cabinet doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 635-09-02-L 06 | Install countertop | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 635-09-02-L 07 | Install countertop edge molding | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 635-09-03 | Wall | 44 | 12/06/24 | 12/13/24 | 44.0h | : | |
| 635-09-03-L | Labor | 44 | 12/06/24 | 12/13/24 | 1.1w | : | |
| 635-09-03-L 01 | Install wood panels | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 635-09-03-L 02 | Install column at stairway | 8 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 635-09-03-L 03 | Install simple base board molding | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 635-09-03-L 04 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 635-09-04 | Ceiling | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 635-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 635-09-04-L 01 | Install simple perimeter crown molding | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 635-09-04-L 02 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 635-09-05 | Finish Trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 635-09-05-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 635-09-05-L 01 | Install overhead panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636 | Crew Lounge area | 344 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 636-09 | Carpentry | 344 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 636-09-01 | Room Framing | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 636-09-01-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 636-09-01-L 01 | Install cabin side framing port | 24 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 636-09-01-L 02 | Install port window boxes | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 636-09-01-L 03 | Install cabin side paneling port | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 636-09-01-L 04 | Frame out for refrigerator | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 636-09-01-L 05 | Frame out stairway walls | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 636-09-01-L 06 | Frame out stairway steps | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 636-09-02 | AC Plenums | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 636-09-02-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 636-09-02-L 01 | Fabricate AC plenum aft | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 636-09-02-L 02 | Install AC plenum aft | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 636-09-02-L 03 | Rough in AC ducting port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-02-L 04 | Connect AC ducting to plenum | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-03 | Sink cabinet | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 636-09-03-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 636-09-03-L 01 | Install toe kick | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 636-09-03-L 02 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-09-03-L 03 | Install finish panels | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-09-03-L 04 | Install drawer front panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-03-L 05 | Install door panels | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 636-09-03-L 06 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-04 | Lower cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 636-09-04-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 636-09-04-L 01 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-09-04-L 02 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-04-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-04-L 04 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-04-L 05 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-05 | Upper Cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 636-09-05-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 636-09-05-L 01 | Install base frame | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-09-05-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-05-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-05-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-05-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-06 | Pantry | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 636-09-06-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 636-09-06-L 01 | Install base frame | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 636-09-06-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-06-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-06-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-06-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-07 | Wall | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 636-09-07-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 636-09-07-L 01 | Install fwd bhd storage cabinets | 12 | 12/02/24 | 12/03/24 | 12.0h | : | |
| 636-09-07-L 02 | Install fwd bhd storage cabinets doors | 4 | 12/03/24 | 12/03/24 | 4.0h | : | |
| 636-09-07-L 03 | Install fwd bulkhead AC grills | 4 | 12/04/24 | 12/04/24 | 4.0h | : | |
| 636-09-07-L 04 | Install fwd bulkhead wood panels | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 636-09-07-L 05 | Install STB shipside wood panels | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 636-09-07-L 06 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 636-09-07-L 07 | Install simple Base board | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 636-09-08 | Windows | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 636-09-08-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 636-09-08-L 01 | Install window boxes | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-09-08-L 02 | Install window pilasters | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-08-L 03 | Install window sill molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-08-L 04 | Install window valances | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-08-L 05 | Install window panel | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-09 | Appliances | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 636-09-09-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 636-09-09-L 01 | Install dishwahers | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-09-L 02 | Install double ovens | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-09-09-L 03 | Install microwave | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-09-L 04 | Install icemaker | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636-09-10 | Ceiling | 24 | 12/02/24 | 12/13/24 | 75.0h | : | |
| 636-09-10-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 636-09-10-L 01 | Fab overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 636-09-11 | Trim | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 636-09-11-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 636-09-11-L 01 | Install overhead panels | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 640 | MAIN DECK FRAMING | 864 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 640-09 | Carpentry | 864 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 640-09-01 | Joiner Floor | 400 | 11/18/24 | 12/13/24 | 160.0h | : | |
