| WBS | Project Categories | Labor Hrs. | Start Date | Finish Dates | Duration | : | Comments |
| | DEPARTMENT TOTAL | 4,320 | 11/15/24 | 12/13/24 | . | : | . |
| 4 | ENGINE ROOM | 476 | 11/26/24 | 12/13/24 | 13.7w | : | |
| 6 | INTERIOR | 1,008 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 7 | MECHANICAL SPACES | 1,092 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 8 | EXTERIOR | 1,744 | 11/26/24 | 12/13/24 | 33.2w | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |
|
|
| WBS | Job Description | Labor Hrs. | Start Date | Finish Date | Duration | : | Comments |
| 4 | ENGINE ROOM | 476 | 11/26/24 | 12/13/24 | 13.7w | : | |
| 401 | Insulation | 240 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 401-14 | Marine Outfitting | 240 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 401-14-01 | Insulation | 80 | 12/05/24 | 12/13/24 | 56.0h | : | |
| 401-14-01-L | Labor | 80 | 12/05/24 | 12/13/24 | 1.4w | : | |
| 401-14-01-L 02 | Install Fire insulation to fwd bulkhead | 8 | 12/05/24 | 12/05/24 | 8.0h | : | |
| 401-14-01-L 03 | Install Fire insulation to aft bulkhead | 8 | 12/06/24 | 12/06/24 | 8.0h | : | |
| 401-14-01-L 04 | Install mass damping to fwd Bulkhead | 8 | 12/09/24 | 12/09/24 | 8.0h | : | |
| 401-14-01-L 05 | Install mass damping to aft Bulkhead | 8 | 12/10/24 | 12/10/24 | 8.0h | : | |
| 401-14-01-L 06 | Install Sound insulation to fwd bulkhead | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 401-14-01-L 07 | Install Sound insulation to aft bulkhead | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 401-14-01-L 08 | Install insulation to ship sides (P) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 401-14-01-L 09 | Install Fire insulation to overhead | 8 | 12/11/24 | 12/11/24 | 8.0h | : | |
| 401-14-01-L 10 | Install mass damping to overhead | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 401-14-01-L 11 | Install Sound insulation to overhead | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 401-14-02 | Framing | 160 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 401-14-02-L | Labor | 160 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 401-14-02-L 01 | Frame out Fwd bulkhead | 48 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 401-14-02-L 02 | Frame out Aft bulkhead | 48 | 12/05/24 | 12/09/24 | 24.0h | : | |
| 401-14-02-L 03 | Frame out Cabin Side (P) | 64 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 425 | Outfitting | 236 | 11/26/24 | 12/13/24 | 3.0w | : | |
| 425-04 | Metal Fabrication | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 425-04-02 | Flooring | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 425-04-02-L | Labor | 32 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 425-04-02-L 01 | Install diamond plate flooring (S) | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 425-04-02-L 02 | Install diamond plate flooring (S) | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 425-14 | Marine Outfitting | 204 | 11/26/24 | 12/13/24 | 108.0h | : | |
| 425-14-01 | Finish Paneling | 112 | 11/26/24 | 12/13/24 | 108.0h | : | |
| 425-14-01-L | Labor | 112 | 12/05/24 | 12/13/24 | 1.4w | : | |
| 425-14-01-L 01 | Install finish panels Fwd bulkhead | 32 | 12/05/24 | 12/06/24 | 16.0h | : | |
| 425-14-01-L 02 | Install finish panels Fwd bulkhead | 32 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 425-14-01-L 03 | Install cabin side pref port | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 425-14-02 | Overhead | 92 | 11/26/24 | 12/13/24 | 108.0h | : | |
| 425-14-02-L | Labor | 92 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 425-14-02-L 01 | Fabricate recess light boxes | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 425-14-02-L 02 | Install recess light boxes | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 425-14-02-L 03 | Install overhead framing | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 425-14-02-L 04 | Install overhead perf | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 425-14-02-L 05 | Brushed aluminum edging | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 6 | INTERIOR | 1,008 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 601 | LOWER GUEST FRAMING | 336 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 601-14 | Marine Outfitting | 336 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 601-14-01 | Shipside Insulation | 336 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 601-14-01-L | Labor | 336 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 601-14-01-L 01 | Install insulation pins to Lower deck shipside | 32 | 11/15/24 | 11/18/24 | 16.0h | : | |
| 601-14-01-L 02 | Install insulation pins to Lower deck aft bhd | 32 | 11/19/24 | 11/20/24 | 16.0h | : | |
| 601-14-01-L 03 | Install insulation pins to Lower deck overhead | 32 | 11/21/24 | 11/22/24 | 16.0h | : | |
| 601-14-01-L 04 | Install insulation to Lower deck shipside | 80 | 11/25/24 | 11/29/24 | 40.0h | : | |
| 601-14-01-L 05 | Install insulation to Lower deck aft bhd | 80 | 12/02/24 | 12/06/24 | 40.0h | : | |
| 601-14-01-L 06 | Install insulation to Lower deck overhead | 80 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 619 | LOWER CREW FRAMING | 336 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 619-14 | Marine Outfitting | 336 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 619-14-01 | Shipside Insulation | 336 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 619-14-01-L | Labor | 336 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 619-14-01-L 01 | Install insulation pins to Lower deck shipside | 32 | 11/15/24 | 11/18/24 | 16.0h | : | |
| 619-14-01-L 02 | Install insulation pins to Lower deck aft bhd | 32 | 11/19/24 | 11/20/24 | 16.0h | : | |
| 619-14-01-L 03 | Install insulation pins to Lower deck overhead | 32 | 11/21/24 | 11/22/24 | 16.0h | : | |
| 619-14-01-L 04 | Install insulation to Lower deck shipside | 80 | 11/25/24 | 11/29/24 | 40.0h | : | |
| 619-14-01-L 05 | Install insulation to Lower deck aft bhd | 80 | 12/02/24 | 12/06/24 | 40.0h | : | |
| 619-14-01-L 06 | Install insulation to Lower deck overhead | 80 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 640 | MAIN DECK FRAMING | 336 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 640-14 | Marine Outfitting | 336 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 640-14-01 | Insulation | 336 | 11/15/24 | 12/13/24 | 168.0h | : | |
| 640-14-01-L | Labor | 336 | 11/15/24 | 12/13/24 | 4.2w | : | |
| 640-14-01-L 01 | Install insulation pins to deck shipside | 32 | 11/15/24 | 11/18/24 | 16.0h | : | |
| 640-14-01-L 02 | Install insulation pins to deck aft bhd | 32 | 11/19/24 | 11/20/24 | 16.0h | : | |
| 640-14-01-L 03 | Install insulation pins to deck overhead | 32 | 11/21/24 | 11/22/24 | 16.0h | : | |
| 640-14-01-L 04 | Install insulation to deck shipside | 80 | 11/25/24 | 11/29/24 | 40.0h | : | |
| 640-14-01-L 05 | Install insulation to deck aft bhd | 80 | 12/02/24 | 12/06/24 | 40.0h | : | |
| 640-14-01-L 06 | Install insulation to deck overhead | 80 | 12/09/24 | 12/13/24 | 40.0h | : | |
| 7 | MECHANICAL SPACES | 1,092 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 701 | Chain locker | 160 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 701-14 | Marine Outfitting | 160 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 701-14-01 | Chain bin (P) | 160 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 701-14-01-L | Labor | 160 | 11/25/24 | 12/06/24 | 2.0w | : | |
| 701-14-01-L 01 | Frame out chain bin | 48 | 11/25/24 | 11/27/24 | 24.0h | : | |
| 701-14-01-L 02 | Dry-fit chain bin | 48 | 11/28/24 | 12/02/24 | 24.0h | : | |
| 701-14-01-L 03 | Install chain bin | 64 | 12/03/24 | 12/06/24 | 32.0h | : | |
| 702 | Machinery room - FWD | 408 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 702-14 | Marine Outfitting | 408 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 702-14-01 | Finish Paneling - P | 112 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 702-14-01-L | Labor | 112 | 11/25/24 | 12/03/24 | 1.4w | : | |
| 702-14-01-L 01 | Install finish panels Fwd bulkhead | 32 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 702-14-01-L 02 | Install finish panels Fwd bulkhead | 32 | 11/27/24 | 11/28/24 | 16.0h | : | |
| 702-14-01-L 03 | Install cabin side pref port | 48 | 11/29/24 | 12/03/24 | 24.0h | : | |
| 702-14-02 | Overhead - P | 92 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 702-14-02-L | Labor | 92 | 11/25/24 | 11/29/24 | 1.0w | : | |
| 702-14-02-L 01 | Fabricate recess light boxes | 16 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 702-14-02-L 02 | Install recess light boxes | 12 | 11/25/24 | 11/26/24 | 12.0h | : | |
| 702-14-02-L 03 | Install overhead framing | 24 | 11/26/24 | 11/29/24 | 24.0h | : | |
| 702-14-02-L 04 | Install overhead perf | 16 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 702-14-02-L 05 | Brushed aluminum edging | 24 | 11/27/24 | 11/29/24 | 24.0h | : | |
| 702-14-03 | Finish Paneling - S | 112 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 702-14-03-L | Labor | 112 | 11/25/24 | 11/28/24 | 0.8w | : | |
| 702-14-03-L 01 | Install finish panels Fwd bulkhead | 32 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 702-14-03-L 02 | Install finish panels Fwd bulkhead | 32 | 11/27/24 | 11/28/24 | 16.0h | : | |
| 702-14-03-L 03 | Install cabin side perf STB | 48 | 11/25/24 | 11/27/24 | 24.0h | : | |
| 702-14-04 | Overhead - S | 92 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 702-14-04-L | Labor | 92 | 11/25/24 | 11/29/24 | 1.0w | : | |
| 702-14-04-L 01 | Fabricate recess light boxes | 16 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 702-14-04-L 02 | Install recess light boxes | 12 | 11/25/24 | 11/26/24 | 12.0h | : | |
| 702-14-04-L 03 | Install overhead framing | 24 | 11/26/24 | 11/29/24 | 24.0h | : | |
| 702-14-04-L 04 | Install overhead perf | 16 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 702-14-04-L 05 | Brushed aluminum edging | 24 | 11/27/24 | 11/29/24 | 24.0h | : | |
| 703 | Machinery room - MID | 112 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 703-14 | Marine Outfitting | 112 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 703-14-01 | Finish Paneling - P | 112 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 703-14-01-L | Labor | 112 | 11/25/24 | 12/03/24 | 1.4w | : | |
| 703-14-01-L 01 | Install finish panels Fwd bulkhead | 32 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 703-14-01-L 02 | Install finish panels Fwd bulkhead | 32 | 11/27/24 | 11/28/24 | 16.0h | : | |
| 703-14-01-L 03 | Install cabin side pref port | 48 | 11/29/24 | 12/03/24 | 24.0h | : | |
| 710 | Garage | 412 | 11/25/24 | 12/13/24 | 3.0w | : | |
| 710-14 | Marine Outfitting | 412 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 710-14-01 | Insulation - P | 48 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 710-14-01-L | Labor | 48 | 11/25/24 | 11/26/24 | 0.4w | : | |
| 710-14-01-L 01 | Install Fire insulation to aft bulkhead | 8 | 11/25/24 | 11/25/24 | 8.0h | : | |
| 710-14-01-L 02 | Install mass damping to aft Bulkhead | 8 | 11/25/24 | 11/25/24 | 8.0h | : | |
| 710-14-01-L 03 | Install Sound insulation to aft bulkhead | 8 | 11/25/24 | 11/25/24 | 8.0h | : | |
| 710-14-01-L 04 | Install insulation to ship sides (P) | 8 | 11/26/24 | 11/26/24 | 8.0h | : | |
| 710-14-01-L 05 | Install mass damping to overhead | 8 | 11/25/24 | 11/25/24 | 8.0h | : | |
| 710-14-01-L 06 | Install Sound insulation to overhead | 8 | 11/26/24 | 11/26/24 | 8.0h | : | |
| 710-14-02 | Framing - P | 160 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 710-14-02-L | Labor | 160 | 11/25/24 | 12/06/24 | 2.0w | : | |
| 710-14-02-L 01 | Frame out Fwd bulkhead | 48 | 11/25/24 | 11/27/24 | 24.0h | : | |
| 710-14-02-L 02 | Frame out Aft bulkhead | 48 | 11/28/24 | 12/02/24 | 24.0h | : | |
| 710-14-02-L 03 | Frame out Cabin Side (P) | 64 | 12/03/24 | 12/06/24 | 32.0h | : | |
| 710-14-03 | Finish Paneling - P | 112 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 710-14-03-L | Labor | 112 | 11/25/24 | 12/03/24 | 1.4w | : | |
| 710-14-03-L 01 | Install finish panels Fwd bulkhead | 32 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 710-14-03-L 02 | Install finish panels Fwd bulkhead | 32 | 11/27/24 | 11/28/24 | 16.0h | : | |
| 710-14-03-L 03 | Install cabin side pref port | 48 | 11/29/24 | 12/03/24 | 24.0h | : | |
| 710-14-04 | Overhead - P | 92 | 11/25/24 | 12/13/24 | 120.0h | : | |
| 710-14-04-L | Labor | 92 | 11/25/24 | 11/29/24 | 1.0w | : | |
| 710-14-04-L 01 | Fabricate recess light boxes | 16 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 710-14-04-L 02 | Install recess light boxes | 12 | 11/25/24 | 11/26/24 | 12.0h | : | |
| 710-14-04-L 03 | Install overhead framing | 24 | 11/26/24 | 11/29/24 | 24.0h | : | |
| 710-14-04-L 04 | Install overhead perf | 16 | 11/25/24 | 11/26/24 | 16.0h | : | |
| 710-14-04-L 05 | Brushed aluminum edging | 24 | 11/27/24 | 11/29/24 | 24.0h | : | |
| 8 | EXTERIOR | 1,744 | 11/26/24 | 12/13/24 | 33.2w | : | |
| 802 | Main deck - FWD | 184 | 12/11/24 | 12/13/24 | 4.6w | : | |
| 802-14 | Marine Outfitting | 184 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 802-14-01 | Patio door | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 802-14-01-L | Labor | 48 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 802-14-01-L 01 | Install door (P) | 24 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 802-14-01-L 02 | Install door (S) | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 802-14-02 | Chain Locker Hatch | 64 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 802-14-02-L | Labor | 64 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 802-14-02-L 01 | Assemble chain locker deck hatch | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 802-14-02-L 02 | Dry fit chain locker hatch | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 802-14-02-L 03 | Install chain locker hatch | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 802-14-03 | Stairways' | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 802-14-03-L | Labor | 32 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 802-14-03-L 01 | Install Stairway P | 16 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 802-14-03-L 02 | Install Stairway S | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 802-14-04 | Deck Fittings | 40 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 802-14-04-L | Labor | 40 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 802-14-04-L 01 | Install Bollard cleats | 16 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 802-14-04-L 02 | Install Fair leads | 16 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 802-14-04-L 03 | Install freshwater Deck fill | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 803 | Main deck Walkway - Port | 36 | 12/11/24 | 12/13/24 | 1.7w | : | |
| 803-14 | Marine Outfitting | 36 | 12/11/24 | 12/13/24 | 17.0h | : | |
| 803-14-01 | Stairway | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 803-14-01-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 803-14-01-L 01 | Install Stairway A | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 803-14-02 | Deck fittings | 20 | 12/11/24 | 12/13/24 | 17.0h | : | |
| 803-14-02-L | Labor | 20 | 12/11/24 | 12/13/24 | 0.3w | : | |
| 803-14-02-L 01 | Install Bollard cleats | 16 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 803-14-02-L 02 | Install fuel deck fill | 4 | 12/12/24 | 12/13/24 | 4.0h | : | |
| 804 | Main deck Walkway - STBD | 20 | 12/12/24 | 12/13/24 | 1.7w | : | |
| 804-14 | Marine Outfitting | 20 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 804-14-01 | Deck fittings | 20 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 804-14-01-L | Labor | 20 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 804-14-01-L 01 | Install Bollard cleats | 16 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 804-14-01-L 02 | Deck fill (freshwater) | 4 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 805 | Main deck - Aft | 84 | 12/11/24 | 12/13/24 | 4.0w | : | |
| 805-14 | Marine Outfitting | 84 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 805-14-01 | Deck fittings | 28 | 12/11/24 | 12/13/24 | 20.0h | : | |
| 805-14-01-L | Labor | 28 | 12/11/24 | 12/13/24 | 0.5w | : | |
| 805-14-01-L 01 | Install Bollard cleats | 16 | 12/11/24 | 12/12/24 | 8.0h | : | |
| 805-14-01-L 02 | Install deck fills | 4 | 12/12/24 | 12/12/24 | 4.0h | : | |
| 805-14-01-L 03 | Transom fairleads | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 805-14-02 | Doors | 48 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 805-14-02-L | Labor | 48 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 805-14-02-L 01 | Install Galley door | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 805-14-02-L 02 | Install aft salon door | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 805-14-03 | Furniture | 8 | 12/13/24 | 12/13/24 | 6.0h | : | |
| 805-14-03-L | Labor | 8 | 12/13/24 | 12/13/24 | 0.1w | : | |
| 805-14-03-L 01 | Install table | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 806 | Transom | 444 | 12/02/24 | 12/13/24 | 2.5w | : | |
| 806-09 | Carpentry | 32 | 12/10/24 | 12/13/24 | 100.0h | : | |
| 806-09-04 | Teak Stairway (P) | 16 | 12/10/24 | 12/13/24 | 30.0h | : | |
| 806-09-04-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 806-09-04-L 01 | Install Stairway A | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-09-05 | Teak Stairway (S) | 16 | 12/10/24 | 12/13/24 | 30.0h | : | |
| 806-09-05-L | Labor | 16 | 12/13/24 | 12/13/24 | 0.2w | : | |
| 806-09-05-L 01 | Install Stairway A | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-14 | Marine Outfitting | 412 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 806-14-01 | Insulation - P | 48 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 806-14-01-L | Labor | 48 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 806-14-01-L 01 | Install Fire insulation to aft bulkhead | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-14-01-L 02 | Install mass damping to aft Bulkhead | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-14-01-L 03 | Install Sound insulation to aft bulkhead | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 806-14-01-L 04 | Install insulation to ship sides (P) | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-14-01-L 05 | Install mass damping to overhead | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 806-14-01-L 06 | Install Sound insulation to overhead | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 806-14-02 | Framing - P | 160 | 12/02/24 | 12/13/24 | 80.0h | : | |
| 806-14-02-L | Labor | 160 | 12/02/24 | 12/13/24 | 2.0w | : | |
| 806-14-02-L 01 | Frame out Fwd bulkhead | 48 | 12/02/24 | 12/04/24 | 24.0h | : | |
| 806-14-02-L 02 | Frame out Aft bulkhead | 48 | 12/05/24 | 12/09/24 | 24.0h | : | |
| 806-14-02-L 03 | Frame out Cabin Side (P) | 64 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 806-14-03 | Finish Paneling - P | 112 | 12/05/24 | 12/13/24 | 56.0h | : | |
| 806-14-03-L | Labor | 112 | 12/05/24 | 12/13/24 | 1.4w | : | |
| 806-14-03-L 01 | Install finish panels Fwd bulkhead | 32 | 12/05/24 | 12/06/24 | 16.0h | : | |
| 806-14-03-L 02 | Install finish panels Fwd bulkhead | 32 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 806-14-03-L 03 | Install cabin side pref port | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 806-14-04 | Overhead - P | 92 | 12/06/24 | 12/13/24 | 44.0h | : | |
| 806-14-04-L | Labor | 92 | 12/09/24 | 12/13/24 | 1.0w | : | |
| 806-14-04-L 01 | Fabricate recess light boxes | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 806-14-04-L 02 | Install recess light boxes | 12 | 12/09/24 | 12/10/24 | 12.0h | : | |
| 806-14-04-L 03 | Install overhead framing | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 806-14-04-L 04 | Install overhead perf | 16 | 12/09/24 | 12/10/24 | 16.0h | : | |
| 806-14-04-L 05 | Brushed aluminum edging | 24 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 807 | Beach Club | 24 | 12/12/24 | 12/13/24 | 1.6w | : | |
| 807-14 | Marine Outfitting | 24 | 12/12/24 | 12/13/24 | 24.0h | : | |
| 807-14-02 | Deck Fittings | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 807-14-02-L | Labor | 24 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 807-14-02-L 01 | Install Bollard cleats | 16 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 807-14-02-L 02 | Install swim ladder mounts | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 808 | Swim platform | 216 | 12/12/24 | 12/13/24 | 2.4w | : | |
| 808-14 | Marine Outfitting | 216 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01 | Hatches | 192 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L | Labor | 192 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 808-14-01-L 01 | Assemble engine room hatch (P) | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L 02 | Assemble engine room hatch (S) | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L 03 | Assemble storage locker deck hatch | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L 04 | Dry fit engine room hatch (P) | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L 05 | Dry fit engine room hatch (S) | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L 06 | Dry fit storage locker hatch | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 808-14-01-L 07 | Install engine room hatch (P) | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 808-14-01-L 08 | Install engine room hatch (S) | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 808-14-01-L 09 | Install storage locker hatch | 16 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 808-14-02 | Deck Fittings | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 808-14-02-L | Labor | 24 | 12/12/24 | 12/13/24 | 0.3w | : | |
| 808-14-02-L 01 | Install Bollard cleats | 16 | 12/12/24 | 12/13/24 | 8.0h | : | |
| 808-14-02-L 02 | Install swim ladder mounts | 8 | 12/13/24 | 12/13/24 | 4.0h | : | |
| 815 | Flybridge deck | 16 | 12/12/24 | 12/13/24 | 6.3w | : | |
| 815-14 | Marine Outfitting | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 815-14-01 | Furniture | 16 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 815-14-01-L | Labor | 16 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 815-14-01-L 01 | Install table | 8 | 12/12/24 | 12/12/24 | 8.0h | : | |
| 815-14-01-L 02 | Install bar stools | 8 | 12/13/24 | 12/13/24 | 8.0h | : | |
| 816 | Hardtop | 80 | 12/09/24 | 12/13/24 | 2.8w | : | |
| 816-14 | Marine Outfitting | 80 | 12/09/24 | 12/13/24 | 33.0h | : | |
| 816-14-01 | Furniture | 80 | 12/09/24 | 12/13/24 | 33.0h | : | |
| 816-14-01-L | Labor | 80 | 12/12/24 | 12/13/24 | 0.4w | : | |
| 816-14-01-L 01 | Attached side stanchions to hardtop | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 816-14-01-L 02 | Dry fit hardtop | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 816-14-01-L 03 | Final install hardtop | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 820 | Windows/portlights | 640 | 11/26/24 | 12/13/24 | 2.8w | : | |
| 820-14 | Marine Outfitting | 640 | 11/26/24 | 12/13/24 | 112.0h | : | |
| 820-14-01 | Portlights | 48 | 12/11/24 | 12/13/24 | 24.0h | : | |
| 820-14-01-L | Labor | 48 | 12/11/24 | 12/13/24 | 0.6w | : | |
| 820-14-01-L 01 | Install port hull windows | 24 | 12/11/24 | 12/12/24 | 12.0h | : | |
| 820-14-01-L 02 | Install STB hull windows | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 820-14-02 | Hull windows | 352 | 11/26/24 | 12/13/24 | 112.0h | : | |
| 820-14-02-L | Labor | 352 | 11/26/24 | 12/13/24 | 2.8w | : | |
| 820-14-02-L 01 | Dry-fit hull windows (P) | 80 | 11/26/24 | 12/02/24 | 40.0h | : | |
| 820-14-02-L 02 | Dry-fit hull windows (S) | 80 | 12/03/24 | 12/09/24 | 40.0h | : | |
| 820-14-02-L 03 | Apply sika-flex to window (P) | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 820-14-02-L 04 | Apply sika-flex to window (S) | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 820-14-02-L 05 | Install hull windows (P) | 64 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 820-14-02-L 06 | Install hull windows (S) | 64 | 12/10/24 | 12/13/24 | 32.0h | : | |
| 820-14-03 | Main Deck windows | 240 | 12/06/24 | 12/13/24 | 44.0h | : | |
| 820-14-03-L | Labor | 240 | 12/06/24 | 12/13/24 | 1.1w | : | |
| 820-14-03-L 01 | Dry-fit main deck side windows (P) | 32 | 12/06/24 | 12/10/24 | 16.0h | : | |
| 820-14-03-L 02 | Dry-fit main deck side windows (S) | 32 | 12/10/24 | 12/12/24 | 16.0h | : | |
| 820-14-03-L 03 | Dry-fit main deck side windows (A) | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 820-14-03-L 04 | Dry-fit main deck side windows (P) | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| 820-14-03-L 05 | Install main deck side windows (P) | 32 | 12/06/24 | 12/10/24 | 16.0h | : | |
| 820-14-03-L 06 | Install main deck side windows (S) | 32 | 12/10/24 | 12/12/24 | 16.0h | : | |
| 820-14-03-L 07 | Install main deck side windows (A) | 24 | 12/12/24 | 12/13/24 | 12.0h | : | |
| 820-14-03-L 08 | Install main deck side windows (P) | 32 | 12/12/24 | 12/13/24 | 16.0h | : | |
| | |
| ******** | ****************************** | ******** | *********** | *********** | ********** | | *********** |