DESTINATION ONE
A- Project Data
B- Drawings
C- Photographs
D- Documentation
E- Worksheets
1.2 Department Schedules
010. Plumbing
.
Department Catagory Schedules
WBSProject CategoriesLabor Hrs.Start DateFinish DatesDuration:Comments
DEPARTMENT TOTAL6,32111/08/2412/13/24.:.
3MECHANICAL SYSTEMS4,90411/08/2412/13/2467.2w:
4ENGINE ROOM56011/29/2412/13/2413.7w:
6INTERIOR68012/06/2412/13/244.2w:
8EXTERIOR17712/10/2412/13/2433.2w:
******** *********************************************************************************
.
Department Job Schedules
WBSJob DescriptionLabor Hrs.Start DateFinish DateDuration:Comments
3MECHANICAL SYSTEMS4,90411/08/2412/13/2467.2w:
301  Freshwater76011/20/2412/13/243.5w:
301-10    Plumbing76011/20/2412/13/243.5w:
301-10-01      Piping - Lower area (P)33611/25/2412/13/2415.0d:
301-10-01-L        Labor33612/02/2412/13/241.9w:
301-10-01-L 02          Install guest area deck/bhd penetrations3212/09/2412/10/2416.0h:
301-10-01-L 03          Install hanger supports/foundations4812/11/2412/13/2424.0h:
301-10-01-L 04          Rough-in guest area hot & cold main feed pipe1612/13/2412/13/248.0h:
301-10-01-L 05          Rough-in hot & cold drops to crew Fwd1612/02/2412/03/248.0h:
301-10-01-L 06          Rough-in hot & cold drops to main galley4812/11/2412/13/2424.0h:
301-10-01-L 07          Rough-in hot & cold drops to guest bath4812/03/2412/06/2424.0h:
301-10-01-L 08          Rough-in hot & cold drops to laundry1612/06/2412/09/248.0h:
301-10-01-L 09          Rough-in cold drop to blackwater tank cleanout1612/09/2412/10/248.0h:
301-10-01-L 10          Clean piping and cap all open lines812/10/2412/10/244.0h:
301-10-01-L 11          Pressure test hot & cold piping2412/11/2412/12/2412.0h:
301-10-01-L 12          Insulate hot & cold main feed pipe2412/12/2412/13/2412.0h:
301-10-01-L 13          Insulate drops to crew812/12/2412/12/244.0h:
301-10-01-L 14          Insulate drops to main galley1612/13/2412/13/248.0h:
301-10-01-L 15          Insulate drops to guest bathroom1612/13/2412/13/248.0h:
301-10-02      Piping - Main Deck6811/25/2412/13/2415.0d:
301-10-02-L        Labor6812/04/2412/13/241.5w:
301-10-02-L 01          Install main deck/bhd penetrations1212/04/2412/06/2412.0h:
301-10-02-L 02          Install hanger supports/foundations1612/06/2412/10/2416.0h:
301-10-02-L 03          Rough-in main deck hot & cold main feed pipe1212/12/2412/13/2412.0h:
301-10-02-L 04          Rough-in hot & cold drops to master stateroom412/13/2412/13/244.0h:
301-10-02-L 05          Rough-in hot & cold drops to main salon412/11/2412/11/244.0h:
301-10-02-L 06          Clean piping and cap all open lines412/11/2412/11/244.0h:
301-10-02-L 07          Pressure test hot & cold piping412/12/2412/12/244.0h:
301-10-02-L 08          Insulate hot & cold main feed pipe412/12/2412/12/244.0h:
301-10-02-L 09          Insulate drops to pilothouse812/13/2412/13/248.0h:
301-10-04      Piping - Exterior Decks9611/27/2412/13/2412.5d:
301-10-04-L        Labor9611/28/2412/13/242.4w:
301-10-04-L 01          Install exterior deck/bhd penetrations1611/28/2411/29/2416.0h:
301-10-04-L 02          Install hanger supports/foundations2412/02/2412/04/2424.0h:
301-10-04-L 03          Rough-in cold drop to fwd hose bib412/05/2412/05/244.0h:
301-10-04-L 04          Rough-in cold drop to aft hose bib412/05/2412/05/244.0h:
301-10-04-L 05          Rough-in cold drop to flybridge hose bib412/06/2412/06/244.0h:
301-10-04-L 06          Rough-in hot & cold drops to flybridge wet bar812/06/2412/09/248.0h:
301-10-04-L 07          Clean piping and cap all open lines812/09/2412/10/248.0h:
301-10-04-L 08          Pressure test hot & cold piping1212/10/2412/11/2412.0h:
301-10-04-L 09          Insulate drop to fwd hose bib412/12/2412/12/244.0h:
301-10-04-L 10          Insulate drop to aft hose bib412/12/2412/12/244.0h:
301-10-04-L 11          Insulate drop to flybridge hose bib412/13/2412/13/244.0h:
301-10-04-L 12          Insulate drops to flybridge wet bar412/13/2412/13/244.0h:
301-10-05      Piping - Machinery Spaces12011/25/2412/13/24120.0h:
301-10-05-L        Labor12011/25/2412/13/243.0w:
301-10-05-L 01          Install guest area deck/bhd penetrations1211/25/2411/26/2412.0h:
301-10-05-L 02          Install hanger supports/foundations1611/26/2411/28/2416.0h:
301-10-05-L 03          Rough-in H&C main feed pipe thru engine room1611/28/2412/02/2416.0h:
301-10-05-L 04          Rough-in cold drop to AC make up1212/02/2412/03/2412.0h:
301-10-05-L 05          Rough-in cold drop to blackwater system1212/04/2412/05/2412.0h:
301-10-05-L 06          Rough-in cold drop to seachest priming1212/05/2412/06/2412.0h:
301-10-05-L 07          Rough-in hot & cold drops to sink1612/09/2412/10/2416.0h:
301-10-05-L 08          Plumb deck fills to tanks2412/11/2412/13/2424.0h:
301-10-06      Pumps14011/20/2412/13/24140.0h:
301-10-06-L        Labor14011/20/2412/13/243.5w:
301-10-06-L 01          Install FW pump in tank1211/20/2411/21/2412.0h:
301-10-06-L 02          Install main pressure filters1611/22/2411/25/2416.0h:
301-10-06-L 03          Install supply manifold piping1211/26/2411/27/2412.0h:
301-10-06-L 04          Connect FW tank to supply manifold1611/27/2411/29/2416.0h:
301-10-06-L 05          Connect pressure filters to supply manifold1611/29/2412/03/2416.0h:
301-10-06-L 06          Connect dockside supply to manifold1612/03/2412/05/2416.0h:
301-10-06-L 07          Install pumps w/ cross over system1212/05/2412/06/2412.0h:
301-10-06-L 08          Connect system pressure filters to system piping1612/09/2412/10/2416.0h:
301-10-06-L 09          Fill & commission system2412/11/2412/13/2424.0h:
302  Graywater system60011/18/2412/13/244.0w:
302-10    Plumbing60011/18/2412/13/244.0w:
302-10-01      Piping - Lower deck (P)24011/25/2412/13/24120.0h:
302-10-01-L        Labor24011/25/2412/13/243.0w:
302-10-01-L 02          Install guest area deck/bhd penetrations2411/25/2411/27/2424.0h:
302-10-01-L 03          Install hanger supports/foundations6411/28/2412/03/2432.0h:
302-10-01-L 04          Rough in lower deck main pipe6412/04/2412/09/2432.0h:
302-10-01-L 05          Rough in drainage pipe to crew2412/05/2412/09/2424.0h:
302-10-01-L 06          Rough in drainage pipe to galley1612/10/2412/11/2416.0h:
302-10-01-L 07          Rough in drainage pipe to master bathroom1612/12/2412/13/2416.0h:
302-10-01-L 08          Rough in drainage pipe to laundry1612/10/2412/11/2416.0h:
302-10-01-L 09          Pressure test piping1612/12/2412/13/2416.0h:
302-10-02      Piping - Main deck10012/06/2412/13/2448.0h:
302-10-02-L        Labor10012/06/2412/13/241.2w:
302-10-02-L 01          Install guest area deck/bhd penetrations2412/06/2412/10/2424.0h:
302-10-02-L 02          Install hanger supports/foundations4812/11/2412/13/2424.0h:
302-10-02-L 03          Rough in drainage pipe to wetbar1212/12/2412/13/2412.0h:
302-10-02-L 04          Pressure test piping1612/12/2412/13/2416.0h:
302-10-03      Piping - Flybridge deck10012/06/2412/13/2448.0h:
302-10-03-L        Labor10012/06/2412/13/241.2w:
302-10-03-L 01          Install guest area deck/bhd penetrations2412/06/2412/10/2424.0h:
302-10-03-L 02          Install hanger supports/foundations4812/11/2412/13/2424.0h:
302-10-03-L 03          Rough in drainage pipe to wetbar1212/12/2412/13/2412.0h:
302-10-03-L 04          Pressure test piping1612/12/2412/13/2416.0h:
302-10-04      Components16011/18/2412/13/24160.0h:
302-10-04-L        Labor16011/18/2412/13/244.0w:
302-10-04-L 01          Connect garbage disposal overboard1611/18/2411/19/2416.0h:
302-10-04-L 02          Connect 'rough in' plumbing to tanks1611/20/2411/21/2416.0h:
302-10-04-L 03          Install/plumb tank suction strainer2411/22/2411/26/2424.0h:
302-10-04-L 04          Install/plumb pumps to tank 1611/27/2411/28/2416.0h:
302-10-04-L 05          Plumb maserator pump2411/29/2412/03/2424.0h:
302-10-04-L 06          Connect maserator pump to deck discharge1612/04/2412/05/2416.0h:
302-10-04-L 07          Install/plumb cross over to blackwater pump2412/06/2412/10/2424.0h:
302-10-04-L 08          Fab/Install discharge manifold 1612/11/2412/12/2416.0h:
302-10-04-L 09          Plumb pumps to overboard812/13/2412/13/248.0h:
303  Blackwater55611/13/2412/13/244.5w:
303-10    Plumbing55611/13/2412/13/244.5w:
303-10-01      Components18011/13/2412/13/24180.0h:
303-10-01-L        Labor18011/13/2412/13/244.5w:
303-10-01-L 01          Rough in tank discharge to pump2411/13/2411/18/2424.0h:
303-10-01-L 02          Connect 'rough in' plumbing to tanks2411/18/2411/21/2424.0h:
303-10-01-L 03          Install/plumb tank suction strainer3211/21/2411/27/2432.0h:
303-10-01-L 04          Install/plumb pumps to tank 2411/27/2412/02/2424.0h:
303-10-01-L 05          Install maserator pump2412/02/2412/05/2424.0h:
303-10-01-L 06          Plumb maserator pump to deck dischange1612/05/2412/09/2416.0h:
303-10-01-L 07          Connect supply to freshwater system1212/09/2412/10/2412.0h:
303-10-01-L 08          Fab/Install discharge manifold 1612/11/2412/12/2416.0h:
303-10-01-L 09          Plumb pumps to overboard812/13/2412/13/248.0h:
303-10-02      Piping - Lower Deck (P)20011/26/2412/13/24112.0h:
303-10-02-L        Labor20011/26/2412/13/242.8w:
303-10-02-L 02          Install guest area deck/bhd penetrations1611/26/2411/27/2416.0h:
303-10-02-L 03          Install hanger supports/foundations2411/28/2412/02/2424.0h:
303-10-02-L 04          Rough in lower deck guest main pipe8012/03/2412/09/2440.0h:
303-10-02-L 05          Rough in drainage pipe to Crew3212/06/2412/11/2432.0h:
303-10-02-L 06          Rough in drainage pipe to Master bath toilet1612/10/2412/11/2416.0h:
303-10-02-L 07          Rough in drainage pipe to Master bath bidet1612/12/2412/13/2416.0h:
303-10-02-L 08          Pressure test piping1612/12/2412/13/2416.0h:
303-10-03      Piping - Main Deck14411/28/2412/13/2496.0h:
303-10-03-L        Labor14411/28/2412/13/242.4w:
303-10-03-L 01          Install guest area deck/bhd penetrations1611/28/2411/29/2416.0h:
303-10-03-L 02          Install hanger supports/foundations2412/02/2412/04/2424.0h:
303-10-03-L 03          Rough in lower deck guest main pipe6412/05/2412/10/2432.0h:
303-10-03-L 04          Rough in drainage pipe to guest 1812/11/2412/11/248.0h:
303-10-03-L 05          Rough in drainage pipe to guest 2812/12/2412/12/248.0h:
303-10-03-L 06          Rough in drainage pipe to Master toilet812/13/2412/13/248.0h:
303-10-03-L 07          Pressure test piping1612/12/2412/13/2416.0h:
303-10-04      Insulation3212/10/2412/13/2432.0h:
303-10-04-L        Labor3212/10/2412/13/240.8w:
303-10-04-L 01          Insulate lower deck crew supply piping1612/10/2412/11/2416.0h:
303-10-04-L 02          Insulate lower deck guest supply piping1612/12/2412/13/2416.0h:
304  Air Conditioning1,89611/08/2412/13/245.1w:
304-10    Plumbing1,89611/08/2412/13/245.1w:
304-10-01      Components48011/08/2412/13/24204.0h:
304-10-01-L        Labor48011/08/2412/13/245.1w:
304-10-01-L 01          Install main deck/bhd pipe penetrations2412/09/2412/10/2412.0h:
304-10-01-L 02          Install pipe hanger supports/foundations4812/11/2412/13/2424.0h:
304-10-01-L 03          Rough-in engine rm. chill water pipe4811/08/2411/13/2424.0h:
304-10-01-L 04          Rough-in chiller base condensate drain1611/13/2411/14/248.0h:
304-10-01-L 05          Pressure test chill water system piping2411/14/2411/15/2412.0h:
304-10-01-L 06          Install chilled water pumps2411/18/2411/19/2412.0h:
304-10-01-L 07          Connect chill water pipe to chiller unit3211/19/2411/21/2416.0h:
304-10-01-L 08          Connect system to circulating water pumps2411/21/2411/22/2412.0h:
304-10-01-L 09          Insulate all engine rm. chill water pipe4811/25/2411/27/2424.0h:
304-10-01-L 10          Fabricate raw water supply manifold 3211/28/2411/29/2416.0h:
304-10-01-L 11          Fabricate raw water discharge manifold 2412/02/2412/03/2412.0h:
304-10-01-L 12          Install raw water pumps2412/03/2412/04/2412.0h:
304-10-01-L 13          Install/connect raw water supply manifold 3212/05/2412/06/2416.0h:
304-10-01-L 14          Install/connect raw water discharge manifold 2412/09/2412/10/2412.0h:
304-10-01-L 15          Install/plumb raw water pumps2412/10/2412/11/2412.0h:
304-10-01-L 16          Connect freshwater make up system1612/12/2412/12/248.0h:
304-10-01-L 17          Plumb raw water pumps to overboard1612/13/2412/13/248.0h:
304-10-02      Piping - Lower area60011/12/2412/13/2423.3d:
304-10-03      Piping - Main Deck67211/18/2412/13/2420.0d:
304-10-03-L        Labor67211/18/2412/13/244.0w:
304-10-03-L 01          Install main deck/bhd penetrations7212/09/2412/11/2424.0h:
304-10-03-L 02          Install hanger supports/foundations4812/12/2412/13/2416.0h:
304-10-03-L 03          Rough-in main deck chill water main feed pipe24011/18/2411/29/2480.0h:
304-10-03-L 04          Rough-in chill water drops to master stateroom7212/02/2412/04/2424.0h:
304-10-03-L 05          Rough-in chill water drops to main salon7212/05/2412/09/2424.0h:
304-10-03-L 06          Clean piping and cap all open lines4812/10/2412/11/2416.0h:
304-10-03-L 07          Pressure test chill water piping4812/12/2412/13/2416.0h:
304-10-03-L 08          Rough-in condensate drain to main salon7212/11/2412/13/2424.0h:
304-10-04      Engine room14411/12/2412/13/2423.3d:
306  Deck Drainage System35611/20/2412/13/243.6w:
306-10    Plumbing35611/20/2412/13/24144.0h:
306-10-01      Pipe Penetrations4812/06/2412/13/2448.0h:
306-10-01-L        Labor4812/06/2412/13/2448.0h:
306-10-01-L 02          Main deck 1212/06/2412/09/2412.0h:
306-10-01-L 03          below FB deck1212/09/2412/10/2412.0h:
306-10-01-L 04          engine room1212/11/2412/12/2412.0h:
306-10-01-L 05          pump hold1212/12/2412/13/2412.0h:
306-10-02      Equipment Mounting2012/11/2412/13/2420.0h:
306-10-02-L        Labor2012/11/2412/13/2420.0h:
306-10-02-L 01          Install Fwd Main deck drain wastes412/11/2412/11/244.0h:
306-10-02-L 02          Install Port Main deck drain wastes412/12/2412/12/244.0h:
306-10-02-L 03          Install STB Main deck drain wastes412/12/2412/12/244.0h:
306-10-02-L 04          Install Aft Main deck drain wastes412/13/2412/13/244.0h:
306-10-02-L 05          Install Flybridge deck drain wastes412/13/2412/13/244.0h:
306-10-03      Deck Drain Plumbing - P14411/20/2412/13/24144.0h:
306-10-03-L        Labor14411/20/2412/13/24144.0h:
306-10-03-L 01          Install Fwd Main deck drain pipe811/20/2411/20/248.0h:
306-10-03-L 02          Install Port Main deck drain pipe811/21/2411/21/248.0h:
306-10-03-L 03          Install STB Main deck drain pipe811/22/2411/22/248.0h:
306-10-03-L 04          Install Aft Main deck drain pipe811/25/2411/25/248.0h:
306-10-03-L 05          Install Flybridge deck drain pipe811/26/2411/26/248.0h:
306-10-03-L 06          Connect Fwd Main deck drain pipe811/27/2411/27/248.0h:
306-10-03-L 07          Connect Port Main deck drain pipe811/28/2411/28/248.0h:
306-10-03-L 08          Connect STB Main deck drain pipe811/29/2411/29/248.0h:
306-10-03-L 09          Connect Aft Main deck drain pipe812/02/2412/02/248.0h:
306-10-03-L 10          Connect Flybridge deck drain pipe812/03/2412/03/248.0h:
306-10-03-L 11          Install Fwd Main hatch drain pipe812/04/2412/04/248.0h:
306-10-03-L 12          Install Port Main hatch drain pipe812/05/2412/05/248.0h:
306-10-03-L 13          Install STB Main hatch drain pipe812/06/2412/06/248.0h:
306-10-03-L 14          Install Aft Main hatch drain pipe812/09/2412/09/248.0h:
306-10-03-L 15          Connect Fwd Main hatch drain pipe812/10/2412/10/248.0h:
306-10-03-L 16          Connect Port Main hatch drain pipe812/11/2412/11/248.0h:
306-10-03-L 17          Connect STB Main hatch drain pipe812/12/2412/12/248.0h:
306-10-03-L 18          Connect Aft Main hatch drain pipe812/13/2412/13/248.0h:
306-10-04      Deck Drain Plumbing - S14411/20/2412/13/24144.0h:
306-10-04-L        Labor14411/20/2412/13/24144.0h:
306-10-04-L 01          Install Fwd Main deck drain pipe811/20/2411/20/248.0h:
306-10-04-L 02          Install Port Main deck drain pipe811/21/2411/21/248.0h:
306-10-04-L 03          Install STB Main deck drain pipe811/22/2411/22/248.0h:
306-10-04-L 04          Install Aft Main deck drain pipe811/25/2411/25/248.0h:
306-10-04-L 05          Install Flybridge deck drain pipe811/26/2411/26/248.0h:
306-10-04-L 06          Connect Fwd Main deck drain pipe811/27/2411/27/248.0h:
306-10-04-L 07          Connect Port Main deck drain pipe811/28/2411/28/248.0h:
306-10-04-L 08          Connect STB Main deck drain pipe811/29/2411/29/248.0h:
306-10-04-L 09          Connect Aft Main deck drain pipe812/02/2412/02/248.0h:
306-10-04-L 10          Connect Flybridge deck drain pipe812/03/2412/03/248.0h:
306-10-04-L 11          Install Fwd Main hatch drain pipe812/04/2412/04/248.0h:
306-10-04-L 12          Install Port Main hatch drain pipe812/05/2412/05/248.0h:
306-10-04-L 13          Install STB Main hatch drain pipe812/06/2412/06/248.0h:
306-10-04-L 14          Install Aft Main hatch drain pipe812/09/2412/09/248.0h:
306-10-04-L 15          Connect Fwd Main hatch drain pipe812/10/2412/10/248.0h:
306-10-04-L 16          Connect Port Main hatch drain pipe812/11/2412/11/248.0h:
306-10-04-L 17          Connect STB Main hatch drain pipe812/12/2412/12/248.0h:
306-10-04-L 18          Connect Aft Main hatch drain pipe812/13/2412/13/248.0h:
312  Bilge system56011/18/2412/13/244.0w:
312-10    Plumbing56011/18/2412/13/244.0w:
312-10-01      Rough-in DC Piping - P16011/18/2412/13/24160.0h:
312-10-01-L        Labor16011/18/2412/13/244.0w:
312-10-01-L 01          Rough in DC pipe fwd3211/18/2411/21/2432.0h:
312-10-01-L 02          Rough in DC pipe mid ship3211/22/2411/27/2432.0h:
312-10-01-L 03          Rough in DC pipe fwd eng. room3211/28/2412/03/2432.0h:
312-10-01-L 04          Rough in DC pipe aft eng. room3212/04/2412/09/2432.0h:
312-10-01-L 05          Rough in DC pipe lazzerette3212/10/2412/13/2432.0h:
312-10-02      Install/Connect DC piping to pump - P8012/02/2412/13/2480.0h:
312-10-02-L        Labor8012/02/2412/13/242.0w:
312-10-02-L 01          Install/connect DC pump fwd1612/02/2412/03/2416.0h:
312-10-02-L 02          Install/connect DC pump mid ship1612/04/2412/05/2416.0h:
312-10-02-L 03          Install/connect DC pump fwd eng. room1612/06/2412/09/2416.0h:
312-10-02-L 04          Install/connect DC pump aft eng. room1612/10/2412/11/2416.0h:
312-10-02-L 05          Install/connect DC pump lazzerette1612/12/2412/13/2416.0h:
312-10-03      Connect to DC piping Overboard - P4012/05/2412/13/2450.0h:
312-10-03-L        Labor4012/09/2412/13/241.0w:
312-10-03-L 01          Connect DC pump to overboard fwd812/09/2412/09/248.0h:
312-10-03-L 02          Connect DC pump to overboard mid ship812/10/2412/10/248.0h:
312-10-03-L 03          Connect DC pump to overboard fwd eng. room812/11/2412/11/248.0h:
312-10-03-L 04          Connect DC pump to overboard aft eng. room812/12/2412/12/248.0h:
312-10-03-L 05          Connect DC pump to overboard lazzerette812/13/2412/13/248.0h:
312-10-04      Rough-in DC Piping - S16011/18/2412/13/24160.0h:
312-10-04-L        Labor16011/18/2412/13/244.0w:
312-10-04-L 01          Rough in DC pipe fwd3211/18/2411/21/2432.0h:
312-10-04-L 02          Rough in DC pipe mid ship3211/22/2411/27/2432.0h:
312-10-04-L 03          Rough in DC pipe fwd eng. room3211/28/2412/03/2432.0h:
312-10-04-L 04          Rough in DC pipe aft eng. room3212/04/2412/09/2432.0h:
312-10-04-L 05          Rough in DC pipe lazzerette3212/10/2412/13/2432.0h:
312-10-05      Install/Connect DC piping to pump - S8012/02/2412/13/2480.0h:
312-10-05-L        Labor8012/02/2412/13/242.0w:
312-10-05-L 01          Install/connect DC pump fwd1612/02/2412/03/2416.0h:
312-10-05-L 02          Install/connect DC pump mid ship1612/04/2412/05/2416.0h:
312-10-05-L 03          Install/connect DC pump fwd eng. room1612/06/2412/09/2416.0h:
312-10-05-L 04          Install/connect DC pump aft eng. room1612/10/2412/11/2416.0h:
312-10-05-L 05          Install/connect DC pump lazzerette1612/12/2412/13/2416.0h:
312-10-06      Connect to DC piping Overboard4012/03/2412/13/2472.0h:
312-10-06-L        Labor4012/09/2412/13/241.0w:
312-10-06-L 01          Connect DC pump to overboard fwd812/09/2412/09/248.0h:
312-10-06-L 02          Connect DC pump to overboard mid ship812/10/2412/10/248.0h:
312-10-06-L 03          Connect DC pump to overboard fwd eng. room812/11/2412/11/248.0h:
312-10-06-L 04          Connect DC pump to overboard aft eng. room812/12/2412/12/248.0h:
312-10-06-L 05          Connect DC pump to overboard lazzerette812/13/2412/13/248.0h:
323  Anchor2412/11/2412/13/2410.0w:
323-10    Plumbing2412/11/2412/13/2424.0h:
323-10-01      Connect2412/11/2412/13/2424.0h:
323-10-01-L        Labor2412/11/2412/13/240.6w:
323-10-01-L 01          Connect wash down system2412/11/2412/13/2424.0h:
330  Watermakers15212/04/2412/13/241.5w:
330-10    Plumbing15212/04/2412/13/241.5w:
330-10-01      Rough-in piping4012/04/2412/13/2460.0h:
330-10-01-L        Labor4012/09/2412/13/241.0w:
330-10-01-L 01          Rough-in raw water supply from seachest1612/09/2412/10/2416.0h:
330-10-01-L 02          Rough-in F.W supply to tank1212/11/2412/12/2412.0h:
330-10-01-L 03          Rough-in overboard dump line1212/12/2412/13/2412.0h:
330-10-02      Install5612/05/2412/13/2456.0h:
330-10-02-L        Labor5612/05/2412/13/241.4w:
330-10-02-L 01          Install L.P pump1612/05/2412/06/2416.0h:
330-10-02-L 02          Install H.P pump1612/09/2412/10/2416.0h:
330-10-02-L 03          Install filters1212/11/2412/12/2412.0h:
330-10-02-L 04          Install watermaker membranes1212/12/2412/13/2412.0h:
330-10-03      Connect5612/05/2412/13/2456.0h:
330-10-03-L        Labor5612/05/2412/13/241.4w:
330-10-03-L 01          Connect back flush to FW system1612/05/2412/06/2416.0h:
330-10-03-L 02          Connect dump line to overboard discharge1612/09/2412/10/2416.0h:
330-10-03-L 03          Connect L.P pump812/11/2412/11/248.0h:
330-10-03-L 04          Connect H.P pump812/12/2412/12/248.0h:
330-10-03-L 05          Connect membranes812/13/2412/13/248.0h:
4ENGINE ROOM56011/29/2412/13/2413.7w:
405  Main engine Installation8012/12/2412/13/2413.7w:
405-04    Metal Fabrication8012/12/2412/13/2416.0h:
405-04-01      Brackets/Foundations4012/12/2412/13/2416.0h:
405-04-01-L        Labor4012/12/2412/13/240.4w:
405-04-01-L 01          Fabricate exhaust gases overboard 812/12/2412/12/248.0h:
405-04-01-L 02          Fabricate exhaust water overboard812/13/2412/13/248.0h:
405-04-01-L 03          Install exhaust water overboard1212/12/2412/13/2412.0h:
405-04-01-L 04          Install exhaust water overboard 1212/12/2412/13/2412.0h:
405-04-02      Fabrication Piping4012/12/2412/13/2416.0h:
405-04-02-L        Labor4012/12/2412/13/240.4w:
405-04-02-L 01          Fabricate exhaust gases overboard 812/12/2412/12/248.0h:
405-04-02-L 02          Fabricate exhaust water overboard812/13/2412/13/248.0h:
405-04-02-L 03          Install exhaust water overboard 1212/12/2412/13/2412.0h:
405-04-02-L 04          Install exhaust water overboard 1212/12/2412/13/2412.0h:
410  Generators8012/12/2412/13/242.4w:
410-04    Metal Fabrication8012/12/2412/13/2416.0h:
410-04-01      Brackets/Foundations4012/12/2412/13/2416.0h:
410-04-01-L        Labor4012/12/2412/13/240.4w:
410-04-01-L 01          Fabricate exhaust gases overboard 812/12/2412/12/248.0h:
410-04-01-L 02          Fabricate exhaust water overboard812/13/2412/13/248.0h:
410-04-01-L 03          Install exhaust water overboard1212/12/2412/13/2412.0h:
410-04-01-L 04          Install exhaust water overboard 1212/12/2412/13/2412.0h:
410-04-02      Fabrication Piping4012/12/2412/13/2416.0h:
410-04-02-L        Labor4012/12/2412/13/240.4w:
410-04-02-L 01          Fabricate exhaust gases overboard 812/12/2412/12/248.0h:
410-04-02-L 02          Fabricate exhaust water overboard812/13/2412/13/248.0h:
410-04-02-L 03          Install exhaust water overboard 1212/12/2412/13/2412.0h:
410-04-02-L 04          Install exhaust water overboard 1212/12/2412/13/2412.0h:
415  Sea chests8412/10/2412/13/241.0w:
415-04    Metal Fabrication8412/10/2412/13/241.0w:
415-04-01      Main engines Install/Connect 4212/12/2412/13/2438.0h:
415-04-01-L        Labor4212/12/2412/13/240.4w:
415-04-01-L 01          Install intake standpipe (P)612/13/2412/13/246.0h:
415-04-01-L 02          Install seachest (P)1212/12/2412/13/2412.0h:
415-04-01-L 03          Install supply/crossover pipe1612/12/2412/13/2416.0h:
415-04-01-L 04          Install access cover/strainer (S)812/13/2412/13/248.0h:
415-04-02      Aux Install/Connect4212/10/2412/13/2439.0h:
415-04-02-L        Labor4212/10/2412/13/240.7w:
415-04-02-L 01          Install intake standpipe (S)612/13/2412/13/246.0h:
415-04-02-L 02          Install seachest (S)1212/10/2412/11/2412.0h:
415-04-02-L 03          Install supply/crossover pipe1612/12/2412/13/2416.0h:
415-04-02-L 04          Install access cover/strainer (S)812/13/2412/13/248.0h:
416  Raw water cooling systems22812/04/2412/13/241.6w:
416-04    Metal Fabrication22812/04/2412/13/241.6w:
416-04-02      Brackets - S8012/09/2412/13/2440.0h:
416-04-02-L        Labor8012/09/2412/13/241.0w:
416-04-02-L 01          Fabricate pipe hanger foundations2412/09/2412/11/2424.0h:
416-04-02-L 02          Fabricate pipe hangers1612/12/2412/13/2416.0h:
416-04-02-L 03          Machine standpipe flanges4012/09/2412/13/2440.0h:
416-04-03      Rough-in Piping10412/04/2412/13/2464.0h:
416-04-03-L        Labor10412/04/2412/13/241.6w:
416-04-03-L 01          Rough in Main Engine supply (P)1612/12/2412/13/2416.0h:
416-04-03-L 02          Rough in generator supply (S)1212/09/2412/10/2412.0h:
416-04-03-L 03          Rough in AC chiller supply (1)1212/12/2412/13/2412.0h:
416-04-03-L 04          Rough in fire pump supply3212/04/2412/09/2432.0h:
416-04-03-L 05          Rough in hydraulic cooling supply1612/10/2412/11/2416.0h:
416-04-03-L 06          Rough in watermaker supply1612/12/2412/13/2416.0h:
416-04-04      Install Piping4412/12/2412/13/2416.0h:
416-04-04-L        Labor4412/12/2412/13/240.4w:
416-04-04-L 01          Install all shut off valve to seachest crossover812/12/2412/12/248.0h:
416-04-04-L 02          Install/Connect Main engine supply to crossover (P)812/13/2412/13/248.0h:
416-04-04-L 03          Install/connect generator supply to crossover (S)812/13/2412/13/248.0h:
416-04-04-L 04          Install/connect AC supply to crossover (2)812/13/2412/13/248.0h:
416-04-04-L 05          Install/connect watermaker supply to crossover 1212/12/2412/13/2412.0h:
420  Lube oil8811/29/2412/13/242.2w:
420-04    Metal Fabrication8811/29/2412/13/2488.0h:
420-04-01      Components - P8811/29/2412/13/2488.0h:
420-04-01-L        Labor8811/29/2412/13/242.2w:
420-04-01-L 01          Fabricate transfer manifold2411/29/2412/03/2424.0h:
420-04-01-L 02          Fabricate Clean oil tank3212/04/2412/09/2432.0h:
420-04-01-L 03          Fabricate Dirty oil tank3212/10/2412/13/2432.0h:
6INTERIOR68012/06/2412/13/244.2w:
602  Guest Stateroom 11612/12/2412/13/242.0w:
602-10    Plumbing1612/12/2412/13/240.4w:
602-10-01      Air Conditioning1612/12/2412/13/2416.0h:
602-10-01-L        Labor1612/12/2412/13/240.4w:
602-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
602-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
602-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
603  Guest Bathroom 12812/13/2412/13/242.4w:
603-10    Plumbing2812/13/2412/13/240.2w:
603-10-01      Sink812/13/2412/13/248.0h:
603-10-01-L        Labor812/13/2412/13/240.2w:
603-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
603-10-01-L 02          Install faucet212/13/2412/13/242.0h:
603-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
603-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
603-10-02      Shower812/13/2412/13/248.0h:
603-10-02-L        Labor812/13/2412/13/240.2w:
603-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
603-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
603-10-03      Toilet812/13/2412/13/248.0h:
603-10-03-L        Labor812/13/2412/13/240.2w:
603-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
603-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
603-10-04      Finish trims412/13/2412/13/244.0h:
603-10-04-L        Labor412/13/2412/13/240.1w:
603-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
604  Guest Stateroom 21612/12/2412/13/242.2w:
604-10    Plumbing1612/12/2412/13/240.4w:
604-10-01      Air Conditioning1612/12/2412/13/2416.0h:
604-10-01-L        Labor1612/12/2412/13/240.4w:
604-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
604-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
604-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
605  Guest Bathroom 22812/13/2412/13/242.4w:
605-10    Plumbing2812/13/2412/13/240.2w:
605-10-01      Sink812/13/2412/13/248.0h:
605-10-01-L        Labor812/13/2412/13/240.2w:
605-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
605-10-01-L 02          Install faucet212/13/2412/13/242.0h:
605-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
605-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
605-10-02      Shower812/13/2412/13/248.0h:
605-10-02-L        Labor812/13/2412/13/240.2w:
605-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
605-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
605-10-03      Toilet812/13/2412/13/248.0h:
605-10-03-L        Labor812/13/2412/13/240.2w:
605-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
605-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
605-10-04      Finish trims412/13/2412/13/244.0h:
605-10-04-L        Labor412/13/2412/13/240.1w:
605-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
606  Guest Stateroom 31612/12/2412/13/242.9w:
606-10    Plumbing1612/12/2412/13/240.4w:
606-10-01      Air Conditioning1612/12/2412/13/2416.0h:
606-10-01-L        Labor1612/12/2412/13/240.4w:
606-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
606-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
606-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
607  Guest Bathroom 32812/13/2412/13/242.4w:
607-10    Plumbing2812/13/2412/13/240.2w:
607-10-01      Sink812/13/2412/13/248.0h:
607-10-01-L        Labor812/13/2412/13/240.2w:
607-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
607-10-01-L 02          Install faucet212/13/2412/13/242.0h:
607-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
607-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
607-10-02      Shower812/13/2412/13/248.0h:
607-10-02-L        Labor812/13/2412/13/240.2w:
607-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
607-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
607-10-03      Toilet812/13/2412/13/248.0h:
607-10-03-L        Labor812/13/2412/13/240.2w:
607-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
607-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
607-10-04      Finish trims412/13/2412/13/244.0h:
607-10-04-L        Labor412/13/2412/13/240.1w:
607-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
608  Guest Stateroom 41612/12/2412/13/242.9w:
608-10    Plumbing1612/12/2412/13/240.4w:
608-10-01      Air Conditioning1612/12/2412/13/2416.0h:
608-10-01-L        Labor1612/12/2412/13/240.4w:
608-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
608-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
608-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
609  Guest Bathroom 42812/13/2412/13/242.4w:
609-10    Plumbing2812/13/2412/13/240.2w:
609-10-01      Sink812/13/2412/13/248.0h:
609-10-01-L        Labor812/13/2412/13/240.2w:
609-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
609-10-01-L 02          Install faucet212/13/2412/13/242.0h:
609-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
609-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
609-10-02      Shower812/13/2412/13/248.0h:
609-10-02-L        Labor812/13/2412/13/240.2w:
609-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
609-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
609-10-03      Toilet812/13/2412/13/248.0h:
609-10-03-L        Labor812/13/2412/13/240.2w:
609-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
609-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
609-10-04      Finish trims412/13/2412/13/244.0h:
609-10-04-L        Labor412/13/2412/13/240.1w:
609-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
615  Lower Guest Foyer - STBD1212/12/2412/13/241.3w:
615-10    Plumbing1212/12/2412/13/2412.0h:
615-10-01      Appliances1212/12/2412/13/2412.0h:
615-10-01-M        Labor1212/12/2412/13/240.3w:
615-10-01-M 01          Install supply to washer812/12/2412/13/248.0h:
615-10-01-M 02          Connect washer supply412/13/2412/13/244.0h:
620  Captain's cabin 11612/12/2412/13/242.9w:
620-10    Plumbing1612/12/2412/13/240.4w:
620-10-01      Air Conditioning1612/12/2412/13/2416.0h:
620-10-01-L        Labor1612/12/2412/13/240.4w:
620-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
620-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
620-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
621  Captain's Bathroom2812/13/2412/13/241.9w:
621-10    Plumbing2812/13/2412/13/240.2w:
621-10-01      Sink812/13/2412/13/248.0h:
621-10-01-L        Labor812/13/2412/13/240.2w:
621-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
621-10-01-L 02          Install faucet212/13/2412/13/242.0h:
621-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
621-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
621-10-02      Shower812/13/2412/13/248.0h:
621-10-02-L        Labor812/13/2412/13/240.2w:
621-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
621-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
621-10-03      Toilet812/13/2412/13/248.0h:
621-10-03-L        Labor812/13/2412/13/240.2w:
621-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
621-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
621-10-04      Finish trims412/13/2412/13/244.0h:
621-10-04-L        Labor412/13/2412/13/240.1w:
621-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
622  Crew cabin 11612/12/2412/13/242.9w:
622-10    Plumbing1612/12/2412/13/240.4w:
622-10-01      Air Conditioning1612/12/2412/13/2416.0h:
622-10-01-L        Labor1612/12/2412/13/240.4w:
622-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
622-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
622-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
623  Crew Bathroom 2812/13/2412/13/241.9w:
623-10    Plumbing2812/13/2412/13/240.2w:
623-10-01      Sink812/13/2412/13/248.0h:
623-10-01-L        Labor812/13/2412/13/240.2w:
623-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
623-10-01-L 02          Install faucet212/13/2412/13/242.0h:
623-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
623-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
623-10-02      Shower812/13/2412/13/248.0h:
623-10-02-L        Labor812/13/2412/13/240.2w:
623-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
623-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
623-10-03      Toilet812/13/2412/13/248.0h:
623-10-03-L        Labor812/13/2412/13/240.2w:
623-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
623-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
623-10-04      Finish trims412/13/2412/13/244.0h:
623-10-04-L        Labor412/13/2412/13/240.1w:
623-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
624  Crew cabin 21612/12/2412/13/242.9w:
624-10    Plumbing1612/12/2412/13/240.4w:
624-10-01      Air Conditioning1612/12/2412/13/2416.0h:
624-10-01-L        Labor1612/12/2412/13/240.4w:
624-10-01-L 01          Install AC fan coils812/12/2412/12/248.0h:
624-10-01-L 02          Connect AC supply/return412/13/2412/13/244.0h:
624-10-01-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
625  Crew Bathroom 22812/13/2412/13/241.9w:
625-10    Plumbing2812/13/2412/13/240.2w:
625-10-01      Sink812/13/2412/13/248.0h:
625-10-01-L        Labor812/13/2412/13/240.2w:
625-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
625-10-01-L 02          Install faucet212/13/2412/13/242.0h:
625-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
625-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
625-10-02      Shower812/13/2412/13/248.0h:
625-10-02-L        Labor812/13/2412/13/240.2w:
625-10-02-L 01          Connect shower drain412/13/2412/13/244.0h:
625-10-02-L 02          Install/connect shower mixer412/13/2412/13/244.0h:
625-10-03      Toilet812/13/2412/13/248.0h:
625-10-03-L        Labor812/13/2412/13/240.2w:
625-10-03-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
625-10-03-L 02          Install/plumb toilet412/13/2412/13/244.0h:
625-10-04      Finish trims412/13/2412/13/244.0h:
625-10-04-L        Labor412/13/2412/13/240.1w:
625-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
635  Laundry1212/12/2412/13/241.3w:
635-10    Plumbing1212/12/2412/13/2412.0h:
635-10-01      Appliances1212/12/2412/13/2412.0h:
635-10-01-L        Labor1212/12/2412/13/240.3w:
635-10-01-L 01          Install supply to washer812/12/2412/13/248.0h:
635-10-01-L 02          Connect washer supply412/13/2412/13/244.0h:
636  Crew Lounge area8412/06/2412/13/242.0w:
636-10    Plumbing8412/06/2412/13/241.2w:
636-10-01      Sink2412/11/2412/13/2424.0h:
636-10-01-L        Labor2412/11/2412/13/240.6w:
636-10-01-L 01          Install freshwater angle stops412/11/2412/11/244.0h:
636-10-01-L 02          Install faucets412/11/2412/11/244.0h:
636-10-01-L 03          Connect faucet to angle stops412/12/2412/12/244.0h:
636-10-01-L 04          Connect sink drains412/12/2412/12/244.0h:
636-10-01-L 05          Install/connect garbage disposal812/13/2412/13/248.0h:
636-10-02      Air Conditioning4812/06/2412/13/2448.0h:
636-10-02-L        Labor4812/06/2412/13/241.2w:
636-10-02-L 01          Install AC fan coils2412/06/2412/10/2424.0h:
636-10-02-L 02          Connect AC supply/return1212/11/2412/12/2412.0h:
636-10-02-L 03          Connect AC condensate drain1212/12/2412/13/2412.0h:
636-10-03      Appliances1212/12/2412/13/2412.0h:
636-10-03-L        Labor1212/12/2412/13/240.3w:
636-10-03-L 01          Install supply to icemaker812/12/2412/13/248.0h:
636-10-03-L 02          Connect ice maker supply412/13/2412/13/244.0h:
641  Owners Stateroom3212/10/2412/13/243.2w:
641-10    Plumbing3212/10/2412/13/240.8w:
641-10-01      Air Conditioning3212/10/2412/13/2432.0h:
641-10-01-L        Labor3212/10/2412/13/240.8w:
641-10-01-L 01          Install AC fan coils1612/10/2412/11/2416.0h:
641-10-01-L 02          Connect AC supply/return812/12/2412/12/248.0h:
641-10-01-L 03          Connect AC condensate drain812/13/2412/13/248.0h:
643  Owners Bathroom4812/12/2412/13/243.8w:
643-10    Plumbing4812/12/2412/13/240.4w:
643-10-01      Sink 1212/12/2412/13/2412.0h:
643-10-01-L        Labor1212/12/2412/13/240.3w:
643-10-01-L 01          Install freshwater angle stops412/12/2412/12/244.0h:
643-10-01-L 02          Install faucet412/13/2412/13/244.0h:
643-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
643-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
643-10-02      Shower1612/12/2412/13/2416.0h:
643-10-02-L        Labor1612/12/2412/13/240.4w:
643-10-02-L 01          Connect shower drain812/12/2412/12/248.0h:
643-10-02-L 02          Install/connect shower mixer812/13/2412/13/248.0h:
643-10-03      Toilet1612/12/2412/13/2416.0h:
643-10-03-L        Labor1612/12/2412/13/240.4w:
643-10-03-L 01          Install/connect toilet soleniod812/12/2412/12/248.0h:
643-10-03-L 02          Install/plumb toilet812/13/2412/13/248.0h:
643-10-04      Finish trims412/13/2412/13/244.0h:
643-10-04-L        Labor412/13/2412/13/240.1w:
643-10-04-L 01          Install all finish trims412/13/2412/13/244.0h:
645  Galley9612/06/2412/13/242.0w:
645-10    Plumbing9612/06/2412/13/241.2w:
645-10-01      Sink2412/11/2412/13/2424.0h:
645-10-01-L        Labor2412/11/2412/13/240.6w:
645-10-01-L 01          Install freshwater angle stops412/11/2412/11/244.0h:
645-10-01-L 02          Install faucets412/11/2412/11/244.0h:
645-10-01-L 03          Connect faucet to angle stops412/12/2412/12/244.0h:
645-10-01-L 04          Connect sink drains412/12/2412/12/244.0h:
645-10-01-L 05          Install/connect garbage disposal812/13/2412/13/248.0h:
645-10-02      Air Conditioning4812/06/2412/13/2448.0h:
645-10-02-L        Labor4812/06/2412/13/241.2w:
645-10-02-L 01          Install AC fan coils2412/06/2412/10/2424.0h:
645-10-02-L 02          Connect AC supply/return1212/11/2412/12/2412.0h:
645-10-02-L 03          Connect AC condensate drain1212/12/2412/13/2412.0h:
645-10-03      Appliances2412/11/2412/13/2424.0h:
645-10-03-L        Labor2412/11/2412/13/240.6w:
645-10-03-L 01          Install supply to icemaker812/11/2412/11/248.0h:
645-10-03-L 02          Connect ice maker supply412/12/2412/12/244.0h:
645-10-03-L 03          Install supply to washer812/12/2412/13/248.0h:
645-10-03-L 04          Connect washer supply412/13/2412/13/244.0h:
647  Powder room2012/13/2412/13/241.9w:
647-10    Plumbing2012/13/2412/13/240.2w:
647-10-01      Sink812/13/2412/13/248.0h:
647-10-01-L        Labor812/13/2412/13/240.2w:
647-10-01-L 01          Install freshwater angle stops212/13/2412/13/242.0h:
647-10-01-L 02          Install faucet212/13/2412/13/242.0h:
647-10-01-L 03          Connect faucet to angle stops212/13/2412/13/242.0h:
647-10-01-L 04          Connect sink drain212/13/2412/13/242.0h:
647-10-02      Toilet812/13/2412/13/248.0h:
647-10-02-L        Labor812/13/2412/13/240.2w:
647-10-02-L 01          Install/connect toilet soleniod412/13/2412/13/244.0h:
647-10-02-L 02          Install/plumb toilet412/13/2412/13/244.0h:
647-10-03      Finish trims412/13/2412/13/244.0h:
647-10-03-L        Labor412/13/2412/13/240.1w:
647-10-03-L 01          Install all finish trims412/13/2412/13/244.0h:
652  Main Salon2012/11/2412/13/243.3w:
652-10    Plumbing2012/11/2412/13/240.5w:
652-10-02      Air Condtioning2012/11/2412/13/2420.0h:
652-10-02-L        Labor2012/11/2412/13/240.5w:
652-10-02-L 01          Install AC fan coils1212/11/2412/12/2412.0h:
652-10-02-L 02          Connect AC supply/return412/13/2412/13/244.0h:
652-10-02-L 03          Connect AC condensate drain412/13/2412/13/244.0h:
661  Pilothouse4812/06/2412/13/242.0w:
661-10    Plumbing4812/06/2412/13/241.2w:
661-10-01      Air Conditioning4812/06/2412/13/2448.0h:
661-10-01-L        Labor4812/06/2412/13/241.2w:
661-10-01-L 01          Install AC fan coils2412/06/2412/10/2424.0h:
661-10-01-L 02          Connect AC supply/return1212/11/2412/12/2412.0h:
661-10-01-L 03          Connect AC condensate drain1212/12/2412/13/2412.0h:
8EXTERIOR17712/10/2412/13/2433.2w:
802  Main deck - FWD6912/10/2412/13/244.6w:
802-10    Plumbing6912/10/2412/13/240.7w:
802-10-01      Install/Connect6912/10/2412/13/2429.0h:
802-10-01-L        Labor6912/10/2412/13/240.7w:
802-10-01-L 01          Connect drains2112/10/2412/12/2421.0h:
802-10-01-L 02          Connect deck fill812/13/2412/13/248.0h:
802-10-01-L 03          Wash down spigots812/13/2412/13/248.0h:
802-10-01-L 04          Plumb jacuzzi tub supply1612/12/2412/13/2416.0h:
802-10-01-L 05          Plumb jacuzzi tub waste1612/12/2412/13/2416.0h:
803  Main deck Walkway - Port2412/11/2412/13/241.7w:
803-10    Plumbing2412/11/2412/13/2424.0h:
803-10-01      Install/Connect2412/11/2412/13/2424.0h:
803-10-01-L        Labor2412/11/2412/13/240.6w:
803-10-01-L 01          Connect drain drains1612/11/2412/12/2416.0h:
803-10-01-L 02          Connect deck fill812/13/2412/13/248.0h:
804  Main deck Walkway - STBD2412/11/2412/13/241.7w:
804-10    Plumbing2412/11/2412/13/2424.0h:
804-10-01      Install/Connect2412/11/2412/13/2424.0h:
804-10-01-L        Labor2412/11/2412/13/240.6w:
804-10-01-L 01          Connect drain drains1612/11/2412/12/2416.0h:
804-10-01-L 02          Connect deck fill812/13/2412/13/248.0h:
805  Main deck - Aft2012/12/2412/13/244.0w:
805-10    Plumbing2012/12/2412/13/2412.0h:
805-10-01      Install/Connect2012/12/2412/13/2412.0h:
805-10-01-L        Labor2012/12/2412/13/240.3w:
805-10-01-L 01          Connect deck fill812/13/2412/13/248.0h:
805-10-01-L 02          Install/connect applances812/12/2412/13/248.0h:
805-10-01-L 03          Wash down spigot412/13/2412/13/244.0h:
806  Transom2412/11/2412/13/242.5w:
806-10    Plumbing2412/11/2412/13/2424.0h:
806-10-01      Sink2412/11/2412/13/2424.0h:
806-10-01-L        Labor2412/11/2412/13/240.6w:
806-10-01-L 01          Install freshwater angle stops412/11/2412/11/244.0h:
806-10-01-L 02          Install faucets412/11/2412/11/244.0h:
806-10-01-L 03          Connect faucet to angle stops412/12/2412/12/244.0h:
806-10-01-L 04          Connect sink drains412/12/2412/12/244.0h:
806-10-01-L 05          Install/connect garbage disposal812/13/2412/13/248.0h:
807  Beach Club812/13/2412/13/241.6w:
807-10    Plumbing812/13/2412/13/248.0h:
807-10-01      Install/Connect812/13/2412/13/248.0h:
807-10-01-L        Labor812/13/2412/13/240.2w:
807-10-01-L 01          Install/Connect appliances/sink412/13/2412/13/244.0h:
807-10-01-L 02          Wash down spigot412/13/2412/13/244.0h:
815  Flybridge deck812/13/2412/13/246.3w:
815-10    Plumbing812/13/2412/13/248.0h:
815-10-01      Install/Connect812/13/2412/13/248.0h:
815-10-01-L        Labor812/13/2412/13/240.2w:
815-10-01-L 01          Install/Connect appliances/sink412/13/2412/13/244.0h:
815-10-01-L 02          Wash down spigot412/13/2412/13/244.0h:
******** *********************************************************************************