| 640-09-01-L | Labor | 400 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 640-09-01-L 01 | Cut floor panels | 40 | 11/25/24 | 11/29/24 | 40.0h | : | |
| 640-09-01-L 02 | Fabricate sound damping foundation strips | 120 | 11/18/24 | 11/22/24 | 40.0h | : | |
| 640-09-01-L 03 | Install floor panels foundation strips | 120 | 12/02/24 | 12/06/24 | 40.0h | : | |
| 640-09-01-L 04 | Install sub-floor panels | 120 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 640-09-02 | Bulkheads/Cabins | 464 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 640-09-02-L | Labor | 464 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 640-09-02-L 01 | Cut all shipside and inner wall panels | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 640-09-02-L 02 | Cut all AC and window boxes | 40 | 11/15/24 | 11/21/24 | 40.0h | : | |
| 640-09-02-L 03 | Assemble all shipside and inner wall panels | 64 | 11/22/24 | 11/27/24 | 32.0h | : | |
| 640-09-02-L 04 | Assemble all AC and window boxes | 64 | 11/28/24 | 12/03/24 | 32.0h | : | |
| 640-09-02-L 05 | Dry-fit all shipside and inner wall panels onboard | 64 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 640-09-02-L 06 | Dry-fit all AC and window boxes onboard | 64 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 640-09-02-L 07 | Install all shipside and inner wall panels onboard | 64 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 640-09-02-L 08 | Install all AC and window boxes onboard | 64 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 641 | Owners Stateroom | 442 | 11/29/24 | 12/13/24 | 3.2w | : | |
| 641-09 | Carpentry | 442 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 641-09-01 | Room Framing | 88 | 11/29/24 | 12/13/24 | 88.0h | : | |
| 641-09-01-L | Labor | 88 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 641-09-01-L 01 | Install shipside framing | 16 | 11/29/24 | 12/02/24 | 16.0h | : | |
| 641-09-01-L 02 | Install portlight framing | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 641-09-01-L 03 | Frame closet sides | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 641-09-01-L 04 | Install overhead framing | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 641-09-01-L 05 | Rough in window box | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 641-09-01-L 06 | Provide accesses to pipes/wiring | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 641-09-02 | AC Plenum (P) | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 641-09-02-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 641-09-02-L 01 | Fabricate AC plenum | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 641-09-02-L 02 | Install AC plenum | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-09-02-L 03 | Rough in AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-02-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-03 | AC Plenum (S) | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 641-09-03-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 641-09-03-L 01 | Fabricate AC plenum | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 641-09-03-L 02 | Install AC plenum | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-09-03-L 03 | Rough in AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-03-L 04 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-04 | Bed | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 641-09-04-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 641-09-04-L 01 | Install toe kick | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-04-L 02 | Install base frame | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-04-L 03 | Install side/foot rails | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-04-L 04 | Install upper rail | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-05 | Nightstand | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 641-09-05-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 641-09-05-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-05-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-05-L 03 | Fabricate upper rail/Countertop | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-05-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-05-L 05 | Install panels/door | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-05-L 06 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-06 | Dresser Cabinet (P) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 641-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 641-09-06-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-06-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-06-L 03 | Fabricate upper rail/Countertop | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-06-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-06-L 05 | Install panels/door | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-06-L 06 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-07 | Dresser Cabinet (S) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 641-09-07-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 641-09-07-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-07-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-07-L 03 | Fabricate upper rail/Countertop | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-07-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-07-L 05 | Install panels/door | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-07-L 06 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-08 | TV Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 641-09-08-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 641-09-08-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-08-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 641-09-08-L 03 | Fabricate upper rail/Countertop | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-08-L 04 | Install filler piece to bed | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-08-L 05 | Install panels/door | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-08-L 06 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 641-09-09 | Wall | 52 | 12/05/24 | 12/13/24 | 52.0h | : | |
| 641-09-09-L | Labor | 52 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 641-09-09-L 04 | Install finish walls boxes at FWD nightstand | 4 | 12/05/24 | 12/05/24 | 4.0h | : | |
| 641-09-09-L 05 | Install finish walls boxes at AFT nightstand | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 641-09-09-L 06 | Clean and prep walls for wall covering | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 641-09-09-L 07 | Install simple Base board molding | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 641-09-09-L 08 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 641-09-09-L 09 | Fab headboard panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 641-09-10 | Ceiling | 52 | 12/05/24 | 12/13/24 | 52.0h | : | |
| 641-09-10-L | Labor | 52 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 641-09-10-L 01 | Install simple perimeter crown molding | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 641-09-10-L 02 | Install AC grill finish panel | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 641-09-10-L 03 | Fabricate ceiling panels | 32 | 12/09/24 | 12/13/24 | 32.0h | : | |
| 641-09-10-L 04 | Install perimeter AC soffit | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-11 | Doors | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 641-09-11-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 641-09-11-L 01 | Prep door opening to receive door jabs | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-09-11-L 02 | Install entry door casing and Jabs (3) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-11-L 03 | Install entry doors (3) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641-09-12 | Windows (P) | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 641-09-12-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 641-09-12-L 01 | Install window boxes (Port) | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 641-09-12-L 02 | Install window pilasters (Port) | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 641-09-12-L 03 | Install window sill molding (Port) | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-09-12-L 04 | Install window valances (Port) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 641-09-13 | Windows (S) | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 641-09-13-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 641-09-13-L 01 | Install window boxes (STB) | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 641-09-13-L 02 | Install window pilasters (STB) | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 641-09-13-L 03 | Install window sill molding (STB) | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-09-13-L 04 | Install window valances (STB) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 641-09-14 | Aft Windows | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 641-09-14-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 641-09-14-L 01 | Install fwd window boxes | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 641-09-14-L 02 | Install fwd window mullion boxes | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 641-09-14-L 03 | Install fwd window panels | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 641-09-14-L 04 | Install fwd window sill molding | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-09-14-L 05 | Install window upper valance | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 641-09-15 | Trim | 10 | 12/12/24 | 12/13/24 | 10.0h | : | |
| 641-09-15-L | Labor | 10 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 641-09-15-L 01 | Install upholstered bed trim | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 641-09-15-L 02 | Install finished ceiling panels | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 642 | Owners Closet | 172 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 642-09 | Carpentry | 172 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 642-09-01 | Room Framing | 52 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 642-09-01-L | Labor | 52 | 12/05/24 | 12/13/24 | 1.3w | : | |
| 642-09-01-L 01 | Install shipside framing | 8 | 12/05/24 | 12/06/24 | 8.0h | : | |
| 642-09-01-L 02 | Install portlight framing | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 642-09-01-L 03 | Frame closet sides | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 642-09-01-L 04 | Frame stairway walls | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 642-09-01-L 05 | Install stariway steps | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 642-09-01-L 06 | Install ceiling head box | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 642-09-01-L 07 | Install ceiling box framing | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-01-L 08 | Rough in window box | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-02 | Doors | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 642-09-02-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 642-09-02-L 01 | Prep door opening to receive door jabs (P) | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 642-09-02-L 02 | Install entry door casing and Jabs (P) | 8 | 12/10/24 | 12/11/24 | 8.0h | : | |
| 642-09-02-L 03 | Install entry doors (P) | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 642-09-02-L 04 | Prep door opening to receive door jabs (S) | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 642-09-02-L 05 | Install entry door casing and Jabs (S) | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 642-09-02-L 06 | Install entry doors (S) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-03 | Windows | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 642-09-03-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 642-09-03-L 01 | Install window boxes (Port) | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 642-09-03-L 02 | Install window sill molding (Port) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-03-L 03 | Install window valances (Port) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-04 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 642-09-04-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 642-09-04-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 642-09-04-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 642-09-04-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-04-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-05 | Closet | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 642-09-05-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 642-09-05-L 01 | Install finish paneling | 24 | 12/09/24 | 12/12/24 | 24.0h | : | |
| 642-09-05-L 02 | Install lower cabinet frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 642-09-05-L 03 | Install lower cabinet trim/counter top | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 642-09-05-L 04 | Install lower cabinet shelves | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 643 | Owners Bathroom | 154 | 12/06/24 | 12/13/24 | 3.8w | : | |
| 643-09 | Carpentry | 154 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 643-09-01 | Room Framing | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 643-09-01-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 643-09-01-L 01 | Install cabin side paneling | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 643-09-01-L 02 | Frame shower enclousre | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 643-09-01-L 03 | Install shower sub-floor | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 643-09-01-L 04 | Fabricate shower overhead panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 643-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 643-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 643-09-01-L 07 | Cut pipe/electric accesses | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-01-L 08 | Rough AC ducting from stateroom | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-02 | Sink Vanity Cabinet | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 643-09-02-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 643-09-02-L 01 | Install toe kick | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 643-09-02-L 02 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 643-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 643-09-02-L 04 | Install finish panels/door | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 643-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-02-L 06 | Install pipe box around plumbing | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-02-L 07 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 643-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 643-09-03-L 01 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 643-09-03-L 02 | Install verical light recesses | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-03-L 04 | Install doors | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-09-04 | Walls | 30 | 12/10/24 | 12/13/24 | 30.0h | : | |
| 643-09-04-L | Labor | 30 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 643-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 643-09-04-L 02 | Install fwd finish wood panel | 4 | 12/10/24 | 12/11/24 | 4.0h | : | |
| 643-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 643-09-04-L 04 | Install base board | 6 | 12/11/24 | 12/12/24 | 6.0h | : | |
| 643-09-04-L 05 | Prep walls for wall coverings | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 643-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 643-09-05 | Ceiling | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 643-09-05-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 643-09-05-L 01 | Install simple perimeter crown molding | 6 | 12/09/24 | 12/10/24 | 6.0h | : | |
| 643-09-05-L 02 | Install AC grill finish panel | 2 | 12/10/24 | 12/10/24 | 2.0h | : | |
| 643-09-05-L 03 | Install perimeter AC soffit | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 643-09-05-L 04 | Fab overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 643-09-07 | Finish Trims | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 643-09-07-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 643-09-07-L 01 | Install overhead panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 643-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 645 | Galley | 408 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 645-09 | Carpentry | 408 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 645-09-01 | Room Framing | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 645-09-01-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 645-09-01-L 01 | Install cabin side framing port | 24 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 645-09-01-L 02 | Install port window boxes | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 645-09-01-L 03 | Install cabin side paneling port | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 645-09-01-L 04 | Frame out for refrigerator | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 645-09-01-L 05 | Frame out stairway walls | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 645-09-01-L 06 | Frame out stairway steps | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 645-09-02 | AC Plenums | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 645-09-02-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 645-09-02-L 01 | Fabricate AC plenum aft | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 645-09-02-L 02 | Install AC plenum aft | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 645-09-02-L 03 | Rough in AC ducting port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-02-L 04 | Connect AC ducting to plenum | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-03 | Breakfast Bar | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 645-09-03-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 645-09-03-L 01 | Install toe kick | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-03-L 02 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-03-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-03-L 04 | Install drawer front panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-03-L 05 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-03-L 06 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-04 | Sink cabinet | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 645-09-04-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 645-09-04-L 01 | Install toe kick | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 645-09-04-L 02 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-04-L 03 | Install finish panels | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-04-L 04 | Install drawer front panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-04-L 05 | Install door panels | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 645-09-04-L 06 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-05 | Cook top lower cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 645-09-05-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 645-09-05-L 01 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-05-L 02 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-05-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-05-L 04 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-05-L 05 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-06 | Oven Cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 645-09-06-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 645-09-06-L 01 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-06-L 02 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-06-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-06-L 04 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-06-L 05 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-07 | Cook top Upper Cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 645-09-07-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 645-09-07-L 01 | Install base frame | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-07-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-07-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-07-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-07-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-08 | Breakfast Bar Upper Cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 645-09-08-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 645-09-08-L 01 | Install base frame | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-08-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-08-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-08-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-08-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-09 | Pantry | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 645-09-09-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 645-09-09-L 01 | Install base frame | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 645-09-09-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-09-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-09-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-09-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-10 | Wall | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 645-09-10-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 645-09-10-L 01 | Install fwd bhd storage cabinets | 12 | 12/02/24 | 12/03/24 | 12.0h | : | |
| 645-09-10-L 02 | Install fwd bhd storage cabinets doors | 4 | 12/03/24 | 12/03/24 | 4.0h | : | |
| 645-09-10-L 03 | Install fwd bulkhead AC grills | 4 | 12/04/24 | 12/04/24 | 4.0h | : | |
| 645-09-10-L 04 | Install fwd bulkhead wood panels | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 645-09-10-L 05 | Install STB shipside wood panels | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 645-09-10-L 06 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 645-09-10-L 07 | Install simple Base board | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 645-09-11 | Windows | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 645-09-11-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 645-09-11-L 01 | Install window boxes | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-09-11-L 02 | Install window pilasters | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-11-L 03 | Install window sill molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-11-L 04 | Install window valances | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-11-L 05 | Install window panel | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-12 | Appliances | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 645-09-12-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 645-09-12-L 01 | Install dishwahers | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-12-L 02 | Install double ovens | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-09-12-L 03 | Install microwave | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-12-L 04 | Install icemaker | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645-09-13 | Ceiling | 24 | 12/02/24 | 12/13/24 | 75.0h | : | |
| 645-09-13-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 645-09-13-L 01 | Fab overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 645-09-15 | Trim | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 645-09-15-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 645-09-15-L 01 | Install overhead panels | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 647 | Powder room | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 647-09 | Carpentry | 186 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 647-09-01 | Room Framing | 76 | 12/02/24 | 12/13/24 | 76.0h | : | |
| 647-09-01-L | Labor | 76 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 647-09-01-L 01 | Install cabin side paneling | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 647-09-01-L 02 | Frame shower enclousre | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 647-09-01-L 03 | Install shower sub-floor | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 647-09-01-L 04 | Fabricate shower overhead panel | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 647-09-01-L 05 | West system shower enclosure | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 647-09-01-L 06 | Install overhead framing | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 647-09-01-L 07 | Cut pipe/electric accesses | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-09-01-L 08 | Rough AC ducting from stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-09-02 | Sink Vanity Cabinet | 18 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 647-09-02-L | Labor | 18 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 647-09-02-L 01 | Install toe kick | 4 | 12/11/24 | 12/12/24 | 4.0h | : | |
| 647-09-02-L 02 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 647-09-02-L 03 | Install side filler pieces | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 647-09-02-L 04 | Install finish panels/door | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-09-02-L 05 | Install shelf | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-09-02-L 06 | Install sub-countertop for stone | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-09-03 | Medicine Cabinet | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 647-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 647-09-03-L 01 | Install base frame | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 647-09-03-L 02 | Install verical light recesses | 2 | 12/12/24 | 12/12/24 | 2.0h | : | |
| 647-09-03-L 03 | Install side filler pieces | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-09-03-L 04 | Install doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-09-03-L 05 | Install shelves | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-09-04 | Walls | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 647-09-04-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 647-09-04-L 01 | Install Ship side finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 647-09-04-L 02 | Install fwd finish wood panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 647-09-04-L 03 | Install fwd finish wood panel molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 647-09-04-L 04 | Install base board | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 647-09-04-L 05 | Prep walls for wall coverings | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-09-04-L 06 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-09-05 | Ceiling | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 647-09-05-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 647-09-05-L 01 | Install simple perimeter crown molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 647-09-05-L 02 | Install AC grill finish panel | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 647-09-05-L 03 | Install perimeter AC soffit | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 647-09-05-L 04 | Fab overhead panels | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 647-09-06 | Flooring | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 647-09-06-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 647-09-06-L 01 | Prep flooring for stonework | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 647-09-07 | Finish Trims | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 647-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 647-09-07-L 01 | Install overhead panels | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 647-09-07-L 02 | Install bathroom accessories | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 648 | Port Main Foyer | 104 | 12/09/24 | 12/13/24 | 1.7w | : | |
| 648-09 | Carpentry | 104 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 648-09-01 | Wall (P) | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 648-09-01-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 648-09-01-L 01 | Install wood panels (S) | 24 | 12/09/24 | 12/11/24 | 24.0h | : | |
| 648-09-01-L 02 | Install simple base board molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 648-09-01-L 03 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 648-09-02 | Wall (S) | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 648-09-02-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 648-09-02-L 01 | Install wood panels (S) | 24 | 12/09/24 | 12/11/24 | 24.0h | : | |
| 648-09-02-L 02 | Install simple base board molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 648-09-02-L 03 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 648-09-03 | Flooring (P) | 12 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 648-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 648-09-03-L 01 | Install perimeter molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 648-09-04 | Flooring (S) | 12 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 648-09-04-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 648-09-04-L 01 | Install perimeter molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 649 | STBD Main Foyer | 104 | 12/09/24 | 12/13/24 | 1.7w | : | |
| 649-09 | Carpentry | 104 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 649-09-01 | Wall (P) | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 649-09-01-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 649-09-01-L 01 | Install wood panels (S) | 24 | 12/09/24 | 12/11/24 | 24.0h | : | |
| 649-09-01-L 02 | Install simple base board molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 649-09-01-L 03 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 649-09-02 | Wall (S) | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 649-09-02-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 649-09-02-L 01 | Install wood panels (S) | 24 | 12/09/24 | 12/11/24 | 24.0h | : | |
| 649-09-02-L 02 | Install simple base board molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 649-09-02-L 03 | Cut in outlets/switches | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 649-09-03 | Flooring (P) | 12 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 649-09-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 649-09-03-L 01 | Install perimeter molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 649-09-04 | Flooring (S) | 12 | 12/11/24 | 12/13/24 | 18.0h | : | |
| 649-09-04-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 649-09-04-L 01 | Install perimeter molding | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 652 | Main Salon | 392 | 11/21/24 | 12/13/24 | 3.3w | : | |
| 652-09 | Carpentry | 392 | 11/21/24 | 12/13/24 | 3.3w | : | |
| 652-09-01 | Room Framing | 64 | 12/04/24 | 12/13/24 | 64.0h | : | |
| 652-09-01-L | Labor | 64 | 12/04/24 | 12/13/24 | 1.6w | : | |
| 652-09-01-L 01 | Install cabin side framing (P) | 8 | 12/04/24 | 12/04/24 | 8.0h | : | |
| 652-09-01-L 02 | Install port window boxes (P) | 8 | 12/05/24 | 12/05/24 | 8.0h | : | |
| 652-09-01-L 03 | Frame out pilasters (P) | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 652-09-01-L 04 | Install cabin side paneling (P) | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 652-09-01-L 05 | Install cabin side framing (S) | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 652-09-01-L 06 | Install window boxes (S) | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 652-09-01-L 07 | Frame out pilasters (S) | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 652-09-01-L 08 | Install cabin side paneling (S) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 652-09-02 | AC Plenum | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 652-09-02-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 652-09-02-L 01 | Fabricate AC plenum (P) | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 652-09-02-L 02 | Rough in AC ducting (P) | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-02-L 03 | Install AC plenum (P) | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-02-L 04 | Install AC valances (P) | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-02-L 05 | Fabricate AC plenum (S) | 8 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 652-09-02-L 06 | Rough in AC ducting (S) | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-02-L 07 | Install AC plenum (S) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-02-L 08 | Install AC valances (S) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-03 | Ship side fwd Cabinet (S) | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 652-09-03-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 652-09-03-L 01 | Install toe kick | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 652-09-03-L 02 | Install toe kick molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-03-L 03 | Install base frame cabinets | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-03-L 04 | Install finish panels | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-03-L 05 | Install cabinet doors | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-03-L 06 | Install countertop | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 652-09-03-L 07 | Install countertop edge molding | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 652-09-04 | Ship side aft Cabinet (S) | 36 | 12/09/24 | 12/13/24 | 36.0h | : | |
| 652-09-04-L | Labor | 36 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 652-09-04-L 01 | Install toe kick | 4 | 12/09/24 | 12/09/24 | 4.0h | : | |
| 652-09-04-L 02 | Install toe kick molding | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-04-L 03 | Install base frame cabinets | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-04-L 04 | Install finish panels | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-04-L 05 | Install cabinet doors | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-04-L 06 | Install countertop | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 652-09-04-L 07 | Install countertop edge molding | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 652-09-07 | TV Cabinet (Ceiling) | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 652-09-07-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 652-09-07-L 01 | Install base frame | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-07-L 02 | Install pop-down enclosure | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-07-L 03 | Install cabinet door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-07-L 04 | Install components/ install hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-08 | Wall | 72 | 12/03/24 | 12/13/24 | 72.0h | : | |
| 652-09-08-L | Labor | 72 | 12/03/24 | 12/13/24 | 1.8w | : | |
| 652-09-08-L 01 | Install shipside aft panels (Port) | 12 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 652-09-08-L 02 | Install shipside aft panels (STB) | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 652-09-08-L 03 | Install main salon fwd bulkhead | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 652-09-08-L 04 | Install main salon fwd walls | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 652-09-08-L 05 | Install stairway panels | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 652-09-08-L 06 | Install aft bhd panels | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-08-L 07 | Install aft door molding | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-08-L 08 | Install archway moldings | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-08-L 09 | Install simple Base board | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 652-09-09 | Windows | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 652-09-09-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 652-09-09-L 01 | Install window boxes (Port) | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-09-L 02 | Install window pilasters (Port) | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 652-09-09-L 03 | Install window sill molding (Port) | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-09-L 04 | Install window valances (Port) | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-09-L 05 | Install window boxes (STB) | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-09-L 06 | Install window pilasters (STB) | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-09-L 07 | Install window sill molding (STB) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-09-L 08 | Install window valances (STB) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-10 | Aft Windows | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 652-09-10-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 652-09-10-L 01 | Install fwd window boxes | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 652-09-10-L 02 | Install fwd window mullion boxes | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-10-L 03 | Install fwd window panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 652-09-10-L 04 | Install fwd window sill molding | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-10-L 05 | Install window upper valance | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-11 | Ceiling | 72 | 11/21/24 | 12/13/24 | 130.0h | : | |
| 652-09-11-L | Labor | 72 | 12/03/24 | 12/13/24 | 1.8w | : | |
| 652-09-11-L 01 | Install overhead framing | 24 | 12/03/24 | 12/05/24 | 24.0h | : | |
| 652-09-11-L 02 | Finish perimeter crown molding | 16 | 12/06/24 | 12/09/24 | 16.0h | : | |
| 652-09-11-L 03 | Fab overhead panels | 24 | 12/10/24 | 12/12/24 | 24.0h | : | |
| 652-09-11-L 04 | Finish AC grill finish panel | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 652-09-12 | Trim | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-09-12-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 652-09-12-L 01 | Connect AC ducting | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661 | Pilothouse | 368 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 661-09 | Carpentry | 368 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 661-09-01 | Room Framing | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 661-09-01-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 661-09-01-L 01 | Install cabin side framing port | 24 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 661-09-01-L 02 | Install port window boxes | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 661-09-01-L 03 | Install cabin side paneling port | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 661-09-01-L 04 | Frame out for refrigerator | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 661-09-01-L 05 | Frame out stairway walls | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 661-09-01-L 06 | Frame out stairway steps | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 661-09-02 | AC Plenums | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 661-09-02-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 661-09-02-L 01 | Fabricate AC plenum aft | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 661-09-02-L 02 | Install AC plenum aft | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 661-09-02-L 03 | Rough in AC ducting port | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-02-L 04 | Connect AC ducting to plenum | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-03 | Lower console | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 661-09-03-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 661-09-03-L 01 | Install toe kick | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-03-L 02 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-03-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-03-L 04 | Install drawer front panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-03-L 05 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-03-L 06 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-04 | Upper console | 28 | 12/10/24 | 12/13/24 | 28.0h | : | |
| 661-09-04-L | Labor | 28 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 661-09-04-L 01 | Install toe kick | 4 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 661-09-04-L 02 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-04-L 03 | Install finish panels | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-04-L 04 | Install drawer front panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-04-L 05 | Install door panels | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 661-09-04-L 06 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-05 | Chart table | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 661-09-05-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 661-09-05-L 01 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-05-L 02 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-05-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-05-L 04 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-05-L 05 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-06 | Bench seat | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 661-09-06-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 661-09-06-L 01 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-06-L 02 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-06-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-06-L 04 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-06-L 05 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-07 | Seat step | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 661-09-07-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 661-09-07-L 01 | Install base frame | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-07-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-07-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-07-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-07-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-08 | Seat Upper Storage cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 661-09-08-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 661-09-08-L 01 | Install base frame | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-08-L 02 | Install lower edge molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-08-L 03 | Install shelfs | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-08-L 04 | Install cabinets doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-08-L 05 | Install Hardware | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-09 | Wall | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 661-09-09-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 661-09-09-L 01 | Install fwd bhd storage cabinets | 12 | 12/02/24 | 12/03/24 | 12.0h | : | |
| 661-09-09-L 02 | Install fwd bhd storage cabinets doors | 4 | 12/03/24 | 12/03/24 | 4.0h | : | |
| 661-09-09-L 03 | Install fwd bulkhead AC grills | 4 | 12/04/24 | 12/04/24 | 4.0h | : | |
| 661-09-09-L 04 | Install fwd bulkhead wood panels | 16 | 12/04/24 | 12/06/24 | 16.0h | : | |
| 661-09-09-L 05 | Install STB shipside wood panels | 24 | 12/06/24 | 12/11/24 | 24.0h | : | |
| 661-09-09-L 06 | Cut in outlets/switches | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 661-09-09-L 07 | Install simple Base board | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 661-09-10 | Windows | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 661-09-10-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 661-09-10-L 01 | Install window boxes | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 661-09-10-L 02 | Install window pilasters | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-10-L 03 | Install window sill molding | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 661-09-10-L 04 | Install window valances | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-10-L 05 | Install window panel | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661-09-11 | Ceiling | 24 | 12/02/24 | 12/13/24 | 75.0h | : | |
| 661-09-11-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 661-09-11-L 01 | Fab overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 661-09-12 | Trim | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 661-09-12-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 661-09-12-L 01 | Install overhead panels | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 8 | EXTERIOR | 612 | 12/02/24 | 12/13/24 | 33.2w | : | |
| 803 | Main deck Walkway - Port | 140 | 12/03/24 | 12/13/24 | 1.7w | : | |
| 803-09 | Carpentry | 140 | 12/03/24 | 12/13/24 | 68.0h | : | |
| 803-09-01 | Entry door | 88 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 803-09-01-L | Labor | 88 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 803-09-01-L 01 | Template deck area | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 803-09-01-L 02 | Prepare teak for jointing | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 803-09-01-L 03 | Join teak panels | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 803-09-01-L 04 | Cut teak panels to templates | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 803-09-02 | Overhead | 52 | 12/03/24 | 12/13/24 | 68.0h | : | |
| 803-09-02-L | Labor | 52 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 803-09-02-L 01 | Install overhead framing | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 803-09-02-L 02 | Install overhead lighta nd speaker blocking | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 803-09-02-L 03 | Fabriacate overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 804 | Main deck Walkway - STBD | 140 | 12/03/24 | 12/13/24 | 1.7w | : | |
| 804-09 | Carpentry | 140 | 12/03/24 | 12/13/24 | 68.0h | : | |
| 804-09-01 | Entry door | 88 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 804-09-01-L | Labor | 88 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 804-09-01-L 01 | Template deck area | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 804-09-01-L 02 | Prepare teak for jointing | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 804-09-01-L 03 | Join teak panels | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 804-09-01-L 04 | Cut teak panels to templates | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 804-09-02 | Overhead | 52 | 12/03/24 | 12/13/24 | 68.0h | : | |
| 804-09-02-L | Labor | 52 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 804-09-02-L 01 | Install overhead framing | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 804-09-02-L 02 | Install overhead lighta nd speaker blocking | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 804-09-02-L 03 | Fabriacate overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 805 | Main deck - Aft | 52 | 12/03/24 | 12/13/24 | 4.0w | : | |
| 805-09 | Carpentry | 52 | 12/03/24 | 12/13/24 | 100.0h | : | |
| 805-09-01 | Overhead | 52 | 12/03/24 | 12/13/24 | 68.0h | : | |
| 805-09-01-L | Labor | 52 | 12/09/24 | 12/13/24 | 0.9w | : | |
| 805-09-01-L 01 | Install overhead framing | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 805-09-01-L 02 | Install overhead lighta nd speaker blocking | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 805-09-01-L 03 | Fabriacate overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 806 | Transom | 100 | 12/02/24 | 12/13/24 | 2.5w | : | |
| 806-09 | Carpentry | 100 | 12/02/24 | 12/13/24 | 100.0h | : | |
| 806-09-01 | Room Framing | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 806-09-01-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 806-09-01-L 01 | Install cabin side framing port | 24 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 806-09-01-L 02 | Install port window boxes | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 806-09-01-L 03 | Install cabin side paneling port | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 806-09-01-L 04 | Frame out for refrigerator | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 806-09-01-L 05 | Frame out stairway walls | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 806-09-01-L 06 | Frame out stairway steps | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-09-02 | Lower cabinet | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 806-09-02-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 806-09-02-L 01 | Install base frame cabinets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 806-09-02-L 02 | Install toe kick | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 806-09-02-L 03 | Install finish panels | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 806-09-02-L 04 | Install door panels | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 806-09-02-L 05 | Install sub-countertop for stone | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 815 | Flybridge deck | 140 | 12/02/24 | 12/13/24 | 6.3w | : | |
| 815-09 | Carpentry | 140 | 12/02/24 | 12/13/24 | 250.0h | : | |
| 815-09-02 | Overhead | 120 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 815-09-02-L | Labor | 120 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 815-09-02-L 01 | Install overhead framing | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 815-09-02-L 02 | Install overhead lighta nd speaker blocking | 40 | 12/02/24 | 12/06/24 | 40.0h | : | |
| 815-09-02-L 03 | Fabriacate overhead panels | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 815-09-04 | Cabinets | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 815-09-04-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 815-09-04-L 01 | Fabricatel cabinet doors | 16 | 12/11/24 | 12/13/24 | 16.0h | : | |
| 815-09-04-L 02 | Install cabinet doors | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 816 | Hardtop | 40 | 12/03/24 | 12/13/24 | 2.8w | : | |
| 816-09 | Carpentry | 40 | 12/03/24 | 12/13/24 | 72.0h | : | |
| 816-09-01 | Overhead | 40 | 12/03/24 | 12/13/24 | 72.0h | : | |
| 816-09-01-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 816-09-01-L 01 | Install overhead framing/blocking | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 816-09-01-L 02 | Fab/remove overhead panels | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |