| 1.1 Project Budgets | |
| 700. Mechanical Spaces | |
| Project Job Baselines | |
| 08/18/26 | |
| Code | Job Assignment | Duration | Labor Hrs. | Start Date | Finish Date | : | Comments |
| 7 | MECHANICAL SPACES | 3w | 2,252 | 07/29/26 | 08/18/26 | : | |
| 701 | Chain locker | 3w | 184 | 07/29/26 | 08/18/26 | : | |
| 701-12 | Electrical | 16h | 24 | 08/17/26 | 08/18/26 | : | |
| 701-12-01 | Rough-in circuits | 16h | 16 | 08/17/26 | 08/18/26 | : | |
| 701-12-02 | Install/Connect | 8h | 8 | 08/18/26 | 08/18/26 | : | |
| 701-14 | Marine Outfitting | 120h | 160 | 07/29/26 | 08/18/26 | : | |
| 701-14-01 | Chain bin (P) | 120h | 160 | 07/29/26 | 08/18/26 | : | |
| 702 | Machinery room - FWD | 3w | 452 | 07/29/26 | 08/18/26 | : | |
| 702-12 | Electrical | 28h | 44 | 08/13/26 | 08/18/26 | : | |
| 702-12-01 | Rough-in circuits | 28h | 28 | 08/13/26 | 08/18/26 | : | |
| 702-12-02 | Install/Connect | 16h | 16 | 08/17/26 | 08/18/26 | : | |
| 702-14 | Marine Outfitting | 120h | 408 | 07/29/26 | 08/18/26 | : | |
| 702-14-01 | Finish Paneling - P | 120h | 112 | 07/29/26 | 08/18/26 | : | |
| 702-14-02 | Overhead - P | 120h | 92 | 07/29/26 | 08/18/26 | : | |
| 702-14-03 | Finish Paneling - S | 120h | 112 | 07/29/26 | 08/18/26 | : | |
| 702-14-04 | Overhead - S | 120h | 92 | 07/29/26 | 08/18/26 | : | |
| 703 | Machinery room - MID | 3w | 156 | 07/29/26 | 08/18/26 | : | |
| 703-12 | Electrical | 28h | 44 | 08/13/26 | 08/18/26 | : | |
| 703-12-01 | Rough-in circuits | 28h | 28 | 08/13/26 | 08/18/26 | : | |
| 703-12-02 | Install/Connect | 16h | 16 | 08/17/26 | 08/18/26 | : | |
| 703-14 | Marine Outfitting | 120h | 112 | 07/29/26 | 08/18/26 | : | |
| 703-14-01 | Finish Paneling - P | 120h | 112 | 07/29/26 | 08/18/26 | : | |
| 710 | Garage | 3w | 1,000 | 07/29/26 | 08/18/26 | : | |
| 710-11 | Mechanical | 120h | 456 | 07/29/26 | 08/18/26 | : | |
| 710-11-01 | Garage doors | 120h | 312 | 07/29/26 | 08/18/26 | : | |
| 710-11-02 | Crane | 120h | 72 | 07/29/26 | 08/18/26 | : | |
| 710-11-03 | Passerell gangway | 120h | 72 | 07/29/26 | 08/18/26 | : | |
| 710-12 | Electrical | 28h | 132 | 08/13/26 | 08/18/26 | : | |
| 710-12-01 | Rough-in circuits | 28h | 84 | 08/13/26 | 08/18/26 | : | |
| 710-12-03 | Install/Connect | 16h | 48 | 08/17/26 | 08/18/26 | : | |
| 710-14 | Marine Outfitting | 120h | 412 | 07/29/26 | 08/18/26 | : | |
| 710-14-01 | Insulation - P | 120h | 48 | 07/29/26 | 08/18/26 | : | |
| 710-14-02 | Framing - P | 120h | 160 | 07/29/26 | 08/18/26 | : | |
| 710-14-03 | Finish Paneling - P | 120h | 112 | 07/29/26 | 08/18/26 | : | |
| 710-14-04 | Overhead - P | 120h | 92 | 07/29/26 | 08/18/26 | : | |
| 711 | Lazzerette | 3w | 460 | 07/29/26 | 08/18/26 | : | |
| 711-11 | Mechanical | 120h | 312 | 07/29/26 | 08/18/26 | : | |
| 711-11-01 | Lazzerette door | 120h | 312 | 07/29/26 | 08/18/26 | : | |
| 711-12 | Electrical | 76h | 148 | 08/05/26 | 08/18/26 | : | |
| 711-12-01 | Lazzerette door | 72h | 72 | 08/06/26 | 08/18/26 | : | |
| 711-12-02 | Install/Connect | 76h | 76 | 08/05/26 | 08/18/26 | : | |
| | |
| ******* | ****************************** | ******* | ******* | ********** | ********** | | *********************************** |
|
|
|