| WBS | Project Categories | Labor Hrs. | Start Date | Finish Dates | Duration | : | Comments |
| | DEPARTMENT TOTAL | 6,321 | 11/08/24 | 12/13/24 | . | : | . |
| 3 | MECHANICAL SYSTEMS | 4,904 | 11/08/24 | 12/13/24 | 67.2w | : | |
| 4 | ENGINE ROOM | 560 | 11/29/24 | 12/13/24 | 13.7w | : | |
| 6 | INTERIOR | 680 | 12/06/24 | 12/13/24 | 4.2w | : | |
| 8 | EXTERIOR | 177 | 12/10/24 | 12/13/24 | 33.2w | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |
|
|
| WBS | Job Description | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 3 | MECHANICAL SYSTEMS | 4,904 | 11/08/24 | 12/13/24 | 67.2w | : | |
| 301 | Freshwater | 760 | 11/20/24 | 12/13/24 | 3.5w | : | |
| 301-10 | Plumbing | 760 | 11/20/24 | 12/13/24 | 3.5w | : | |
| 301-10-01 | Piping - Lower area (P) | 336 | 11/25/24 | 12/13/24 | 15.0d | : | |
| 301-10-01-L | Labor | 336 | 12/02/24 | 12/13/24 | 1.9w | : | |
| 301-10-01-L 02 | Install guest area deck/bhd penetrations | 32 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 301-10-01-L 03 | Install hanger supports/foundations | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 301-10-01-L 04 | Rough-in guest area hot & cold main feed pipe | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 301-10-01-L 05 | Rough-in hot & cold drops to crew Fwd | 16 | 12/02/24 | 12/03/24 | 8.0h | : | |
| 301-10-01-L 06 | Rough-in hot & cold drops to main galley | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 301-10-01-L 07 | Rough-in hot & cold drops to guest bath | 48 | 12/03/24 | 12/06/24 | 24.0h | : | |
| 301-10-01-L 08 | Rough-in hot & cold drops to laundry | 16 | 12/06/24 | 12/09/24 | 8.0h | : | |
| 301-10-01-L 09 | Rough-in cold drop to blackwater tank cleanout | 16 | 12/09/24 | 12/10/24 | 8.0h | : | |
| 301-10-01-L 10 | Clean piping and cap all open lines | 8 | 12/10/24 | 12/10/24 | 4.0h | : | |
| 301-10-01-L 11 | Pressure test hot & cold piping | 24 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 301-10-01-L 12 | Insulate hot & cold main feed pipe | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 301-10-01-L 13 | Insulate drops to crew | 8 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 301-10-01-L 14 | Insulate drops to main galley | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 301-10-01-L 15 | Insulate drops to guest bathroom | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 301-10-02 | Piping - Main Deck | 68 | 11/25/24 | 12/13/24 | 15.0d | : | |
| 301-10-02-L | Labor | 68 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 301-10-02-L 01 | Install main deck/bhd penetrations | 12 | 12/04/24 | 12/06/24 | 12.0h | : | |
| 301-10-02-L 02 | Install hanger supports/foundations | 16 | 12/06/24 | 12/10/24 | 16.0h | : | |
| 301-10-02-L 03 | Rough-in main deck hot & cold main feed pipe | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 301-10-02-L 04 | Rough-in hot & cold drops to master stateroom | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 301-10-02-L 05 | Rough-in hot & cold drops to main salon | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 301-10-02-L 06 | Clean piping and cap all open lines | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 301-10-02-L 07 | Pressure test hot & cold piping | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 301-10-02-L 08 | Insulate hot & cold main feed pipe | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 301-10-02-L 09 | Insulate drops to pilothouse | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 301-10-04 | Piping - Exterior Decks | 96 | 11/27/24 | 12/13/24 | 12.5d | : | |
| 301-10-04-L | Labor | 96 | 11/28/24 | 12/13/24 | 2.4w | : | |
| 301-10-04-L 01 | Install exterior deck/bhd penetrations | 16 | 11/28/24 | 11/29/24 | 16.0h | : | |
| 301-10-04-L 02 | Install hanger supports/foundations | 24 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 301-10-04-L 03 | Rough-in cold drop to fwd hose bib | 4 | 12/05/24 | 12/05/24 | 4.0h | : | |
| 301-10-04-L 04 | Rough-in cold drop to aft hose bib | 4 | 12/05/24 | 12/05/24 | 4.0h | : | |
| 301-10-04-L 05 | Rough-in cold drop to flybridge hose bib | 4 | 12/06/24 | 12/06/24 | 4.0h | : | |
| 301-10-04-L 06 | Rough-in hot & cold drops to flybridge wet bar | 8 | 12/06/24 | 12/09/24 | 8.0h | : | |
| 301-10-04-L 07 | Clean piping and cap all open lines | 8 | 12/09/24 | 12/10/24 | 8.0h | : | |
| 301-10-04-L 08 | Pressure test hot & cold piping | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 301-10-04-L 09 | Insulate drop to fwd hose bib | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 301-10-04-L 10 | Insulate drop to aft hose bib | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 301-10-04-L 11 | Insulate drop to flybridge hose bib | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 301-10-04-L 12 | Insulate drops to flybridge wet bar | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 301-10-05 | Piping - Machinery Spaces | 120 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 301-10-05-L | Labor | 120 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 301-10-05-L 01 | Install guest area deck/bhd penetrations | 12 | 11/25/24 | 11/26/24 | 12.0h | : | |
| 301-10-05-L 02 | Install hanger supports/foundations | 16 | 11/26/24 | 11/28/24 | 16.0h | : | |
| 301-10-05-L 03 | Rough-in H&C main feed pipe thru engine room | 16 | 11/28/24 | 12/02/24 | 16.0h | : | |
| 301-10-05-L 04 | Rough-in cold drop to AC make up | 12 | 12/02/24 | 12/03/24 | 12.0h | : | |
| 301-10-05-L 05 | Rough-in cold drop to blackwater system | 12 | 12/04/24 | 12/05/24 | 12.0h | : | |
| 301-10-05-L 06 | Rough-in cold drop to seachest priming | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 301-10-05-L 07 | Rough-in hot & cold drops to sink | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 301-10-05-L 08 | Plumb deck fills to tanks | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 301-10-06 | Pumps | 140 | 11/20/24 | 12/13/24 | 140.0h | : | |
| 301-10-06-L | Labor | 140 | 11/20/24 | 12/13/24 | 3.5w | : | |
| 301-10-06-L 01 | Install FW pump in tank | 12 | 11/20/24 | 11/21/24 | 12.0h | : | |
| 301-10-06-L 02 | Install main pressure filters | 16 | 11/22/24 | 11/25/24 | 16.0h | : | |
| 301-10-06-L 03 | Install supply manifold piping | 12 | 11/26/24 | 11/27/24 | 12.0h | : | |
| 301-10-06-L 04 | Connect FW tank to supply manifold | 16 | 11/27/24 | 11/29/24 | 16.0h | : | |
| 301-10-06-L 05 | Connect pressure filters to supply manifold | 16 | 11/29/24 | 12/03/24 | 16.0h | : | |
| 301-10-06-L 06 | Connect dockside supply to manifold | 16 | 12/03/24 | 12/05/24 | 16.0h | : | |
| 301-10-06-L 07 | Install pumps w/ cross over system | 12 | 12/05/24 | 12/06/24 | 12.0h | : | |
| 301-10-06-L 08 | Connect system pressure filters to system piping | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 301-10-06-L 09 | Fill & commission system | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 302 | Graywater system | 600 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 302-10 | Plumbing | 600 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 302-10-01 | Piping - Lower deck (P) | 240 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 302-10-01-L | Labor | 240 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 302-10-01-L 02 | Install guest area deck/bhd penetrations | 24 | 11/25/24 | 11/27/24 | 24.0h | : | |
| 302-10-01-L 03 | Install hanger supports/foundations | 64 | 11/28/24 | 12/03/24 | 32.0h | : | |
| 302-10-01-L 04 | Rough in lower deck main pipe | 64 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 302-10-01-L 05 | Rough in drainage pipe to crew | 24 | 12/05/24 | 12/09/24 | 24.0h | : | |
| 302-10-01-L 06 | Rough in drainage pipe to galley | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 302-10-01-L 07 | Rough in drainage pipe to master bathroom | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 302-10-01-L 08 | Rough in drainage pipe to laundry | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 302-10-01-L 09 | Pressure test piping | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 302-10-02 | Piping - Main deck | 100 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 302-10-02-L | Labor | 100 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 302-10-02-L 01 | Install guest area deck/bhd penetrations | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 302-10-02-L 02 | Install hanger supports/foundations | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 302-10-02-L 03 | Rough in drainage pipe to wetbar | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 302-10-02-L 04 | Pressure test piping | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 302-10-03 | Piping - Flybridge deck | 100 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 302-10-03-L | Labor | 100 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 302-10-03-L 01 | Install guest area deck/bhd penetrations | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 302-10-03-L 02 | Install hanger supports/foundations | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 302-10-03-L 03 | Rough in drainage pipe to wetbar | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 302-10-03-L 04 | Pressure test piping | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 302-10-04 | Components | 160 | 11/18/24 | 12/13/24 | 160.0h | : | |
| 302-10-04-L | Labor | 160 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 302-10-04-L 01 | Connect garbage disposal overboard | 16 | 11/18/24 | 11/19/24 | 16.0h | : | |
| 302-10-04-L 02 | Connect 'rough in' plumbing to tanks | 16 | 11/20/24 | 11/21/24 | 16.0h | : | |
| 302-10-04-L 03 | Install/plumb tank suction strainer | 24 | 11/22/24 | 11/26/24 | 24.0h | : | |
| 302-10-04-L 04 | Install/plumb pumps to tank | 16 | 11/27/24 | 11/28/24 | 16.0h | : | |
| 302-10-04-L 05 | Plumb maserator pump | 24 | 11/29/24 | 12/03/24 | 24.0h | : | |
| 302-10-04-L 06 | Connect maserator pump to deck discharge | 16 | 12/04/24 | 12/05/24 | 16.0h | : | |
| 302-10-04-L 07 | Install/plumb cross over to blackwater pump | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 302-10-04-L 08 | Fab/Install discharge manifold | 16 | 12/11/24 | 12/12/24 | 16.0h | : | |
| 302-10-04-L 09 | Plumb pumps to overboard | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 303 | Blackwater | 556 | 11/13/24 | 12/13/24 | 4.5w | : | |
| 303-10 | Plumbing | 556 | 11/13/24 | 12/13/24 | 4.5w | : | |
| 303-10-01 | Components | 180 | 11/13/24 | 12/13/24 | 180.0h | : | |
| 303-10-01-L | Labor | 180 | 11/13/24 | 12/13/24 | 4.5w | : | |
| 303-10-01-L 01 | Rough in tank discharge to pump | 24 | 11/13/24 | 11/18/24 | 24.0h | : | |
| 303-10-01-L 02 | Connect 'rough in' plumbing to tanks | 24 | 11/18/24 | 11/21/24 | 24.0h | : | |
| 303-10-01-L 03 | Install/plumb tank suction strainer | 32 | 11/21/24 | 11/27/24 | 32.0h | : | |
| 303-10-01-L 04 | Install/plumb pumps to tank | 24 | 11/27/24 | 12/02/24 | 24.0h | : | |
| 303-10-01-L 05 | Install maserator pump | 24 | 12/02/24 | 12/05/24 | 24.0h | : | |
| 303-10-01-L 06 | Plumb maserator pump to deck dischange | 16 | 12/05/24 | 12/09/24 | 16.0h | : | |
| 303-10-01-L 07 | Connect supply to freshwater system | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 303-10-01-L 08 | Fab/Install discharge manifold | 16 | 12/11/24 | 12/12/24 | 16.0h | : | |
| 303-10-01-L 09 | Plumb pumps to overboard | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 303-10-02 | Piping - Lower Deck (P) | 200 | 11/26/24 | 12/13/24 | 112.0h | : | |
| 303-10-02-L | Labor | 200 | 11/26/24 | 12/13/24 | 2.8w | : | |
| 303-10-02-L 02 | Install guest area deck/bhd penetrations | 16 | 11/26/24 | 11/27/24 | 16.0h | : | |
| 303-10-02-L 03 | Install hanger supports/foundations | 24 | 11/28/24 | 12/02/24 | 24.0h | : | |
| 303-10-02-L 04 | Rough in lower deck guest main pipe | 80 | 12/03/24 | 12/09/24 | 40.0h | : | |
| 303-10-02-L 05 | Rough in drainage pipe to Crew | 32 | 12/06/24 | 12/11/24 | 32.0h | : | |
| 303-10-02-L 06 | Rough in drainage pipe to Master bath toilet | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 303-10-02-L 07 | Rough in drainage pipe to Master bath bidet | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 303-10-02-L 08 | Pressure test piping | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 303-10-03 | Piping - Main Deck | 144 | 11/28/24 | 12/13/24 | 96.0h | : | |
| 303-10-03-L | Labor | 144 | 11/28/24 | 12/13/24 | 2.4w | : | |
| 303-10-03-L 01 | Install guest area deck/bhd penetrations | 16 | 11/28/24 | 11/29/24 | 16.0h | : | |
| 303-10-03-L 02 | Install hanger supports/foundations | 24 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 303-10-03-L 03 | Rough in lower deck guest main pipe | 64 | 12/05/24 | 12/10/24 | 32.0h | : | |
| 303-10-03-L 04 | Rough in drainage pipe to guest 1 | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 303-10-03-L 05 | Rough in drainage pipe to guest 2 | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 303-10-03-L 06 | Rough in drainage pipe to Master toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 303-10-03-L 07 | Pressure test piping | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 303-10-04 | Insulation | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 303-10-04-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 303-10-04-L 01 | Insulate lower deck crew supply piping | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 303-10-04-L 02 | Insulate lower deck guest supply piping | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 304 | Air Conditioning | 1,896 | 11/08/24 | 12/13/24 | 5.1w | : | |
| 304-10 | Plumbing | 1,896 | 11/08/24 | 12/13/24 | 5.1w | : | |
| 304-10-01 | Components | 480 | 11/08/24 | 12/13/24 | 204.0h | : | |
| 304-10-01-L | Labor | 480 | 11/08/24 | 12/13/24 | 5.1w | : | |
| 304-10-01-L 01 | Install main deck/bhd pipe penetrations | 24 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 304-10-01-L 02 | Install pipe hanger supports/foundations | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 304-10-01-L 03 | Rough-in engine rm. chill water pipe | 48 | 11/08/24 | 11/13/24 | 24.0h | : | |
| 304-10-01-L 04 | Rough-in chiller base condensate drain | 16 | 11/13/24 | 11/14/24 | 8.0h | : | |
| 304-10-01-L 05 | Pressure test chill water system piping | 24 | 11/14/24 | 11/15/24 | 12.0h | : | |
| 304-10-01-L 06 | Install chilled water pumps | 24 | 11/18/24 | 11/19/24 | 12.0h | : | |
| 304-10-01-L 07 | Connect chill water pipe to chiller unit | 32 | 11/19/24 | 11/21/24 | 16.0h | : | |
| 304-10-01-L 08 | Connect system to circulating water pumps | 24 | 11/21/24 | 11/22/24 | 12.0h | : | |
| 304-10-01-L 09 | Insulate all engine rm. chill water pipe | 48 | 11/25/24 | 11/27/24 | 24.0h | : | |
| 304-10-01-L 10 | Fabricate raw water supply manifold | 32 | 11/28/24 | 11/29/24 | 16.0h | : | |
| 304-10-01-L 11 | Fabricate raw water discharge manifold | 24 | 12/02/24 | 12/03/24 | 12.0h | : | |
| 304-10-01-L 12 | Install raw water pumps | 24 | 12/03/24 | 12/04/24 | 12.0h | : | |
| 304-10-01-L 13 | Install/connect raw water supply manifold | 32 | 12/05/24 | 12/06/24 | 16.0h | : | |
| 304-10-01-L 14 | Install/connect raw water discharge manifold | 24 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 304-10-01-L 15 | Install/plumb raw water pumps | 24 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 304-10-01-L 16 | Connect freshwater make up system | 16 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 304-10-01-L 17 | Plumb raw water pumps to overboard | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 304-10-02 | Piping - Lower area | 600 | 11/12/24 | 12/13/24 | 23.3d | : | |
| 304-10-03 | Piping - Main Deck | 672 | 11/18/24 | 12/13/24 | 20.0d | : | |
| 304-10-03-L | Labor | 672 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 304-10-03-L 01 | Install main deck/bhd penetrations | 72 | 12/09/24 | 12/11/24 | 24.0h | : | |
| 304-10-03-L 02 | Install hanger supports/foundations | 48 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 304-10-03-L 03 | Rough-in main deck chill water main feed pipe | 240 | 11/18/24 | 11/29/24 | 80.0h | : | |
| 304-10-03-L 04 | Rough-in chill water drops to master stateroom | 72 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 304-10-03-L 05 | Rough-in chill water drops to main salon | 72 | 12/05/24 | 12/09/24 | 24.0h | : | |
| 304-10-03-L 06 | Clean piping and cap all open lines | 48 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 304-10-03-L 07 | Pressure test chill water piping | 48 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 304-10-03-L 08 | Rough-in condensate drain to main salon | 72 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 304-10-04 | Engine room | 144 | 11/12/24 | 12/13/24 | 23.3d | : | |
| 306 | Deck Drainage System | 356 | 11/20/24 | 12/13/24 | 3.6w | : | |
| 306-10 | Plumbing | 356 | 11/20/24 | 12/13/24 | 144.0h | : | |
| 306-10-01 | Pipe Penetrations | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 306-10-01-L | Labor | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 306-10-01-L 02 | Main deck | 12 | 12/06/24 | 12/09/24 | 12.0h | : | |
| 306-10-01-L 03 | below FB deck | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 306-10-01-L 04 | engine room | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 306-10-01-L 05 | pump hold | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 306-10-02 | Equipment Mounting | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 306-10-02-L | Labor | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 306-10-02-L 01 | Install Fwd Main deck drain wastes | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 306-10-02-L 02 | Install Port Main deck drain wastes | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 306-10-02-L 03 | Install STB Main deck drain wastes | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 306-10-02-L 04 | Install Aft Main deck drain wastes | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 306-10-02-L 05 | Install Flybridge deck drain wastes | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 306-10-03 | Deck Drain Plumbing - P | 144 | 11/20/24 | 12/13/24 | 144.0h | : | |
| 306-10-03-L | Labor | 144 | 11/20/24 | 12/13/24 | 144.0h | : | |
| 306-10-03-L 01 | Install Fwd Main deck drain pipe | 8 | 11/20/24 | 11/20/24 | 8.0h | : | |
| 306-10-03-L 02 | Install Port Main deck drain pipe | 8 | 11/21/24 | 11/21/24 | 8.0h | : | |
| 306-10-03-L 03 | Install STB Main deck drain pipe | 8 | 11/22/24 | 11/22/24 | 8.0h | : | |
| 306-10-03-L 04 | Install Aft Main deck drain pipe | 8 | 11/25/24 | 11/25/24 | 8.0h | : | |
| 306-10-03-L 05 | Install Flybridge deck drain pipe | 8 | 11/26/24 | 11/26/24 | 8.0h | : | |
| 306-10-03-L 06 | Connect Fwd Main deck drain pipe | 8 | 11/27/24 | 11/27/24 | 8.0h | : | |
| 306-10-03-L 07 | Connect Port Main deck drain pipe | 8 | 11/28/24 | 11/28/24 | 8.0h | : | |
| 306-10-03-L 08 | Connect STB Main deck drain pipe | 8 | 11/29/24 | 11/29/24 | 8.0h | : | |
| 306-10-03-L 09 | Connect Aft Main deck drain pipe | 8 | 12/02/24 | 12/02/24 | 8.0h | : | |
| 306-10-03-L 10 | Connect Flybridge deck drain pipe | 8 | 12/03/24 | 12/03/24 | 8.0h | : | |
| 306-10-03-L 11 | Install Fwd Main hatch drain pipe | 8 | 12/04/24 | 12/04/24 | 8.0h | : | |
| 306-10-03-L 12 | Install Port Main hatch drain pipe | 8 | 12/05/24 | 12/05/24 | 8.0h | : | |
| 306-10-03-L 13 | Install STB Main hatch drain pipe | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 306-10-03-L 14 | Install Aft Main hatch drain pipe | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 306-10-03-L 15 | Connect Fwd Main hatch drain pipe | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 306-10-03-L 16 | Connect Port Main hatch drain pipe | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 306-10-03-L 17 | Connect STB Main hatch drain pipe | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 306-10-03-L 18 | Connect Aft Main hatch drain pipe | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 306-10-04 | Deck Drain Plumbing - S | 144 | 11/20/24 | 12/13/24 | 144.0h | : | |
| 306-10-04-L | Labor | 144 | 11/20/24 | 12/13/24 | 144.0h | : | |
| 306-10-04-L 01 | Install Fwd Main deck drain pipe | 8 | 11/20/24 | 11/20/24 | 8.0h | : | |
| 306-10-04-L 02 | Install Port Main deck drain pipe | 8 | 11/21/24 | 11/21/24 | 8.0h | : | |
| 306-10-04-L 03 | Install STB Main deck drain pipe | 8 | 11/22/24 | 11/22/24 | 8.0h | : | |
| 306-10-04-L 04 | Install Aft Main deck drain pipe | 8 | 11/25/24 | 11/25/24 | 8.0h | : | |
| 306-10-04-L 05 | Install Flybridge deck drain pipe | 8 | 11/26/24 | 11/26/24 | 8.0h | : | |
| 306-10-04-L 06 | Connect Fwd Main deck drain pipe | 8 | 11/27/24 | 11/27/24 | 8.0h | : | |
| 306-10-04-L 07 | Connect Port Main deck drain pipe | 8 | 11/28/24 | 11/28/24 | 8.0h | : | |
| 306-10-04-L 08 | Connect STB Main deck drain pipe | 8 | 11/29/24 | 11/29/24 | 8.0h | : | |
| 306-10-04-L 09 | Connect Aft Main deck drain pipe | 8 | 12/02/24 | 12/02/24 | 8.0h | : | |
| 306-10-04-L 10 | Connect Flybridge deck drain pipe | 8 | 12/03/24 | 12/03/24 | 8.0h | : | |
| 306-10-04-L 11 | Install Fwd Main hatch drain pipe | 8 | 12/04/24 | 12/04/24 | 8.0h | : | |
| 306-10-04-L 12 | Install Port Main hatch drain pipe | 8 | 12/05/24 | 12/05/24 | 8.0h | : | |
| 306-10-04-L 13 | Install STB Main hatch drain pipe | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 306-10-04-L 14 | Install Aft Main hatch drain pipe | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 306-10-04-L 15 | Connect Fwd Main hatch drain pipe | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 306-10-04-L 16 | Connect Port Main hatch drain pipe | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 306-10-04-L 17 | Connect STB Main hatch drain pipe | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 306-10-04-L 18 | Connect Aft Main hatch drain pipe | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 312 | Bilge system | 560 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 312-10 | Plumbing | 560 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 312-10-01 | Rough-in DC Piping - P | 160 | 11/18/24 | 12/13/24 | 160.0h | : | |
| 312-10-01-L | Labor | 160 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 312-10-01-L 01 | Rough in DC pipe fwd | 32 | 11/18/24 | 11/21/24 | 32.0h | : | |
| 312-10-01-L 02 | Rough in DC pipe mid ship | 32 | 11/22/24 | 11/27/24 | 32.0h | : | |
| 312-10-01-L 03 | Rough in DC pipe fwd eng. room | 32 | 11/28/24 | 12/03/24 | 32.0h | : | |
| 312-10-01-L 04 | Rough in DC pipe aft eng. room | 32 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 312-10-01-L 05 | Rough in DC pipe lazzerette | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 312-10-02 | Install/Connect DC piping to pump - P | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 312-10-02-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 312-10-02-L 01 | Install/connect DC pump fwd | 16 | 12/02/24 | 12/03/24 | 16.0h | : | |
| 312-10-02-L 02 | Install/connect DC pump mid ship | 16 | 12/04/24 | 12/05/24 | 16.0h | : | |
| 312-10-02-L 03 | Install/connect DC pump fwd eng. room | 16 | 12/06/24 | 12/09/24 | 16.0h | : | |
| 312-10-02-L 04 | Install/connect DC pump aft eng. room | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 312-10-02-L 05 | Install/connect DC pump lazzerette | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 312-10-03 | Connect to DC piping Overboard - P | 40 | 12/05/24 | 12/13/24 | 50.0h | : | |
| 312-10-03-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 312-10-03-L 01 | Connect DC pump to overboard fwd | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 312-10-03-L 02 | Connect DC pump to overboard mid ship | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 312-10-03-L 03 | Connect DC pump to overboard fwd eng. room | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 312-10-03-L 04 | Connect DC pump to overboard aft eng. room | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 312-10-03-L 05 | Connect DC pump to overboard lazzerette | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 312-10-04 | Rough-in DC Piping - S | 160 | 11/18/24 | 12/13/24 | 160.0h | : | |
| 312-10-04-L | Labor | 160 | 11/18/24 | 12/13/24 | 4.0w | : | |
| 312-10-04-L 01 | Rough in DC pipe fwd | 32 | 11/18/24 | 11/21/24 | 32.0h | : | |
| 312-10-04-L 02 | Rough in DC pipe mid ship | 32 | 11/22/24 | 11/27/24 | 32.0h | : | |
| 312-10-04-L 03 | Rough in DC pipe fwd eng. room | 32 | 11/28/24 | 12/03/24 | 32.0h | : | |
| 312-10-04-L 04 | Rough in DC pipe aft eng. room | 32 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 312-10-04-L 05 | Rough in DC pipe lazzerette | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 312-10-05 | Install/Connect DC piping to pump - S | 80 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 312-10-05-L | Labor | 80 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 312-10-05-L 01 | Install/connect DC pump fwd | 16 | 12/02/24 | 12/03/24 | 16.0h | : | |
| 312-10-05-L 02 | Install/connect DC pump mid ship | 16 | 12/04/24 | 12/05/24 | 16.0h | : | |
| 312-10-05-L 03 | Install/connect DC pump fwd eng. room | 16 | 12/06/24 | 12/09/24 | 16.0h | : | |
| 312-10-05-L 04 | Install/connect DC pump aft eng. room | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 312-10-05-L 05 | Install/connect DC pump lazzerette | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 312-10-06 | Connect to DC piping Overboard | 40 | 12/03/24 | 12/13/24 | 72.0h | : | |
| 312-10-06-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 312-10-06-L 01 | Connect DC pump to overboard fwd | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 312-10-06-L 02 | Connect DC pump to overboard mid ship | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 312-10-06-L 03 | Connect DC pump to overboard fwd eng. room | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 312-10-06-L 04 | Connect DC pump to overboard aft eng. room | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 312-10-06-L 05 | Connect DC pump to overboard lazzerette | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 323 | Anchor | 24 | 12/11/24 | 12/13/24 | 10.0w | : | |
| 323-10 | Plumbing | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 323-10-01 | Connect | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 323-10-01-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 323-10-01-L 01 | Connect wash down system | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 330 | Watermakers | 152 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 330-10 | Plumbing | 152 | 12/04/24 | 12/13/24 | 1.5w | : | |
| 330-10-01 | Rough-in piping | 40 | 12/04/24 | 12/13/24 | 60.0h | : | |
| 330-10-01-L | Labor | 40 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 330-10-01-L 01 | Rough-in raw water supply from seachest | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 330-10-01-L 02 | Rough-in F.W supply to tank | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 330-10-01-L 03 | Rough-in overboard dump line | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 330-10-02 | Install | 56 | 12/05/24 | 12/13/24 | 56.0h | : | |
| 330-10-02-L | Labor | 56 | 12/05/24 | 12/13/24 | 1.4w | : | |
| 330-10-02-L 01 | Install L.P pump | 16 | 12/05/24 | 12/06/24 | 16.0h | : | |
| 330-10-02-L 02 | Install H.P pump | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 330-10-02-L 03 | Install filters | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 330-10-02-L 04 | Install watermaker membranes | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 330-10-03 | Connect | 56 | 12/05/24 | 12/13/24 | 56.0h | : | |
| 330-10-03-L | Labor | 56 | 12/05/24 | 12/13/24 | 1.4w | : | |
| 330-10-03-L 01 | Connect back flush to FW system | 16 | 12/05/24 | 12/06/24 | 16.0h | : | |
| 330-10-03-L 02 | Connect dump line to overboard discharge | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 330-10-03-L 03 | Connect L.P pump | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 330-10-03-L 04 | Connect H.P pump | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 330-10-03-L 05 | Connect membranes | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 4 | ENGINE ROOM | 560 | 11/29/24 | 12/13/24 | 13.7w | : | |
| 405 | Main engine Installation | 80 | 12/12/24 | 12/13/24 | 13.7w | : | |
| 405-04 | Metal Fabrication | 80 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 405-04-01 | Brackets/Foundations | 40 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 405-04-01-L | Labor | 40 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 405-04-01-L 01 | Fabricate exhaust gases overboard | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 405-04-01-L 02 | Fabricate exhaust water overboard | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 405-04-01-L 03 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 405-04-01-L 04 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 405-04-02 | Fabrication Piping | 40 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 405-04-02-L | Labor | 40 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 405-04-02-L 01 | Fabricate exhaust gases overboard | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 405-04-02-L 02 | Fabricate exhaust water overboard | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 405-04-02-L 03 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 405-04-02-L 04 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 410 | Generators | 80 | 12/12/24 | 12/13/24 | 2.4w | : | |
| 410-04 | Metal Fabrication | 80 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 410-04-01 | Brackets/Foundations | 40 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 410-04-01-L | Labor | 40 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 410-04-01-L 01 | Fabricate exhaust gases overboard | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 410-04-01-L 02 | Fabricate exhaust water overboard | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 410-04-01-L 03 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 410-04-01-L 04 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 410-04-02 | Fabrication Piping | 40 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 410-04-02-L | Labor | 40 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 410-04-02-L 01 | Fabricate exhaust gases overboard | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 410-04-02-L 02 | Fabricate exhaust water overboard | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 410-04-02-L 03 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 410-04-02-L 04 | Install exhaust water overboard | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 415 | Sea chests | 84 | 12/10/24 | 12/13/24 | 1.0w | : | |
| 415-04 | Metal Fabrication | 84 | 12/10/24 | 12/13/24 | 1.0w | : | |
| 415-04-01 | Main engines Install/Connect | 42 | 12/12/24 | 12/13/24 | 38.0h | : | |
| 415-04-01-L | Labor | 42 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 415-04-01-L 01 | Install intake standpipe (P) | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 415-04-01-L 02 | Install seachest (P) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 415-04-01-L 03 | Install supply/crossover pipe | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 415-04-01-L 04 | Install access cover/strainer (S) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 415-04-02 | Aux Install/Connect | 42 | 12/10/24 | 12/13/24 | 39.0h | : | |
| 415-04-02-L | Labor | 42 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 415-04-02-L 01 | Install intake standpipe (S) | 6 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 415-04-02-L 02 | Install seachest (S) | 12 | 12/10/24 | 12/11/24 | 12.0h | : | |
| 415-04-02-L 03 | Install supply/crossover pipe | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 415-04-02-L 04 | Install access cover/strainer (S) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 416 | Raw water cooling systems | 228 | 12/04/24 | 12/13/24 | 1.6w | : | |
| 416-04 | Metal Fabrication | 228 | 12/04/24 | 12/13/24 | 1.6w | : | |
| 416-04-02 | Brackets - S | 80 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 416-04-02-L | Labor | 80 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 416-04-02-L 01 | Fabricate pipe hanger foundations | 24 | 12/09/24 | 12/11/24 | 24.0h | : | |
| 416-04-02-L 02 | Fabricate pipe hangers | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 416-04-02-L 03 | Machine standpipe flanges | 40 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 416-04-03 | Rough-in Piping | 104 | 12/04/24 | 12/13/24 | 64.0h | : | |
| 416-04-03-L | Labor | 104 | 12/04/24 | 12/13/24 | 1.6w | : | |
| 416-04-03-L 01 | Rough in Main Engine supply (P) | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 416-04-03-L 02 | Rough in generator supply (S) | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 416-04-03-L 03 | Rough in AC chiller supply (1) | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 416-04-03-L 04 | Rough in fire pump supply | 32 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 416-04-03-L 05 | Rough in hydraulic cooling supply | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 416-04-03-L 06 | Rough in watermaker supply | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 416-04-04 | Install Piping | 44 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 416-04-04-L | Labor | 44 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 416-04-04-L 01 | Install all shut off valve to seachest crossover | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 416-04-04-L 02 | Install/Connect Main engine supply to crossover (P) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 416-04-04-L 03 | Install/connect generator supply to crossover (S) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 416-04-04-L 04 | Install/connect AC supply to crossover (2) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 416-04-04-L 05 | Install/connect watermaker supply to crossover | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 420 | Lube oil | 88 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 420-04 | Metal Fabrication | 88 | 11/29/24 | 12/13/24 | 88.0h | : | |
| 420-04-01 | Components - P | 88 | 11/29/24 | 12/13/24 | 88.0h | : | |
| 420-04-01-L | Labor | 88 | 11/29/24 | 12/13/24 | 2.2w | : | |
| 420-04-01-L 01 | Fabricate transfer manifold | 24 | 11/29/24 | 12/03/24 | 24.0h | : | |
| 420-04-01-L 02 | Fabricate Clean oil tank | 32 | 12/04/24 | 12/09/24 | 32.0h | : | |
| 420-04-01-L 03 | Fabricate Dirty oil tank | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 6 | INTERIOR | 680 | 12/06/24 | 12/13/24 | 4.2w | : | |
| 602 | Guest Stateroom 1 | 16 | 12/12/24 | 12/13/24 | 2.0w | : | |
| 602-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 602-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 602-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 602-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 602-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 602-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603 | Guest Bathroom 1 | 28 | 12/13/24 | 12/13/24 | 2.4w | : | |
| 603-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 603-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 603-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 603-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 603-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 603-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 603-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 603-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 603-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 603-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 603-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604 | Guest Stateroom 2 | 16 | 12/12/24 | 12/13/24 | 2.2w | : | |
| 604-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 604-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 604-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 604-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 604-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 604-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605 | Guest Bathroom 2 | 28 | 12/13/24 | 12/13/24 | 2.4w | : | |
| 605-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 605-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 605-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 605-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 605-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 605-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 605-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 605-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 605-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 605-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 605-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606 | Guest Stateroom 3 | 16 | 12/12/24 | 12/13/24 | 2.9w | : | |
| 606-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 606-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 606-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 606-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 606-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 606-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607 | Guest Bathroom 3 | 28 | 12/13/24 | 12/13/24 | 2.4w | : | |
| 607-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 607-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 607-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 607-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 607-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 607-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 607-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 607-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 607-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 607-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 607-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608 | Guest Stateroom 4 | 16 | 12/12/24 | 12/13/24 | 2.9w | : | |
| 608-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 608-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 608-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 608-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 608-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 608-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609 | Guest Bathroom 4 | 28 | 12/13/24 | 12/13/24 | 2.4w | : | |
| 609-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 609-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 609-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 609-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 609-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 609-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 609-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 609-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 609-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 609-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 609-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 615 | Lower Guest Foyer - STBD | 12 | 12/12/24 | 12/13/24 | 1.3w | : | |
| 615-10 | Plumbing | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 615-10-01 | Appliances | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 615-10-01-M | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 615-10-01-M 01 | Install supply to washer | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 615-10-01-M 02 | Connect washer supply | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620 | Captain's cabin 1 | 16 | 12/12/24 | 12/13/24 | 2.9w | : | |
| 620-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 620-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 620-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 620-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 620-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 620-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621 | Captain's Bathroom | 28 | 12/13/24 | 12/13/24 | 1.9w | : | |
| 621-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 621-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 621-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 621-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 621-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 621-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 621-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 621-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 621-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 621-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 621-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622 | Crew cabin 1 | 16 | 12/12/24 | 12/13/24 | 2.9w | : | |
| 622-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 622-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 622-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 622-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 622-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 622-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623 | Crew Bathroom | 28 | 12/13/24 | 12/13/24 | 1.9w | : | |
| 623-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 623-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 623-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 623-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 623-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 623-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 623-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 623-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 623-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 623-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 623-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624 | Crew cabin 2 | 16 | 12/12/24 | 12/13/24 | 2.9w | : | |
| 624-10 | Plumbing | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 624-10-01 | Air Conditioning | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 624-10-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 624-10-01-L 01 | Install AC fan coils | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 624-10-01-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 624-10-01-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625 | Crew Bathroom 2 | 28 | 12/13/24 | 12/13/24 | 1.9w | : | |
| 625-10 | Plumbing | 28 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 625-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 625-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 625-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 625-10-02 | Shower | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 625-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 625-10-02-L 01 | Connect shower drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-10-02-L 02 | Install/connect shower mixer | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-10-03 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 625-10-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 625-10-03-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-10-03-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 625-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 625-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 635 | Laundry | 12 | 12/12/24 | 12/13/24 | 1.3w | : | |
| 635-10 | Plumbing | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 635-10-01 | Appliances | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 635-10-01-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 635-10-01-L 01 | Install supply to washer | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 635-10-01-L 02 | Connect washer supply | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 636 | Crew Lounge area | 84 | 12/06/24 | 12/13/24 | 2.0w | : | |
| 636-10 | Plumbing | 84 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 636-10-01 | Sink | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 636-10-01-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 636-10-01-L 01 | Install freshwater angle stops | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-10-01-L 02 | Install faucets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 636-10-01-L 03 | Connect faucet to angle stops | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-10-01-L 04 | Connect sink drains | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 636-10-01-L 05 | Install/connect garbage disposal | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 636-10-02 | Air Conditioning | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 636-10-02-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 636-10-02-L 01 | Install AC fan coils | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 636-10-02-L 02 | Connect AC supply/return | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 636-10-02-L 03 | Connect AC condensate drain | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 636-10-03 | Appliances | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 636-10-03-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 636-10-03-L 01 | Install supply to icemaker | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 636-10-03-L 02 | Connect ice maker supply | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 641 | Owners Stateroom | 32 | 12/10/24 | 12/13/24 | 3.2w | : | |
| 641-10 | Plumbing | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 641-10-01 | Air Conditioning | 32 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 641-10-01-L | Labor | 32 | 12/10/24 | 12/13/24 | 0.8w | : | |
| 641-10-01-L 01 | Install AC fan coils | 16 | 12/10/24 | 12/11/24 | 16.0h | : | |
| 641-10-01-L 02 | Connect AC supply/return | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 641-10-01-L 03 | Connect AC condensate drain | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 643 | Owners Bathroom | 48 | 12/12/24 | 12/13/24 | 3.8w | : | |
| 643-10 | Plumbing | 48 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 643-10-01 | Sink | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 643-10-01-L | Labor | 12 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 643-10-01-L 01 | Install freshwater angle stops | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 643-10-01-L 02 | Install faucet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 643-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 643-10-02 | Shower | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 643-10-02-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 643-10-02-L 01 | Connect shower drain | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 643-10-02-L 02 | Install/connect shower mixer | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 643-10-03 | Toilet | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 643-10-03-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 643-10-03-L 01 | Install/connect toilet soleniod | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 643-10-03-L 02 | Install/plumb toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 643-10-04 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 643-10-04-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 643-10-04-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 645 | Galley | 96 | 12/06/24 | 12/13/24 | 2.0w | : | |
| 645-10 | Plumbing | 96 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 645-10-01 | Sink | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 645-10-01-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 645-10-01-L 01 | Install freshwater angle stops | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-10-01-L 02 | Install faucets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 645-10-01-L 03 | Connect faucet to angle stops | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-10-01-L 04 | Connect sink drains | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-10-01-L 05 | Install/connect garbage disposal | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 645-10-02 | Air Conditioning | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 645-10-02-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 645-10-02-L 01 | Install AC fan coils | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 645-10-02-L 02 | Connect AC supply/return | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 645-10-02-L 03 | Connect AC condensate drain | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 645-10-03 | Appliances | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 645-10-03-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 645-10-03-L 01 | Install supply to icemaker | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 645-10-03-L 02 | Connect ice maker supply | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 645-10-03-L 03 | Install supply to washer | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 645-10-03-L 04 | Connect washer supply | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647 | Powder room | 20 | 12/13/24 | 12/13/24 | 1.9w | : | |
| 647-10 | Plumbing | 20 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 647-10-01 | Sink | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 647-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 647-10-01-L 01 | Install freshwater angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-10-01-L 02 | Install faucet | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-10-01-L 03 | Connect faucet to angle stops | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-10-01-L 04 | Connect sink drain | 2 | 12/13/24 | 12/13/24 | 2.0h | : | |
| 647-10-02 | Toilet | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 647-10-02-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 647-10-02-L 01 | Install/connect toilet soleniod | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-10-02-L 02 | Install/plumb toilet | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-10-03 | Finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 647-10-03-L | Labor | 4 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 647-10-03-L 01 | Install all finish trims | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652 | Main Salon | 20 | 12/11/24 | 12/13/24 | 3.3w | : | |
| 652-10 | Plumbing | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 652-10-02 | Air Condtioning | 20 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 652-10-02-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 652-10-02-L 01 | Install AC fan coils | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 652-10-02-L 02 | Connect AC supply/return | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 652-10-02-L 03 | Connect AC condensate drain | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 661 | Pilothouse | 48 | 12/06/24 | 12/13/24 | 2.0w | : | |
| 661-10 | Plumbing | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 661-10-01 | Air Conditioning | 48 | 12/06/24 | 12/13/24 | 48.0h | : | |
| 661-10-01-L | Labor | 48 | 12/06/24 | 12/13/24 | 1.2w | : | |
| 661-10-01-L 01 | Install AC fan coils | 24 | 12/06/24 | 12/10/24 | 24.0h | : | |
| 661-10-01-L 02 | Connect AC supply/return | 12 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 661-10-01-L 03 | Connect AC condensate drain | 12 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 8 | EXTERIOR | 177 | 12/10/24 | 12/13/24 | 33.2w | : | |
| 802 | Main deck - FWD | 69 | 12/10/24 | 12/13/24 | 4.6w | : | |
| 802-10 | Plumbing | 69 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 802-10-01 | Install/Connect | 69 | 12/10/24 | 12/13/24 | 29.0h | : | |
| 802-10-01-L | Labor | 69 | 12/10/24 | 12/13/24 | 0.7w | : | |
| 802-10-01-L 01 | Connect drains | 21 | 12/10/24 | 12/12/24 | 21.0h | : | |
| 802-10-01-L 02 | Connect deck fill | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 802-10-01-L 03 | Wash down spigots | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 802-10-01-L 04 | Plumb jacuzzi tub supply | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 802-10-01-L 05 | Plumb jacuzzi tub waste | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 803 | Main deck Walkway - Port | 24 | 12/11/24 | 12/13/24 | 1.7w | : | |
| 803-10 | Plumbing | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 803-10-01 | Install/Connect | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 803-10-01-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 803-10-01-L 01 | Connect drain drains | 16 | 12/11/24 | 12/12/24 | 16.0h | : | |
| 803-10-01-L 02 | Connect deck fill | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 804 | Main deck Walkway - STBD | 24 | 12/11/24 | 12/13/24 | 1.7w | : | |
| 804-10 | Plumbing | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 804-10-01 | Install/Connect | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 804-10-01-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 804-10-01-L 01 | Connect drain drains | 16 | 12/11/24 | 12/12/24 | 16.0h | : | |
| 804-10-01-L 02 | Connect deck fill | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 805 | Main deck - Aft | 20 | 12/12/24 | 12/13/24 | 4.0w | : | |
| 805-10 | Plumbing | 20 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 805-10-01 | Install/Connect | 20 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 805-10-01-L | Labor | 20 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 805-10-01-L 01 | Connect deck fill | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 805-10-01-L 02 | Install/connect applances | 8 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 805-10-01-L 03 | Wash down spigot | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 806 | Transom | 24 | 12/11/24 | 12/13/24 | 2.5w | : | |
| 806-10 | Plumbing | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 806-10-01 | Sink | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 806-10-01-L | Labor | 24 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 806-10-01-L 01 | Install freshwater angle stops | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 806-10-01-L 02 | Install faucets | 4 | 12/11/24 | 12/11/24 | 4.0h | : | |
| 806-10-01-L 03 | Connect faucet to angle stops | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 806-10-01-L 04 | Connect sink drains | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 806-10-01-L 05 | Install/connect garbage disposal | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 807 | Beach Club | 8 | 12/13/24 | 12/13/24 | 1.6w | : | |
| 807-10 | Plumbing | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 807-10-01 | Install/Connect | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 807-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 807-10-01-L 01 | Install/Connect appliances/sink | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 807-10-01-L 02 | Wash down spigot | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 815 | Flybridge deck | 8 | 12/13/24 | 12/13/24 | 6.3w | : | |
| 815-10 | Plumbing | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 815-10-01 | Install/Connect | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 815-10-01-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 815-10-01-L 01 | Install/Connect appliances/sink | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 815-10-01-L 02 | Wash down spigot | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |